Purple Line Extension
Section 1 Construction Community Meeting July 18, 2019
1
Purple Line Extension Section 1 Construction Community Meeting - - PowerPoint PPT Presentation
Purple Line Extension Section 1 Construction Community Meeting July 18, 2019 1 Agenda Section 1 Project Overview MOW Building Tunneling Station Updates Eat Shop Play Business Interruption Fund Questions
Section 1 Construction Community Meeting July 18, 2019
1
Section 1
2
Project Alignment
3
4 *Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Forecasted ed S Sched edul ule Se Sect ction
Section 1 Section 2 Section 3
Lengt gth
3.92 Miles 2.59 Miles 2.56 Miles
New Sta tati tions
Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital
Pre re-Cons nstruction
Act ctivities
2014 – 2015 2016 – 2018 2018 – 2019
Constr structi tion
2015 – 2023 2018 – 2025 2019 – 2027
Oper eratio ions
2023 2025 2027
Section 1 Alignment
5
6
Main intenance F Facil cilit ity
Curre rrent W t Work
7
Installing art work on the façade
Schedule
8 *As of July 2019, subject to change
9
Soyeon and Elsie break through at Wilshire/Western
10
TBMs being disassembled for transport back to Wilshire/La Brea Station
11
12
Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St
Schedule
13 *As of July 2019, subject to change
Station Construction
Constructing the interior walls Assembling TBM ring on the west end
Beginning July 2019, STS will restore bus pads at the following locations:
Example of a Bus Pad along Wilshire Bl
Bus Pads and Water Crossings
Antenna
the underground station’s communications room (at the east end of the Wilshire/La Brea Station)
agencies’ other local and mountain top radio transmitter/receiver sites
requires for all users:
underground stations and tunnels
Rendering of Antenna
18
19
Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west
*As of July 2019, subject to change 20
Station Construction
Installing electrical conduit
Start date September 2019*
closure of Orange Grove Av just south of Wilshire Bl for the duration of the project
excavation of appendage structures and successor activities
the relevant city agencies has begun
*As of July 2019, subject to change
Closure area
Concrete and Rebar – Ongoing 2019
anticipated to continue through 2019
control on the south side of Wilshire Bl from Orange Grove Av to Ogden Dr
(9am – 3:30pm; 8pm - 6am)
construction notices and briefings
Concrete work shown from the street level at Wilshire/La Brea. Concrete is being pumped underground from the street level. Similar work will be done at the Wilshire/Fairfax Station.
23
Tunnel Investigation, Ongoing through September 2019
24
Approximate work locations at Wilshire/Crescent Heights.
will be installed throughout Summer 2019
are anticipated to continue in advance of the tunneling from the Wilshire/Fairfax station
required as investigation continues
available in future construction notices
August 2019
STS will be investigating the locations of two abandoned oil wells
8pm to 6am
along Wilshire Bl will be in place to support investigative drilling
Approximate work location at Wilshire Bl/ La Jolla Av
26
27
Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr
*As of July 2019, subject to change 28
Intermittent Daily Gale Closure – North of Wilshire Bl
closed Monday to Saturday, 6am to 6pm
measure due to high volumes of ingress/egress from the property
maintained from San Vicente Bl
until 10pm
29
Gale Dr from north of Wilshire Bl
30
Removing stockpiled excavation material
Instrumentation Work & Street Maintenance
When hen: Ongoi
2019 Instr trumen entati tation w work on n Wils lshire B Bl a l and nd La a Cien eneg ega B a Bl
Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Str treet M eet Mai ainten tenan ance, D Dew ewater atering W Wel ell Mai ainten tenan ance, an and Uti tility W Work on
Wil ilsh shir ire B Bl
Bl and side streets during off-peak hours (non-rush hour)
31
Example of instrumentation drilling
City of Los Angeles
When hen: Ongoi
2019 Construction activities on Wilshire Bl between Fairfax Av and San Vicente Bl may require traffic control in the City of Beverly Hills. Work includes, but is not limited to:
Information on this work and the required traffic control will be available via construction notices.
32
33
Station Names will reflect the following principles
ansit s t system tem c contex text: t: names will reflect the property’s location, relative to the entire transit system, and not duplicated elsewhere.
Proper perty ar area: ea: provide specific information about the property’s location relative to the surrounding area.
borhood
identity: acknowledge the communities and neighborhoods serviced by the station and stops.
Simplic icity: names will be short, easily recognizable and fit for signage and mapping.
34
Metro staff originally developed a set of geographically-based names for the Section 1 Stations and are now seeking community input on those names. Submit your proposals at metro.net/purple
35
3875 Wilshire Bl, Suite 1401 Los Angeles, CA 90010 (562)547-8978
36
5115 Wilshire Bl, Los Angeles, CA 90036 (877) 224-0954
225 N Canon Dr Beverly Hills, CA 90210 (310) 860-7800
37
Helpin ing l g local bu busin siness sses a s as s we bu buil ild. Purp rple L Lin ine Ext xtensio ion U Update
> Financial assistance to small “mom and pop” businesses with 25 or fewer full-time employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > Businesses are eligible for up to $50,000 per impact year
> To date, 936 grants have been awarded with a total value of more than $22.4 million along all three project areas > Crenshaw/LAX Transit Project > Regional Connector, Little Tokyo area > Purple Line Extension Section 1 and Section 2 > February 2019 Metro’s Board of Directors authorized the expansion of the BIF to Section 3 of the Purple Line Extension
> Purple L Line e Ex Exte tension Sect Section 1 1 (as of 7/12 /12/19) > BIF Grants Awarded: 198 > BIF Grant Amount Awarded: $5,142,660.09 > Number of small businesses awarded: 76 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > 213.739.2999
> Purple L Line e Ex Exte tension Sect Section 2 2 (as of 7/12 /12/19) > BIF Grants Awarded: 50 > BIF Grant Amount Awarded: $1,393,595.28 > Number of small businesses awarded: 30 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > 213.739.2999
> Purp rple L Lin ine Ext xtensio ion, S , Sectio ion 3 3 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999
43
44
Section 1
45
Get the latest updates from Sections 1, 2, and 3 of the Purple Line Extension during lunch! Wednesday, July 24, 2019 12pm - 1pm Link to the online meeting: Webex Access Code: 804 430 649 | Password: Purple Join by phone: 1-650-479-3207 (toll-free)
Link to the online meeting: Webex Access Code: 804 613 256 | Password: Purple Join by phone: 1-650-479-3207 (toll-free)
46
Beverly Hills
47