Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo - - PowerPoint PPT Presentation

purple line extension
SMART_READER_LITE
LIVE PREVIEW

Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo - - PowerPoint PPT Presentation

Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations March 13, 2019 1 Agenda Project oject Overvi rview ew Section ion 2 Pre-Con onst struction uction Upda dates tes Wilshire/Rodeo Station


slide-1
SLIDE 1

Purple Line Extension

Wilshire/La Cienega and Wilshire/Rodeo Stations March 13, 2019

1

slide-2
SLIDE 2

Agenda

2

  • Project
  • ject Overvi

rview ew

  • Section

ion 1 Constr nstruc ucti tion

  • n Upda

dates tes

  • Wilshire/La Cienega Station
  • Excavation
  • Fossils
  • Section

ion 2 Pre-Con

  • nst

struction uction Upda dates tes

  • Wilshire/Rodeo Station
  • Staging Yard Demolition
  • Geotechnical Investigation
  • N. Canon Closure
  • City Utilities
  • MOA Update
  • Mitigation Measures
  • Business

ness Inter terru rupt ption

  • n Fund
  • Eat

at Shop p Play ay #Bever verly lyHill ills

slide-3
SLIDE 3

Purple Line Extension

Project Alignment

3

slide-4
SLIDE 4

Sections 1, 2 & 3 Status

4 *Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Section 1 Section 2 Section 3 3.92 Miles 2.59 Miles 2.56 Miles Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital 2014 – 2015 2016 – 2018 2018 – 2019 2015 – 2023 2018 – 2025 2019 – 2027 2023 2025 2027

slide-5
SLIDE 5

Section 1

Wilshire/La Cienega Station

5

slide-6
SLIDE 6

Wilshire/La Cienega Station Box

6

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

slide-7
SLIDE 7

Wilshire/La Cienega Station

*As of March 2019, subject to change 7

slide-8
SLIDE 8

Wilshire/La Cienega

Construction Staging Yards

Typical Activities/Equipment:

  • Excavation
  • Steel work
  • Deliveries
  • Hauling
  • Typical hours are 6am – 11pm;

yard use is permitted 24/7

  • All noise levels must remain in

compliance with MOA and FEIR requirements

8

Excavator in the La Cienega shaft

slide-9
SLIDE 9

Wilshire/Gale

Intermittent Daily Gale Closure – North of Wilshire Bl

  • Gale Dr will be intermittently

closed Monday to Friday, 6am to 6pm, and Saturday 6am to 6pm

  • This closure is a public safety

measure due to high volumes of ingress/egress from the property

  • Access to N Gale Dr will be

maintained from San Vicente Bl

9

Gale Dr from north of Wilshire Bl

slide-10
SLIDE 10

Wilshire/La Cienega

10

Installing braces inside Wilshire/La Cienega Station

slide-11
SLIDE 11

Wilshire/La Cienega – Upcoming Work

Instrumentation Work & Street Maintenance

When: Ongoing ing through gh 2019 Instrume ument ntation ion work on Wilshire ire Bl and La Cienega ga Bl

  • Intermittent lane reductions on

Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Street Maintenanc nce, e, Dewatering ing Well Maintenanc nce, e, and Utility ty Work on Wilshire ire Bl Bl

  • Intermittent lane reductions on Wilshire

Bl and side streets during off-peak hours (non-rush hour)

11

Example of instrumentation drilling

slide-12
SLIDE 12

Staging Yard Mitigation

La Cienega ga Yard

  • Active ventilation fans and fan

lines were wrapped with sound blankets

  • 24’ steel frame placed around

the ventilation system with sound blankets

  • Sound blankets surrounding

the ventilation system have been upgraded allowing for more sound absorption

12

Gale Yard

  • 14’ fences with sound blankets placed

around the crane

  • Applied an acoustic dampening material

to the 895 crane engine enclosure

  • Added a muffling panel on the exhaust

door and engine compartment door

  • Relocated slew alarm
  • Added a noise barrier rubber mat to the

lower engine panels

  • Acoustic plate under mounted on the

crane counterweight

  • Adjusted the crane start up schedule,

when possible

  • Started closing the gate, when feasible
  • Installed noise dampening louvre adjacent

to crane motor

slide-13
SLIDE 13

Section 2

Wilshire/Rodeo Station

13

slide-14
SLIDE 14

Wilshire/Rodeo Station

View from sidewalk

14

slide-15
SLIDE 15

Tunnel Boring Machines

Art and Naming Contest, Submit by Friday

15

slide-16
SLIDE 16

Purple Line Extension

Section 2 Alignment

16

slide-17
SLIDE 17

Wilshire/Rodeo Station Box

Station Box

17

Rendering shows length of the underground station box

  • n Wilshire Bl from Canon Dr to Beverly Dr
slide-18
SLIDE 18

Wilshire/Rodeo Station Schedule

*As of February 2019, subject to change. Pending Council approval. 18

slide-19
SLIDE 19

Geotechnical Investigations

Seismic Boring Study – Round 2

  • Additional borings to investigate and identify subsurface conditions
  • Started October 29, 2018. No work during Holiday Moratorium.
  • Work resumed January 14, 2019
  • Estimated completion: March 13, 2019*
  • Work Hours: 8pm – 6am

19

FI-B-18 FI-B-17 FI-B-16 FI-B-15 FI-B-14 FI-B-13 FI-B-12 FI-B-11 FI-B-3A FI-B-2A

Green = complete, Yellow = underway

slide-20
SLIDE 20
  • Prep work began December 2018
  • Installation to be completed in March

2019*

  • Work Hours: 8am – 6pm
  • Sound wall installed using soldier

piles and prefabricated noise panels

  • Sound Wall: 20 feet
  • Public Information Graphics have

been installed

20

Wilshire/Reeves Staging Yard

Sound Wall Installation

Draft Stag aging ng Yard rd layout

  • ut

*Subject to change

slide-21
SLIDE 21
  • Wilshire Bl and Reeves Dr sidewalks

along the Reeves Staging Yard will be closed for repair

  • Southbound lane on Reeves Dr from

Wilshire Bl to Charleville Bl will be closed

  • Alley behind the former Ace Gallery will

be closed

  • March 13-15, 2019*
  • Sidewalk and street closures will be in

place only on Thursday, 3/14/2019 and Friday, 3/15/2019

  • Work Hours: 9am – 4pm

21

Temporary Sidewalk Closure

Wilshire/Reeves Staging Yard

*Subject to change

slide-22
SLIDE 22

Demolition of N. Canon Properties

Site Addres dress: s: 9383-9393 and 9395-9399 Wilshire Bl

  • Estimated duration of demolition activities: 5 weeks
  • Work start date: February 19, 2019
  • Estimated completion date: late-March, 2019*
  • Two lanes in each direction will be maintained for work on Wilshire Bl
  • Work hours: Monday – Friday, 8am-6pm
  • Traffic control hours: 9am-4pm

22 *Subject to change

slide-23
SLIDE 23
  • N. Canon Demolition Progress

23

  • Temporary fencing will be installed after completion of demolition
  • Installation of 20-foot sound walls around the perimeter of the staging yard will

begin in April 2019

slide-24
SLIDE 24

24

Ut Utility lity Po Potho tholing ling

Example of potholing for water line

  • Potholing work to identify existing

utilities below the street

  • Estimated Duration: 3-4 weeks
  • Anticipated Start Date: April 15, 2019*
  • Estimated Completion Date:

Mid-May, 2019*

  • Work Hours: Monday – Friday

9:00am – 4:00pm

  • Lane closures on Wilshire Blvd. and

adjoining streets will be required

  • Two lanes maintained in each direction.
  • Impacted properties will be notified in

advance of work starting

*Subject to change

slide-25
SLIDE 25

25

Water and Sewer Line Replacement

Anticip ipated ted Start Date: Mid-May 2019*

  • Sewer Replacement - 10 weeks
  • Water Line Replacement - 12 weeks
  • 22 weeks total

Work Hours: rs:

  • Weekdays: 9am – 4pm and 8pm – 7am
  • Weekends: 10am – 6pm (as needed)

Trenching for waterline placement Traffic c Controls:

  • ls:
  • Two lanes in each direction will be maintained

for day work on Wilshire Bl

  • One lane in each direction will be maintained

for night work

slide-26
SLIDE 26

Sewer Line Replacement

Stage 1: 5 d days

26

  • Work Hours: Monday-Friday, 9am-4pm
  • No left turn onto N Crescent Dr from
  • m Wilshire

re Bl Bl

  • No left turn onto Wilshire

ire Bl Bl from

  • m S Crescent Dr
slide-27
SLIDE 27

Sewer Line Replacement

Stage 2: 2: 5 days

27

  • Work Hours: Monday-Friday, 9am-4pm
slide-28
SLIDE 28

Sewer Line Replacement

Stage 3: 3: 5 days

28

  • Work Hours: Monday-Wednesday*, 9am-4pm
  • * Monday-Friday, 9am-4pm if N Canon Dr is closed
slide-29
SLIDE 29
  • N. Canon Drive Closure

Anticipated June 2019

29

slide-30
SLIDE 30
  • N. Canon Drive Closure

Piling Set-up

30

Example of construction area with piling set-up on the north side of Wilshire Bl

slide-31
SLIDE 31
  • N. C

. Canon non Dr Drive ve Cl Clos

  • sure

ure

Traffic Configuration

  • N. Canon Drive

Clifton Way Sound wall with art on Canon side and public information graphics on Wilshire side

  • Install before piling for a minimum of 2 years
  • New traffic signal at Clifton/ Crescent
  • Existing meters / valet spaces on Clifton Way

shift to the north

  • Maintain existing valet time periods
  • Relocate some meters on N. Canon Dr from

East to West side Pedestrian walkway

slide-32
SLIDE 32

Pile Drilling Installation

32

Pile installat ation ion include des:

  • Drill rig to drill holes
  • Crane to lift piles into holes
  • Truck to backfill holes
  • All work occurs behind K-rail

Schedul dule

  • Following utility relocation, anticipated to

start Q3 of 2019

  • Work Hours:
  • 7 days a week
  • 8:00am – 9:00pm, drilling
  • 9:00pm – 11:00pm, non-drilling
  • Work in certain areas restricted to

weekends

Example of piling work in Century City

*Dates subject to change

slide-33
SLIDE 33

33

Pile Drilling Installation

Example of progress on Constellation Bl

slide-34
SLIDE 34

Decking

34

Followi

  • wing

ng Piling: g: Anticip ipate ated d late 2019* 9*

  • Construction of a concrete deck, curb-to-

curb on Wilshire Bl

  • Decking will serve as the temporary street

surface

  • Work Hours:

rs: Full closures Friday night at 8pm through Monday mornings at 7am

  • Metro will work closely with first

responders on emergency access and safety

  • Additional activities under decking

closures: ground improvements, piling, temporary civil improvements Asphalt removal on Wilshire Bl near Detroit St Steel beams welding prior to concrete deck panel installation

*Dates subject to change

slide-35
SLIDE 35

Help lping g loca cal l bu busines esses ses as we bu build. Update te as o

  • f

f 3/8/19 19

slide-36
SLIDE 36

BIF Information and Eligibility

> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > To date, 855 grants have been awarded with a total value of more than $20.0 million along all three projects

slide-37
SLIDE 37

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion

  • n 1

> BIF Grants Awarded: 187 > BIF Grant Amount Awarded: $4,734,838.79 > Number of small businesses awarded: 72 > City of Beverly Hills only > BIF Grants Awarded: 33 > BIF Grant Amount Awarded: $877,061.20 > Number of small businesses awarded: 14 > BIF Business Advisor: Brian Lazo, PCR, 213.739.2999

slide-38
SLIDE 38

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion

  • n 2

> BIF Grants Awarded: 38 > BIF Grant Amount Awarded: $1,093,255.04 > Number of small businesses awarded: 24 > City of Beverly Hills only > BIF Grants Awarded: 35 > BIF Grant Amount Awarded: $1,042,703.15 > Number of small businesses awarded: 22 > BIF Business Advisor: Darrell Smith, PCR, 213.739.2999

slide-39
SLIDE 39

39

8383 Wilshire Blvd, Suite 50 Studio 71 Beverly Hills, CA 90210 323.366.7772

slide-40
SLIDE 40

Construction Updates on La Cienega and Rodeo Stations Wednesday, April 3 6:30pm – 8pm

Beverly Hills City Hall Municipal Gallery, 2nd Floor 455 N Rexford Dr Beverly Hills, CA 90210

2 hour free parking before 5pm Free after 5pm, no validation necessary

40

Next Construction Update

Beverly Hills

slide-41
SLIDE 41

Help Us Keep You Safe

41

Purp rple le Lin ine Ext xten ensio sion 24/7 Project Hotline - 213.922.6934 Email – purplelineext@metro.net On Metro ro Tra ransit See Something, Say Something 888-950-SAFE (7233) Constru ruct ction

  • n Safe

fety y Aware renes ness s Pro rogr gram Glyssa A. Robles, Community Relations Officer Email: roblesgl@metro.net Phone: 213.312.3156 Cit ity of f Beve verl rly y Hil ills PurpleLine@beverlyhills.org Public Works Customer Service: (310) 285-2467

slide-42
SLIDE 42

Stay in Touch

42