Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations April 3, 2019 1 Agenda Mural Update N. Portal Update Transportation Update 2 2 North Canon Artwork Mural to be installed on North side of Canon Wall


  1. Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations April 3, 2019 1

  2. Agenda • Mural Update • N. Portal Update • Transportation Update 2 2

  3. North Canon Artwork Mural to be installed on North side of Canon Wall • City Council (Study Session) – April 2 (Tomokazu Matsuyama) • Stakeholders and Fine Art Commissioners provide art direction • Artist will provide 3 concept designs • Stakeholders and Fine Art Commissioners select preferred concept • Preferred concept to Subway Liaison and full City Council for approval (May/June 2019) 3 Tomokazu Matsuyama

  4. North Portal Environmental Analysis MARCH MAY EARLY 2020 Request for Contract Final document Proposal Awarded by presented to City released City Council Council for decision APRIL 1 Year Request for Environmental Impact Proposal Due Report 4

  5. North Portal – Draft Alternatives 5

  6. Agenda Projec ect Overv rview ew • Section on 1 Cons nstruction on • Section on 2 Pre-Con onstruction on • Updat ates Updat ates Wilshire/La Cienega • Wilshire/Rodeo Station • Station Reeves Yard Sound Wall • Excavation N. Canon Staging Yard • Business ss Inte terrupti ption Fund • Demolition Eat S Shop P p Play # y #Beverl erlyHil ills • City Utilities • N. Canon Closure • Piling • Decking • 6

  7. Purple Line Extension Project Alignment 7

  8. Sections 1, 2 & 3 Status *Subject to change. The PLE project team is working to deliver the project consistent with Measure M Forecasted Schedule Section 1 Section 2 Section 3 Section 3.92 Miles 2.59 Miles 2.56 Miles Length Wilshire/La Brea Wilshire/Rodeo Westwood/UCLA New Stations Wilshire/Fairfax Century City/ Westwood/VA Wilshire/La Cienega Constellation Hospital 2014 – 2015 2016 – 2018 2018 – 2019 Pre-Construction Activities 2015 – 2023 2018 – 2025 2019 – 2027 Construction 2023 2025 2027 Operations 8

  9. Section 2 Wilshire/Rodeo Station 9

  10. Purple Line Extension Section 2 Alignment 10

  11. Wilshire/Rodeo Station Box Station Box Rendering shows length of the underground station box on Wilshire Bl from Canon Dr to Beverly Dr 11

  12. Wilshire/Rodeo Station Schedule *As of April 2019, subject to change. Pending Council approval. 12

  13. Wilshire/Reeves Staging Yard Sound Wall Installation *Subject to change Prep work began December 2018 • Sound wall installation to • be completed in April 2019* Work Hours: 8am – 6pm • Publi lic i inform ormation on g graph phics i installe led o on the Draf aft S Staging Y Yar ard l lay ayout exter erior o of the R Reev eeves es S Staging ng Y Yard 13

  14. Demolition of N. Canon Properties Complete Photo from demolition 14

  15. N. Canon Staging Yard *Subject to change • 20-foot sound wall around the staging yard will be installed to mitigate noise to adjacent properties and public ROW • Anticipated Start Date: mid-April • Completion Date: late May 2019 • Yard will contain: • Electrical substation • Ventilation system • Scrubbers • Water treatment plant • Equipment and material storage 15

  16. Utility Potholing *Subject to change Potholing work to identify • existing utilities below the street Estimated Duration: 3-4 weeks • Anticipated Start Date: April 8, 2019* • Estimated Completion Date: • early May, 2019* Work Hours: Monday – Friday • 9:00am – 4:00pm Lane closures on Wilshire Blvd. • and adjoining streets will be required Two lanes maintained in each • direction. Impacted properties will be notified • in advance of work starting Example of potholing for water line Canon/Wilshire Crescent/Wilshire Beverly/Wilshire Reeves/Wilshire (34 potholes) (20 potholes) (13 potholes) (15 potholes) 16

  17. Utility Potholing Stage 1: 1-2 days Work Hours: Monday-Friday, 9am - 4pm • Crosswalk closure on Wilshire Bl and Crescent Dr •

  18. Utility Potholing Stage 2: 1-2 days Work Hours: Monday-Friday, 9am - 4pm • Crosswalk closure on Wilshire Bl and N Canon Dr •

  19. Utility Potholing Stage 3: 1-2 days Work Hours: Monday-Friday, 9am - 4pm • No left turn on eastbound Wilshire Bl to • northbound N Canon Dr Crosswalk closure on Wilshire Bl and N Canon Dr •

  20. Utility Potholing Stage 4: 1-2 days Work Hours: Monday - Friday, 9am - 4pm •

  21. Utility Potholing Stage 5: 1-2 days Work Hours: Monday-Friday, 9am - 4pm • Flagger will be available for alley access •

  22. Water and Sewer Line Replacement Anti ticipat pated ed S Star tart D t Date: ate: Early May 2019* Sewer Replacement - 10 weeks • Water Line Replacement - 12 weeks • 22 weeks total • Work H k Hour urs: Weekdays: 9am – 4pm and 8pm – 7am • Weekends: 10am – 6pm (as needed) • Trenching for waterline placement Traffic C Control ols: s: Two lanes in each direction will be maintained • for day work on Wilshire Bl One lane in each direction will be maintained • for night work 22

  23. Sewer Line Replacement Stage 1: 5 days Work Hours: Monday - Friday, 9am - 4pm • No left turn onto N Crescent Dr from Wilshire Bl • No left turn onto Wilshire Bl from S Crescent Dr • 23

  24. Sewer Line Replacement Stage 2: 5 days Work Hours: Monday-Friday, 9am - 4pm • 24

  25. Sewer Line Replacement Stage 3: 5 days Work Hours: Monday-Wednesday*, 9am - 4pm • No left turns from Wilshire Bl to N Canon Dr • * Monday - Friday, 9am - 4pm if N Canon Dr is closed • 25

  26. N. Canon Drive Closure Anticipated Summer 2019* *Dates subject to change 26

  27. N. Canon Drive Closure Piling Set-up Example of construction area with piling set-up on the north side of Wilshire Bl 27

  28. Pile Drilling Installation *Dates subject to change Pile ile in installa llation in inclu ludes: Drill rig to drill holes • Crane to lift piles into holes • Truck to backfill holes • All work occurs behind K-rail • Sched hedule Following utility relocation, anticipated to • start Q3 of 2019 Work Hours: • 7 days a week • 8:00am – 9:00pm, drilling • 9:00pm – 11:00pm, non-drilling • Work in certain areas restricted to • weekends Example of piling work in Century City 28

  29. Pile Drilling Installation Example of progress on Constellation Bl 29

  30. Decking *Dates subject to change Following Pi Piling: A Anti ticipa pated ted l late ate 2019* Construction of a concrete deck, curb-to- • curb on Wilshire Bl Decking will serve as the temporary street • surface Work H k Hour urs: Full closures Friday night at • 8pm through Monday mornings at 7am Asphalt removal on Wilshire Bl near Metro will work closely with first • Detroit St responders on emergency access and safety Additional activities under decking • closures: ground improvements, piling, temporary civil improvements, dewatering system installation Steel beams welding prior to concrete deck 30 panel installation

  31. First/Last Mile Planning 31

  32. Complete Streets Plan • Streets designed and operated for all road users • More travel choices • Focus on first/last mile recommendations • Blueprint for transportation planning • Separate implementation process with neighborhood- level input 32

  33. Wilshire Blvd Streetscape Plan • Consistent, attractive streetscape • Safety for all road users • Placemaking • Tie improvements into Metro construction • Streetscape design guidelines (citywide template) • Allow for customization 33

  34. Gale Property Planning • First/last mile study of • Mobility hub options Gale staging yard • Drop off and pick up property • Micromobility (La Cienega station) • Shared mobility • Autonomous vehicle connections 34

  35. Metro’s First / Last Mile Plan • Recommendations for the Rodeo station • Analysis of barriers • Potential improvements • Crossings and connections • Signage and wayfinding • Safety and comfort • Allocation of street space by mode • Micromobility • Shared mobility 35

  36. How to Get Involved • Complete Streets Plan • Review the Draft Plan in Mid-April at: completestreets.beverlyhills.org Special TPC Meeting on May 8 th at 6:00 PM • • Anticipated City Council adoption in June • Wilshire Blvd Streetscape Plan / Gale Property Planning • Anticipated release of RFP in spring/summer • Community outreach in summer/fall • Metro’s First / Last Mile Plan: • Community outreach in spring (Farmer’s Market) • Anticipated plan completion in summer 36

  37. Section 1 Wilshire/La Cienega Station 37

  38. Wilshire/Gale Intermittent Daily Gale Closure – North of Wilshire Bl Gale Dr will be intermittently • closed Monday to Friday, 6am to 6pm, and Saturday 6am to 6pm This closure is a public safety • measure due to high volumes of ingress/egress from the property Access to N Gale Dr will be • maintained from San Vicente Gale Dr from north of Wilshire Bl Bl 38

  39. Wilshire/La Cienega Installing braces inside Wilshire/La Cienega Station 39

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.