Purple Line Extension
Wilshire/La Cienega and Wilshire/Rodeo Stations June 6, 2018
1
Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo - - PowerPoint PPT Presentation
Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations June 6, 2018 1 Agenda Project Overview Section 2 Pre-Construction Updates Wilshire/Rodeo Station Section 1 Construction Updates Seismic Boring Study
Wilshire/La Cienega and Wilshire/Rodeo Stations June 6, 2018
1
2
Closures
from Gale Yard
Demolition
Proposed Work Hours
Project Alignment
3
4
Forecasted Schedule Section
Section 1 Section 2 Section 3
Length
3.92 Miles 2.59 Miles 2.59 Miles
New Stations
Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital
Pre-Construction Activities
2014 – 2015 2016 – 2018 2018 – 2020
Construction
2015 – 2023 2018 – 2025 2019 – 2026
Operations
2023 2025 2026
*Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Wilshire/La Cienega Station
5
6
Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr
*As of June 2018, subject to change 7
Installing Sound Wall
8
Installing sound wall at Gale Staging Yard
Excavation Below Deck
9
Excavation under Wilshire Bl
Jet grouting example
10
Example of jet grouting from San Vicente Bl and Wilshire Bl
Upcoming Work, June 2018
11
Wilshire Bl (concrete barriers, fencing and noise mitigation blankets) will be removed anticipated Friday, June 15- Sunday, June 17 2018
Bl are anticipated to return at Hamilton Dr, Gale Dr And Tower Dr
zones and bus zones are planned to return to this area
Location of the current work zone on Wilshire Bl between La Cienega Bl and San Vicente Bl *Per City Staff Approval
Jet Grouting, West of La Cienega starting June 2018
12
between Carson Rd and La Cienega Bl (with concrete barriers, fencing and noise mitigation blankets) starting June 15 for 4 to 6 months
traffic in each direction.
Dr and Le Doux Rd at Wilshire Bl
weekend directional closures are anticipated.
Location of the new work zone that will be installed on Wilshire Bl between Carson Rd and La Cienega Bl *Per City Staff Approval
Weekend Directional Detours, June - Fall 2018
13
Above: Maps that show directional closures and the
Robertson Bl, Olympic Bl, La Cienega Bl *Pending City Staff Approval
Weekend Directional Closures, June - Fall 2018
14
d direc ecti tion
d directi ction
: Westbound Wilshire closed at La Cienega
*Pending City Staff Approval
Location/closures for utility work on Wilshire Bl
completed in mid-June
maintained to 8447 Wilshire and 8423 Wilshire
be installed for pedestrian safety
will be available in construction notices
15
Jet Grouting in City of Los Angeles
Location of upcoming closures on Wilshire Bl
between Gale and San Vicente
Center will be maintained
available in construction notices
directional closures
16
Replacement Parking Locations
One Hour r Free Parking ng available at:
garage from N Hamilton Dr
garage from S Tower Dr Additional replacement parking west of La Cienega Bl is being pursued Replacement parking locations
17
Starting June 17, 2018, Metro Bus Service will return or be installed at the following locations:
d Wilshire re Bl Bl: :
Cienega Bl in front of 8484 Wilshire Bl
d Wilshire re Bl Bl: :
Dr in front of 8370 Wilshire Bl
Bus Stop Update
18
Metro bus stop locations
und d Wilshire ire Bl Bl: :
4-5 months.
Implement on soundwall when k-rail is removed - Summer 2018
Wilshire/Rodeo Station
20 20
Section 2 Alignment
21
Station Box
Rendering shows length of the underground station box
22
*As of June 2018, subject to change. Pending Council approval. 23
is present
conditions including fault characteristics relative to the proposed Metro tunnels
Seismic Boring Study - Underway
FI-B-07 FI-B-06 FI-B-05 FI-B-04 FI-B-03 FI-B-02 FI-B-01 FI-B-08 FI-B-10 FI-B-09
24
Orange = AT&T Yellow= Gas
Stage 4b: Ending Fri., June 8 / Mon-Fri: 9am-4pm
and Gregory Way
26
Combined Traffic Control
simultaneously within work zone
February through August 2018
27
Current AUR work on Reeves Dr Excavating during AUR
28
Current AUR work on Reeves Dr
29
Placing gas line conduit End of day clean up
Combined Traffic Control * Dates subject to change
working hours
30
direction, from west of Beverly to east of Canon
removed from work zone
Stage 4: 34 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
31
No Left Turns: (if split phasing cannot be implemented)
Closed:
Stage 5: 5days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
32
Stage 6: 12 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
33
Stage 7: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
34
No Left Turns: EB Wilshire to NB Beverly
Stage 8: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
35
Bus Stop Relocations
20/720 WB/EB Wilshire Bl between Rexford Dr and Crescent Dr
20/720 WB/EB Wilshire Bl between Camden Dr and Rodeo Dr
36
Former Ace Gallery, future Construction Staging Yard
37
Reeves Mini Park
park rental fee for the closure of the park
park closure
Wilshire Blvd Beverly Drive Reeves Drive 9430 Wilshire Blvd Reeves Mini Park
Proposed temporary closure area
Former Ace Gallery
Site Addres dress: s: 943 430 0 Wilsh shir ire Bl Schedu edule le
Traffi ffic c Impacts cts
(intermittently throughout duration of demolition)
*Per City Council Approval
piles and prefabricated noise panels
Information Graphics
40
Example ample of prefa fab noise se panel els Draft Stag aging ng Yard rd layout
41
Noise Control
Metro
reduce noise levels at the site
42
Vibratio ion
will be minimized
can be implemented
Dust
construction equipment
43
Implement on soundwall when k-rail is removed - Summer 2018
Site Addres dress: s: 9383-9393 and 9395-9399 Wilshire Bl Sched edule ule
44
*Pending City Council Approval
Program (MMRP)
equipment, maintenance of construction equipment
for equipment emissions
wheel wash
45
Construction Air Quality Compliance
District (SCAQMD) Rule 403, the reduction and control of fugitive dust
California Air Resource Board (CARB)
compliance
46
Memorandum of Agreement
47
The purpose of the MOA is to:
– Minimize construction impacts in Beverly Hills through mitigation measures – Establish verification procedures and penalties for non-compliance – Ensure that the project complies with the standards and requirements of the City of Beverly Hills
Anticipated Schedule for Feedback and Approval
– Share MOA with Community after sharing with CC – City Council for introduction/review (6/19/2018) – City Council for consideration (7/19/2018)
FOCUS AREAS: Work Hours Traffic Noise Compliance Monitoring Business Mitigation Visual Mitigation
Overview
48
Pile – A long, slender column of steel, reinforced concrete or timber Piling g – The process by which a “pile” is drilled deep into the ground to support soil removal and building structures Piling is necessary to ensure strong, solid soil foundations that resist ground
the station box on Wilshire, from Beverly to Crescent
Set-up
49
Cross-section showing work zone and drill rig for pile installation
50
Piling on Wilshire between Gale and La Cienega
51
Drilling pile at La Cienega Staging Yard
Schedule
52
Weekd kdays ays and Weekend kends
Duration tion
*Pending City of Beverly Hills Council Approval
Overview
53
Decking king is a construction process that includes excavating the street and sidewalks, then replacing them with temporary concrete deck panels placed
the normal flow of traffic while maintaining pedestrian access to sidewalks and driveways
construction crews can continue working underground
54
Installation of deck beams across Wilshire at Tower
55
Laying and welding deck beams across Wilshire and Gale
Schedule
56
Pro roposed
rk Hours rs
Dura ration
*Pending City of Beverly Hills Council Approval
57
Wilshire traffic set up during the weeks in between decking
*Pending City of Beverly Hills Council Approval
58
from Thanksgiving to New Years
Overview
59
Appendage work extends off Wilshire into Canon and Beverly. This work will include piling and decking to shorter depths than the underground station. Work will take place over weekend closures and is anticipated for 2020. Anticip icipated ated Work Hours
Loca cations tions
*Pending City of Beverly Hills Council Approval
Overview
60
Jet t Gro routi uting ng is a construction process by which a cement-soil mixture is injected into the ground at high velocity. Jet Grouting improves soil strength and permeability. Propos posed ed Work rk Ho Hours, , 7 day ays/wee /week
Durat ation
Locat ations ions
*Pending City of Beverly Hills Council Approval
61
Jet grouting on Wilshire Bl/San Vicente Bl
*Subject to final, approved MOA
62
Street set-up on Wilshire
63
Exca cava vation tion is removing soil from the underground station area. Traffic ffic Requirements uirements
Overview
*Pending City of Beverly Hills Council Approval
64
Duration: tion: Approximately 9 months at night Weekd kdays ays and weeken kends ds (8pm pm – 7am) am)
Duration: Approximately 18 month during the day
Schedule
*Pending City of Beverly Hills Council Approval
65
Typica ical yard elements and activities
Work Hours rs:
Example - storing deck beams at Wilshire/Fairfax Yard
66
Wilshire/La Brea Staging Yard
k Hours: s:
nd Wall: ll: 20 feet
67
Soundwall Installation
68
reduce noise levels at the site
Overview
69
the street for traffic
Overview
Business Mitigation Assistance (BMA)
70
North Canon Drive Closure North Canon Drive Closure Feasibility Study conducted per MOA requirement in response to stakeholder concerns regarding mitigation measures of design-build impacts:
– Noise – Dust – Construction vehicle traffic – Visual Impacts – Varying lane and street closures
North Canon Drive Closure
– December 13, 2017 – January 10, 2018 – February 7, 2018
– January 9 - 60 hotel – January 17 - Public Works – January 26 - Spago – February 8 - GAC
– February 1
– February 15
72
from the Public
– Traffic impacts – Accessibility – Lost parking – Fire Life Safety – Security – Re-routing one-way streets – Mitigation measures – Valet impacts – Delivery / loading zones
North Canon Drive Closure
73
Council approved feasibility study and design development
to replace current all-way stop signs
select alternate routes to avoid overly congested locations
flows
and N. Crescent
closure could be in place during piling/decking only (2 years) or for entire construction duration (6 years)
North Canon Drive Closure
meetings on 4/19 and 5/10
design:
meters
flow over increased parking capacity
parking
North Canon Drive Closure
Canon Dr Closure Anticipated Schedule:
Wilshire/Rodeo Station
76 76
City y Coun uncil il Approvals* provals*
*Subject to change
77
Purp rple le Lin ine Ext xten ensio sion 24/7 Project Hotline - 213.922.6934 Email – purplelineext@metro.net On Metro ro Tra ransit See Something, Say Something 888-950-SAFE (7233) Constru ruct ction
fety y Aware renes ness s Pro rogr gram Glyssa Alcazar, Community Relations Officer Email: alcazarg@metro.net Phone: 323.900.2192 Cit ity of f Beve verl rly y Hil ills PurpleLine@beverlyhills.org Public Works Customer Service: (310) 285-2467
Help lping g loca cal l bu busines esses ses as we bu build. Update te as o
f 5/25/18 /18
> Financial assistance to small “mom & pop” businesses with 25 or fe r fewe wer r emp mplo loyees yees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > To date, 671 grants have been awarded with a total value of more than $14.9 million along all three projects
> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion
> BIF Grants Awarded: 163 > BIF Grant Amount Awarded: $3,987,263.95 > Number of small businesses awarded: 76 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999
> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion
> BIF Grants Awarded: 11 > BIF Grant Amount Awarded: $318,909.90 > Number of small businesses awarded: 11 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999
82
Beverly Hills
83