Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations June 6, 2018 1 Agenda Project Overview Section 2 Pre-Construction Updates Wilshire/Rodeo Station Section 1 Construction Updates Seismic Boring Study


slide-1
SLIDE 1

Purple Line Extension

Wilshire/La Cienega and Wilshire/Rodeo Stations June 6, 2018

1

slide-2
SLIDE 2

Agenda

2

  • Project Overview
  • Section 1 Construction Updates
  • Wilshire/La Cienega Station
  • Jet Grouting
  • Utility Work/Partial Lane

Closures

  • Excavation and Hauling

from Gale Yard

  • Section 2 Pre-Construction Updates
  • Wilshire/Rodeo Station
  • Seismic Boring Study
  • Advance Utility Relocation
  • Demo of former Ace Gallery
  • N. Canon Abatement and

Demolition

  • MOA for Design-Build -

Proposed Work Hours

  • N. Canon Dr Closure
  • Business Interruption Fund
  • Questions & Answers
slide-3
SLIDE 3

Purple Line Extension

Project Alignment

3

slide-4
SLIDE 4

Sections 1, 2 & 3 Status

4

Forecasted Schedule Section

Section 1 Section 2 Section 3

Length

3.92 Miles 2.59 Miles 2.59 Miles

New Stations

Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital

Pre-Construction Activities

2014 – 2015 2016 – 2018 2018 – 2020

Construction

2015 – 2023 2018 – 2025 2019 – 2026

Operations

2023 2025 2026

*Subject to change. The PLE project team is working to deliver the project consistent with Measure M

slide-5
SLIDE 5

Section 1

Wilshire/La Cienega Station

5

slide-6
SLIDE 6

Wilshire/La Cienega Station

6

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

slide-7
SLIDE 7

Wilshire/La Cienega Station

*As of June 2018, subject to change 7

slide-8
SLIDE 8

Wilshire/La Cienega

Installing Sound Wall

8

Installing sound wall at Gale Staging Yard

slide-9
SLIDE 9

Wilshire/La Cienega

Excavation Below Deck

9

Excavation under Wilshire Bl

slide-10
SLIDE 10

Wilshire/La Cienega

Jet grouting example

10

Example of jet grouting from San Vicente Bl and Wilshire Bl

slide-11
SLIDE 11

Wilshire/La Cienega

Upcoming Work, June 2018

11

  • Work zone on the north side of

Wilshire Bl (concrete barriers, fencing and noise mitigation blankets) will be removed anticipated Friday, June 15- Sunday, June 17 2018

  • Left turn movements on Wilshire

Bl are anticipated to return at Hamilton Dr, Gale Dr And Tower Dr

  • Parking meters, loading

zones and bus zones are planned to return to this area

Location of the current work zone on Wilshire Bl between La Cienega Bl and San Vicente Bl *Per City Staff Approval

slide-12
SLIDE 12

Wilshire/La Cienega

Jet Grouting, West of La Cienega starting June 2018

12

  • Center median work zone will be installed on Wilshire Bl

between Carson Rd and La Cienega Bl (with concrete barriers, fencing and noise mitigation blankets) starting June 15 for 4 to 6 months

  • Work zone: Center lanes of Wilshire Bl, with two lanes of

traffic in each direction.

  • Left turn and thru movements will be restricted from Stanley

Dr and Le Doux Rd at Wilshire Bl

  • Work hours:
  • 7am - 8pm for drilling activities
  • 8pm -10pm for support activities
  • Intermittent off-peak hour weekday lane closures and

weekend directional closures are anticipated.

  • Parking restrictions and changes to bus zones on Wilshire Bl

Location of the new work zone that will be installed on Wilshire Bl between Carson Rd and La Cienega Bl *Per City Staff Approval

slide-13
SLIDE 13

Wilshire/La Cienega

Weekend Directional Detours, June - Fall 2018

13

Above: Maps that show directional closures and the

  • detour. Detour for Wilshire Bl for either direction –

Robertson Bl, Olympic Bl, La Cienega Bl *Pending City Staff Approval

slide-14
SLIDE 14

Wilshire/La Cienega

Weekend Directional Closures, June - Fall 2018

14

  • Closure of one direction of Wilshire Bl done on weekends
  • Eastboun
  • und

d direc ecti tion

  • n: Eastbound Wilshire closed at Robertson
  • Westboun
  • und

d directi ction

  • n:

: Westbound Wilshire closed at La Cienega

  • All local streets remain open
  • These closures are not done simultaneously
  • Further details will be available in construction notices

*Pending City Staff Approval

slide-15
SLIDE 15

Utility Work on the North Side of Wilshire Bl

Location/closures for utility work on Wilshire Bl

  • Utility work scheduled to be

completed in mid-June

  • Vehicle and pedestrian access

maintained to 8447 Wilshire and 8423 Wilshire

  • Signed pedestrian detours will

be installed for pedestrian safety

  • Closure details and work hours

will be available in construction notices

15

slide-16
SLIDE 16

Lane Reductions and Weekend Partial Closures

Jet Grouting in City of Los Angeles

Location of upcoming closures on Wilshire Bl

  • Eastbound Wilshire lane reductions,

between Gale and San Vicente

  • Monday thru Friday 9am-3:30pm
  • Anticipated completion: July 2018
  • Driveway access to the Landmark Shopping

Center will be maintained

  • Closure details and work hours will be

available in construction notices

  • Coordinated with COBH
  • Will not occur during same time as

directional closures

16

slide-17
SLIDE 17

Wilshire/La Cienega

Replacement Parking Locations

One Hour r Free Parking ng available at:

  • 8447 Wilshire Bl – Access

garage from N Hamilton Dr

  • 8350 Wilshire Bl – Access

garage from S Tower Dr Additional replacement parking west of La Cienega Bl is being pursued Replacement parking locations

17

slide-18
SLIDE 18

Starting June 17, 2018, Metro Bus Service will return or be installed at the following locations:

  • Eastboun
  • und

d Wilshire re Bl Bl: :

  • Metro 20/720 bus stop at La

Cienega Bl in front of 8484 Wilshire Bl

  • Eastboun
  • und

d Wilshire re Bl Bl: :

  • Metro 20 bus stop at Gale

Dr in front of 8370 Wilshire Bl

Wilshire/La Cienega

Bus Stop Update

18

Metro bus stop locations

  • Westboun

und d Wilshire ire Bl Bl: :

  • Metro 20/720 stop at Willaman Dr in front
  • f 8677 Wilshire Blvd.
  • *This stop is anticipated to be in place for

4-5 months.

slide-19
SLIDE 19

Section 1 - Public Information Graphics

Implement on soundwall when k-rail is removed - Summer 2018

slide-20
SLIDE 20

Section 2

Wilshire/Rodeo Station

20 20

slide-21
SLIDE 21

Purple Line Extension

Section 2 Alignment

21

slide-22
SLIDE 22

Wilshire/Rodeo Station

Station Box

Rendering shows length of the underground station box

  • n Wilshire Bl from Canon Dr to Beverly Dr

22

slide-23
SLIDE 23

Wilshire/Rodeo Station Schedule

*As of June 2018, subject to change. Pending Council approval. 23

slide-24
SLIDE 24
  • These are deeper borings to investigate the geology to determine if a fault

is present

  • If a fault is present, the design-builder will identify the subsurface

conditions including fault characteristics relative to the proposed Metro tunnels

Geotechnical Investigations

Seismic Boring Study - Underway

FI-B-07 FI-B-06 FI-B-05 FI-B-04 FI-B-03 FI-B-02 FI-B-01 FI-B-08 FI-B-10 FI-B-09

24

slide-25
SLIDE 25

Advance Utility Relocation

Orange = AT&T Yellow= Gas

slide-26
SLIDE 26

SCG and AT&T Utility Relocation

Stage 4b: Ending Fri., June 8 / Mon-Fri: 9am-4pm

  • One lane maintained in each direction with flagger assistance between Wilshire Bl

and Gregory Way

26

slide-27
SLIDE 27

SCG and AT&T Utility Relocation

Combined Traffic Control

  • SCG and AT&T will work

simultaneously within work zone

  • Will reduce overall duration
  • f work
  • Work is scheduled from

February through August 2018

27

Current AUR work on Reeves Dr Excavating during AUR

slide-28
SLIDE 28

SCG and AT&T Utility Relocation

28

Current AUR work on Reeves Dr

slide-29
SLIDE 29

SCG and AT&T Utility Relocation

29

Placing gas line conduit End of day clean up

slide-30
SLIDE 30

SCG and AT&T Utility Relocation

Combined Traffic Control * Dates subject to change

  • Stage 4 - 8 will take place behind K-rail
  • K-rail to remain 24/7 and work will take place behind it during approved

working hours

  • Set up will take place in June 2018*

30

  • Wilshire, two lanes each

direction, from west of Beverly to east of Canon

  • Medians and parking

removed from work zone

  • Buses have been relocated
  • utside of work zone
slide-31
SLIDE 31

SCG and AT&T Utility Relocation

Stage 4: 34 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

31

K-Rail 24/7

No Left Turns: (if split phasing cannot be implemented)

  • EB Wilshire Bl to NB Canon Dr, Crescent Dr
  • WB Wilshire Bl to SB Canon Dr

Closed:

  • NB Reeves Dr closed
slide-32
SLIDE 32

SCG and AT&T Utility Relocation

Stage 5: 5days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

32

K-Rail 24/7

slide-33
SLIDE 33

SCG and AT&T Utility Relocation

Stage 6: 12 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

33

slide-34
SLIDE 34

SCG and AT&T Utility Relocation

Stage 7: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

34

K-Rail 24/7

No Left Turns: EB Wilshire to NB Beverly

slide-35
SLIDE 35

SCG and AT&T Utility Relocation

Stage 8: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm

K-Rail 24/7

35

slide-36
SLIDE 36

Bus Stops

Bus Stop Relocations

  • East of Beverly Dr:

20/720 WB/EB Wilshire Bl between Rexford Dr and Crescent Dr

  • West of Beverly Dr:

20/720 WB/EB Wilshire Bl between Camden Dr and Rodeo Dr

36

slide-37
SLIDE 37

Demolition of 9430 Wilshire Bl

Former Ace Gallery, future Construction Staging Yard

37

slide-38
SLIDE 38

Partial Closure of Reeves Park

Reeves Mini Park

  • Metro is required to pay the City’s

park rental fee for the closure of the park

  • Required 30-day notification of the

park closure

Wilshire Blvd Beverly Drive Reeves Drive 9430 Wilshire Blvd Reeves Mini Park

Proposed temporary closure area

slide-39
SLIDE 39

Demolition of 9430 Wilshire Bl

Former Ace Gallery

Site Addres dress: s: 943 430 0 Wilsh shir ire Bl Schedu edule le

  • Anticipated to start June 25, 2018*
  • Estimated duration of demolition activities: 8-10 weeks
  • Work hours: 8am - 6pm
  • Portion of park may be closed temporarily

Traffi ffic c Impacts cts

  • Sidewalk/partial lane closure along Reeves Dr and Wilshire Bl

(intermittently throughout duration of demolition)

  • Pedestrian protection to be installed
  • Potential closure of the alley
  • 39

*Per City Council Approval

slide-40
SLIDE 40
  • Work Hours: 8am – 6pm
  • Start Date: Immediately following
  • demolition. Anticipate September
  • Sound wall installed using soldier

piles and prefabricated noise panels

  • Sound Wall: 20 feet
  • Soundwall will have Public

Information Graphics

40

Soundwall Installation

Example ample of prefa fab noise se panel els Draft Stag aging ng Yard rd layout

  • ut
slide-41
SLIDE 41

41

Noise Control

  • l
  • All construction personnel will attend Noise Awareness Training provided by

Metro

  • Moveable noise barriers
  • Noise control curtains
  • Noise muffling enclosures on stationary equipment
  • No idling of heavy equipment when not in use
  • No slamming tailgates
  • Configure operations to eliminate backing movements
  • Maintain equipment to avoid rattling and banging of parts
  • Keep noise levels relatively uniform, avoid excessive and impulse noises
  • Truck Manager will be onsite to ensure that trucks idle in and out of site to

reduce noise levels at the site

Mitigation Measures: Noise

slide-42
SLIDE 42

42

Vibratio ion

  • Vibration Monitoring will be implemented
  • If vibration approaches FEIS/R threshold, then operations causing higher levels of vibration

will be minimized

  • Vibration exceedance will cause all work activities to stop until corrective active measures

can be implemented

Dust

  • During demo, water will be used to control fugitive dust
  • Use tarped trucks / covered loads
  • Hand sweep work area prior to opening traffic
  • Implementation of the Mitigation Monitoring Reporting Program (MMRP)
  • Dust control during transport, no idling of heavy equipment, maintenance of

construction equipment

  • Metro’s Green Construction Policy sets rigorous standards for equipment emissions
  • Implementation of Best Management Practices (BMPs)
  • Street watering, street sweeping, truck wheel track outs, wheel wash

Mitigation Measures: Vibration and Dust

slide-43
SLIDE 43

43

Section 2 - Public Information Graphics

Implement on soundwall when k-rail is removed - Summer 2018

slide-44
SLIDE 44

Abatement of N. Canon Properties

Site Addres dress: s: 9383-9393 and 9395-9399 Wilshire Bl Sched edule ule

  • Start date May 16, 2018
  • Estimated duration of demolition activities: 5 weeks
  • Work hours Monday- Friday 8am - 6pm
  • Demolition anticipated in September 2018*

44

*Pending City Council Approval

slide-45
SLIDE 45

Dus ust t Mi Miti tiga gation tion Me Measu sures res

  • Implementation of the Mitigation Monitoring Reporting

Program (MMRP)

  • Dust control during transport, no idling of heavy

equipment, maintenance of construction equipment

  • Metro’s Green Construction Policy sets rigorous standards

for equipment emissions

  • Implementation of Best Management Practices (BMPs)
  • Street watering, street sweeping, truck wheel track outs,

wheel wash

45

slide-46
SLIDE 46

Ai Air r Qu Quality ity Cont ntrol rol Me Measure sures

Construction Air Quality Compliance

  • Activities must comply with South Coast Air Quality Management

District (SCAQMD) Rule 403, the reduction and control of fugitive dust

  • Construction equipment is required to be registered with the

California Air Resource Board (CARB)

  • Use of Tier 4 equipment is required, which reduces emissions by
  • ver 95%
  • Inspectors and Monitors actively observe daily activities and track

compliance

  • Report dust concerns to SCAQMD via 800-288-7664

46

slide-47
SLIDE 47

Memorandum of Agreement

47

The purpose of the MOA is to:

– Minimize construction impacts in Beverly Hills through mitigation measures – Establish verification procedures and penalties for non-compliance – Ensure that the project complies with the standards and requirements of the City of Beverly Hills

Anticipated Schedule for Feedback and Approval

– Share MOA with Community after sharing with CC – City Council for introduction/review (6/19/2018) – City Council for consideration (7/19/2018)

FOCUS AREAS: Work Hours Traffic Noise Compliance Monitoring Business Mitigation Visual Mitigation

slide-48
SLIDE 48

MOA Piling Work Hours

Overview

48

Pile – A long, slender column of steel, reinforced concrete or timber Piling g – The process by which a “pile” is drilled deep into the ground to support soil removal and building structures Piling is necessary to ensure strong, solid soil foundations that resist ground

  • movement. Piles for the Rodeo Station will be drilled around the entire perimeter of

the station box on Wilshire, from Beverly to Crescent

  • Approximately 288 piles will be drilled for the Wilshire/Rodeo Station
  • North side: approximately 147 piles
  • South side: approximately 141 piles
  • Each pile is about 110 feet long
  • Pile drilling work zone will be marked by K-rail and fences
slide-49
SLIDE 49

MOA Piling Work Hours

Set-up

49

Cross-section showing work zone and drill rig for pile installation

slide-50
SLIDE 50

50

MOA Piling Work Hours

Piling on Wilshire between Gale and La Cienega

slide-51
SLIDE 51

51

MOA PiIing Work Hours

Drilling pile at La Cienega Staging Yard

slide-52
SLIDE 52

MOA Piling Work Hours

Schedule

52

Weekd kdays ays and Weekend kends

  • 8am - 9pm, drill and set piles
  • 9pm -11pm, cleanup and non-piling activities

Duration tion

  • Southside Piling: 2 to 3 months (Anticipated to start Fall 2018)
  • One week to re-route traffic
  • Northside Piling: 2 to 3 months

*Pending City of Beverly Hills Council Approval

slide-53
SLIDE 53

MOA Decking Work Hours

Overview

53

Decking king is a construction process that includes excavating the street and sidewalks, then replacing them with temporary concrete deck panels placed

  • ver steel beams
  • The temporary “deck” facilitates

the normal flow of traffic while maintaining pedestrian access to sidewalks and driveways

  • With a temporary deck in place,

construction crews can continue working underground

slide-54
SLIDE 54

54

MOA Decking Work Hours

Installation of deck beams across Wilshire at Tower

slide-55
SLIDE 55

55

MOA Decking Work Hours

Laying and welding deck beams across Wilshire and Gale

slide-56
SLIDE 56

MOA Decking Work Hours

Schedule

56

Pro roposed

  • sed Work

rk Hours rs

  • Friday, 8pm until Monday, 7am

Dura ration

  • Following piling operations
  • Proposed 13 weekend closures
  • Three to four months: Earliest start 2019

*Pending City of Beverly Hills Council Approval

slide-57
SLIDE 57

57

MOA Decking Work Hours

Wilshire traffic set up during the weeks in between decking

slide-58
SLIDE 58

MOA Holiday Moratorium

*Pending City of Beverly Hills Council Approval

58

  • Each year, Metro will request from COBH the right to work

from Thanksgiving to New Years

  • Requests will be required by each July
  • Metro is still considering the request for 2018
slide-59
SLIDE 59

MOA Appendage Work Hours

Overview

59

Appendage work extends off Wilshire into Canon and Beverly. This work will include piling and decking to shorter depths than the underground station. Work will take place over weekend closures and is anticipated for 2020. Anticip icipated ated Work Hours

  • 8pm, Friday – 7am, Monday

Loca cations tions

  • 5 Weekend Closures of Beverly Intersection
  • 3 Weekend Closures of Canon Intersection
  • 3 Weekend Closures of Reeves Intersection

*Pending City of Beverly Hills Council Approval

slide-60
SLIDE 60

MOA Jet Grouting Work Hours

Overview

60

Jet t Gro routi uting ng is a construction process by which a cement-soil mixture is injected into the ground at high velocity. Jet Grouting improves soil strength and permeability. Propos posed ed Work rk Ho Hours, , 7 day ays/wee /week

  • Wilshire
  • 8am – 9pm, Jet Grouting
  • 9pm – 11pm, Breakdown and clean-up
  • Residential Streets, South of Wilshire (Weekdays only)
  • 8am – 6pm, Jet Grouting
  • 6pm – 8pm, Breakdown and clean-up

Durat ation

  • n
  • Jet grouting will be approximately 2-3 months at each location

Locat ations ions

  • Anticipate 18 locations along alignment
  • 16 cross passages
  • East and west side of Wilshire/Rodeo Station

*Pending City of Beverly Hills Council Approval

slide-61
SLIDE 61

61

MOA Jet Grouting Work Hours

Jet grouting on Wilshire Bl/San Vicente Bl

*Subject to final, approved MOA

slide-62
SLIDE 62

62

MOA Jet Grouting Work Hours

Street set-up on Wilshire

slide-63
SLIDE 63

63

Exca cava vation tion is removing soil from the underground station area. Traffic ffic Requirements uirements

  • One lane of traffic open in each direction between Camden and Elm

MOA Excavation Work Hours

Overview

*Pending City of Beverly Hills Council Approval

slide-64
SLIDE 64

64

Duration: tion: Approximately 9 months at night Weekd kdays ays and weeken kends ds (8pm pm – 7am) am)

  • 8pm – 9:30pm: Install traffic control and noise mitigations
  • 9:30pm – 6am: Excavation operation
  • 6am – 7am: De-mobilization & remove traffic control

Duration: Approximately 18 month during the day

  • Monday-Friday: 7am – 4pm
  • Saturday-Sunday: 8am – 6pm

MOA Excavation Work Hours

Schedule

*Pending City of Beverly Hills Council Approval

slide-65
SLIDE 65

MOA St Stagi ging ng Yard d Work Hours

65

Typica ical yard elements and activities

  • Staging/storing of construction equipment
  • Ventilation & electrical infrastructure
  • Mobile trailers/office space
  • Portable restrooms
  • Employee Parking

Work Hours rs:

  • Dayshift: 8am – 8pm
  • Nightshift: 8pm – 8am

Example - storing deck beams at Wilshire/Fairfax Yard

slide-66
SLIDE 66

66

MOA Staging Yards

Wilshire/La Brea Staging Yard

slide-67
SLIDE 67
  • Work

k Hours: s:

  • Weekdays 7am – 4pm
  • Weekends 8am – 6pm
  • Sound

nd Wall: ll: 20 feet

67

MOA Work Hours Staging Yards

Soundwall Installation

slide-68
SLIDE 68

68

  • All construction personnel will attend Noise Awareness Training provided by Metro
  • Noise Control
  • l Measures:
  • Moveable noise barriers
  • Noise control curtains
  • Noise muffling enclosures on stationary equipment
  • No idling of heavy equipment when not in use
  • No slamming tailgates
  • Configure operations to eliminate backing movements
  • Maintain equipment to avoid rattling and banging of parts
  • Keep noise levels relatively uniform, avoid excessive and impulse noises
  • Truck Manager will be onsite to ensure that trucks idle in and out of site to

reduce noise levels at the site

MOA Noise Mitigation

Overview

slide-69
SLIDE 69

69

  • Use tarped trucks / covered loads
  • Hand sweep work Area prior to opening traffic
  • Street sweeper truck will be on standby for any final cleaning prior to reopening

the street for traffic

MOA Dust Control

Overview

slide-70
SLIDE 70

MOA – Design-Build

Business Mitigation Assistance (BMA)

70

  • 24/7 Hotline with live-person
  • Advertising
  • Eat Shop Play Beverly Hills
  • Parking Replacement program
  • Banners and signage (Aesthetic Treatment)
  • Communications, Outreach and Engagement
  • Traffic Control Officers
  • Marketing
  • Lighting
  • Public Information Graphics
slide-71
SLIDE 71

North Canon Drive Closure North Canon Drive Closure Feasibility Study conducted per MOA requirement in response to stakeholder concerns regarding mitigation measures of design-build impacts:

– Noise – Dust – Construction vehicle traffic – Visual Impacts – Varying lane and street closures

  • N. Canon closure anticipated 150 days during piling and decking
slide-72
SLIDE 72

North Canon Drive Closure

  • Community Meetings

– December 13, 2017 – January 10, 2018 – February 7, 2018

  • Stakeholder Meetings

– January 9 - 60 hotel – January 17 - Public Works – January 26 - Spago – February 8 - GAC

  • Traffic & Parking Commission

– February 1

  • City Council Liaison

– February 15

72

  • Concerns and comments

from the Public

– Traffic impacts – Accessibility – Lost parking – Fire Life Safety – Security – Re-routing one-way streets – Mitigation measures – Valet impacts – Delivery / loading zones

slide-73
SLIDE 73

North Canon Drive Closure

73

Council approved feasibility study and design development

  • Install Traffic Signal at Clifton Way & N. Crescent Drive intersection

to replace current all-way stop signs

  • Provide Advanced Vehicle Detour Signage to notify drivers to

select alternate routes to avoid overly congested locations

  • Update Traffic Signal Timings to accommodate the shift in vehicle

flows

  • Review Clifton Way Striping to increase capacity between N. Canon

and N. Crescent

  • Monitor N. Canon closure to observe traffic flows and operations;

closure could be in place during piling/decking only (2 years) or for entire construction duration (6 years)

slide-74
SLIDE 74

North Canon Drive Closure

  • Business stakeholder

meetings on 4/19 and 5/10

  • Discussed roadway

design:

  • Retain existing

meters

  • Prioritize traffic

flow over increased parking capacity

  • Prefer parallel

parking

slide-75
SLIDE 75

North Canon Drive Closure

  • Stakeholder outreach----------------------------------June 2018
  • Finalize design-------------------------------------------June 2018
  • Traffic and Parking Commission review-----------Summer 2018
  • City Council review/action---------------------------Summer 2018
  • Construction---------------------------------------------Fall 2018

Canon Dr Closure Anticipated Schedule:

slide-76
SLIDE 76

Next Steps

Wilshire/Rodeo Station

76 76

City y Coun uncil il Approvals* provals*

  • MOA Design-Build Introduction – June 19, 2018
  • MOA Design-Build Consideration – July 2018

*Subject to change

slide-77
SLIDE 77

Help Us Keep You Safe

77

Purp rple le Lin ine Ext xten ensio sion 24/7 Project Hotline - 213.922.6934 Email – purplelineext@metro.net On Metro ro Tra ransit See Something, Say Something 888-950-SAFE (7233) Constru ruct ction

  • n Safe

fety y Aware renes ness s Pro rogr gram Glyssa Alcazar, Community Relations Officer Email: alcazarg@metro.net Phone: 323.900.2192 Cit ity of f Beve verl rly y Hil ills PurpleLine@beverlyhills.org Public Works Customer Service: (310) 285-2467

slide-78
SLIDE 78

Help lping g loca cal l bu busines esses ses as we bu build. Update te as o

  • f

f 5/25/18 /18

slide-79
SLIDE 79

BIF Information and Eligibility

> Financial assistance to small “mom & pop” businesses with 25 or fe r fewe wer r emp mplo loyees yees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > To date, 671 grants have been awarded with a total value of more than $14.9 million along all three projects

slide-80
SLIDE 80

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion

  • n 1

> BIF Grants Awarded: 163 > BIF Grant Amount Awarded: $3,987,263.95 > Number of small businesses awarded: 76 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999

slide-81
SLIDE 81

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion

  • n 2

> BIF Grants Awarded: 11 > BIF Grant Amount Awarded: $318,909.90 > Number of small businesses awarded: 11 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999

slide-82
SLIDE 82

Updates on La Cienega and Rodeo Stations Wednesday, July 11 6:30pm – 8pm Beverly Hills City Hall Municipal Gallery, 2nd Floor 455 N Rexford Dr Beverly Hills, CA 90210

82

Next Community Meeting

Beverly Hills

slide-83
SLIDE 83

Stay in Touch

83