Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo - - PowerPoint PPT Presentation

purple line extension
SMART_READER_LITE
LIVE PREVIEW

Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo - - PowerPoint PPT Presentation

Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations July 10, 2019 1 Agenda Project oject Overvi rview ew Section ion 2 Pre-Con onst struction uction Upda dates tes Section ion 1 Cons nstruct


slide-1
SLIDE 1

Purple Line Extension

Wilshire/La Cienega and Wilshire/Rodeo Stations July 10, 2019

1

slide-2
SLIDE 2

Agenda

2

  • Project
  • ject Overvi

rview ew

  • Section

ion 1 Cons nstruct uction

  • n Updates

dates

  • Wilshire/La Cienega Station

Excavation

  • Station Naming
  • Section

ion 2 Pre-Con

  • nst

struction uction Upda dates tes

  • Wilshire/Rodeo Station
  • Staging Yards
  • Utility Work
  • Geotechnical

Instrumentation

  • N Cañon Closure
  • Piling
  • Decking
  • Business

ness Inter terru rupt ption

  • n Fund
  • Eat Shop

p Play y #Beverly verlyHill ills

slide-3
SLIDE 3

Purple Line Extension

Project Alignment

3

slide-4
SLIDE 4

Sections 1, 2 & 3 Status

4 *Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Foreca cast sted ed Sched edule ule Section ion

Section 1 Section 2 Section 3

Leng ngth th

3.92 Miles 2.59 Miles 2.56 Miles

New Stat ation ions

Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital

Pre-Const nstruct ruction ion Activiti vities es

2014 – 2015 2016 – 2018 2018 – 2019

Const nstruct ruction ion

2015 – 2023 2018 – 2025 2019 – 2027

Opera rati tion

  • ns

2023 2025 2027

slide-5
SLIDE 5

Section 1

Wilshire/La Cienega Station

5

slide-6
SLIDE 6

Wilshire/La Cienega Station Box

6

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

slide-7
SLIDE 7

Wilshire/La Cienega Station

*As of July 2019, subject to change 7

slide-8
SLIDE 8

Wilshire/Gale

Intermittent Daily Gale Closure – North of Wilshire Bl

  • Gale Dr will be intermittently

closed Monday to Saturday, 6am to 6pm

  • This closure is a public safety

measure due to high volumes of ingress/egress from the property

  • Access to N Gale Dr will be

maintained from San Vicente Bl

  • Hauling operation to occur

until 10pm

8

Gale Dr from north of Wilshire Bl

slide-9
SLIDE 9

Wilshire/La Cienega

9

Removing stockpiled excavation material

slide-10
SLIDE 10

Wilshire/La Cienega – Upcoming Work

Instrumentation Work & Street Maintenance

When: Ongoing ing through gh 2019 Instrume ument ntation ion work on Wilshire ire Bl and La Cienega ga Bl

  • Intermittent lane reductions on

Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Street Maintenanc nce, e, Dewatering ing Well Maintenanc nce, e, and Utility ty Work on Wilshire e Bl

  • Intermittent lane reductions on Wilshire

Bl and side streets during off-peak hours (non-rush hour)

10

Example of instrumentation drilling

slide-11
SLIDE 11

Wilshire/La Cienega – Upcoming Work

City of Los Angeles

When: Ongoing ing through gh 2019 Construction activities on Wilshire Bl between Fairfax Av and San Vicente Bl may require traffic control in the City of Beverly Hills. Work includes, but is not limited to:

  • Geotechnical instrumentation stalls
  • Soil improvement
  • Magnetic surveying

Information on this work and the required traffic control will be available via construction notices.

11

slide-12
SLIDE 12

Staging Yard Mitigation

La Cienega ga Yard

  • Active ventilation fans and fan

lines were wrapped with sound blankets

  • 24’ steel frame placed around

the ventilation system with sound blankets

  • Sound blankets surrounding

the ventilation system have been upgraded allowing for more sound absorption

12

Gale Yard

  • 14’ fences with sound blankets placed

around the crane

  • Applied an acoustic dampening material

to the 895 crane engine enclosure

  • Added a muffling panel on the exhaust

door and engine compartment door

  • Relocated slew alarm
  • Added a noise barrier rubber mat to the

lower engine panels

  • Acoustic plate under mounted on the

crane counterweight

  • Adjusted the crane start up schedule,

when possible

  • Started closing the gate, when feasible
  • Installed noise dampening louvre adjacent

to crane motor

slide-13
SLIDE 13

Station Naming Policy

13

Station Names will reflect the following principles

  • Transit system context:

xt: names will reflect the property’s location, relative to the entire transit system, and not duplicated elsewhere.

  • Property

rty area: provide specific information about the property’s location relative to the surrounding area.

  • Neighb

hbor

  • rhood

hood identity: ty: acknowledge the communities and neighborhoods serviced by the station and stops.

  • Simpli

licity: city: names will be short, easily recognizable and fit for signage and mapping.

slide-14
SLIDE 14

Name your next Purple Line Stations

14

Metro staff originally developed a set of geographically-based names for the Section 1 Stations and are now seeking community input on those names. Submit your proposals at metro.net/purple

slide-15
SLIDE 15

Section 2 Wilshire/Rodeo Station

slide-16
SLIDE 16

Wilshire/Rodeo Station Box

Station Box

16

Rendering shows length of the underground station box

  • n Wilshire Bl from Canon Dr to Beverly Dr
slide-17
SLIDE 17

Driveway Installation

Staging Yards

17

Where re: :

  • Wilshire/Reeves Yard: on Reeves Dr
  • N Cañon Yard: on N Cañon Dr and Wilshire Bl

Durat ation:

  • n: 1 week

Star art t Date te: Mid-July 2019 Work rk Hours: Monday – Friday, 8am – 6pm Tra raffic ffic Contro trol: l:

  • Sidewalk closure in place at driveway

locations during this period

  • Intermittent closure of curb lane on

westbound Wilshire Bl, northbound N Cañon Dr, and southbound Reeves Dr from 9am – 4pm

  • For your safety, do not use

streets as a walk way

slide-18
SLIDE 18
  • N. Cañon Staging Yard

Installation of Sound Wall

  • 20-foot sound wall around the staging yard will be installed to mitigate

noise to adjacent properties and public ROW

  • Star

art t Dat ate: e: Late June 2019

  • Compl

pleti etion

  • n Date:

e: Mid-July 2019

  • Work

k Hours: s: Monday – Friday, 8am – 6pm

18 *Subject to change

Sound wall progress at N Cañon Yard

slide-19
SLIDE 19

19

Utility Work

*Subject to change

Example of sewer line replacement

  • Potholing work to identify existing utilities

below the street

  • Sewer and water line replacement and

relocation and storm drain lateral replacement Star art t Date te: April 8, 2019 Durat ation:

  • n: 6 months*

Antici cipa pate ted Complet pletion: ion: September 2019* Work rk Ho Hours: :

  • Weekdays: 9am – 4pm
  • 8:15pm – 7am (per City approval)
  • Weekends: 10am – 6pm (as needed)

Traffic raffic Control trol:

  • Lane and crosswalk closures as well as turn restrictions will be required for this work.
  • Two lanes in each direction will be maintained for day work on Wilshire Bl
  • One lane in each direction will be maintained for night work on Wilshire Bl
slide-20
SLIDE 20

20

Geotechnical Instrumentation

Installation

Instruments will be installed within the station box area to monitor ground movement, settlement and

  • ther geological conditions. These installations will be

within the public right of way and within privately

  • wned properties.

Start Date: June 24, 2019 Duration:

  • n: Ongoing

Work Hours: rs:

  • Weekdays: 7am – 4pm
  • Weekends: 8am – 7pm (as needed)

Traffic c Control

  • l
  • Intermittent lane, sidewalk, and crosswalk, parking meter closures will be required

for this work on Wilshire Bl, Beverly Dr, Reeves Dr, N Cañon Dr, S Cañon Dr, and the northern alleys between Beverly Dr and Crescent Dr.

  • Flaggers will be available at alleys
  • Two lanes in each direction will be maintained for day work on Wilshire Bl

Example of geotechnical instrument installation in Century City

slide-21
SLIDE 21
  • N. Cañon Drive Closure

Traffic Configuration

Sound wall with art on Cañon Dr side and public information graphics on Wilshire Bl side

  • Install before piling for a minimum of 2 years
  • New traffic signal at Clifton/ Crescent
  • Existing meters / valet spaces on Clifton Way

shift to the north

  • Maintain existing valet time periods
  • Relocate some meters on N Cañon Dr from

East to West side

Pedestrian walkway

slide-22
SLIDE 22

Pile Drilling Installation

22

Pile installat ation ion include des:

  • Drill rig to drill holes
  • Crane to lift piles into holes
  • Truck to backfill holes
  • All work occurs behind K-rail and/or

traffic closures Schedul dule

  • Following utility relocation, anticipated to

start Q3 of 2019 on north side of Wilshire Bl Work Hours rs

  • 7 days a week
  • 8am – 9pm, drilling
  • 9pm – 11pm, non-drilling
  • 5 weekend closures at Wilshire/Beverly Dr

intersection (Friday 8pm – Monday 7am), for piling and decking, collectively

Example of piling work in Century City

*Dates subject to change

slide-23
SLIDE 23

23

Pile Drilling Installation

Example of progress on Constellation Bl

slide-24
SLIDE 24

Wilshire Bl Piling Set-up

North Side Piling Set-up

24

Example of construction area with piling set-up on the north side of Wilshire Bl

slide-25
SLIDE 25

Wilshire Bl Piling Set-up

South Side Piling Set-up

25

Example of construction area with piling set-up on the south side of Wilshire Bl

slide-26
SLIDE 26

Pile Drilling Weekend Installation

26 *Dates subject to change

  • Weekend

d Traff affic ic Closure ure: Friday 8pm – Monday 7am

  • Work Hours:

rs: Saturday and Sunday 7am – 8pm, 8pm – 10pm non-drilling and break-down

  • Weekend

d piling at t the follow lowin ing intersec ection tions and alleys ys: Beverly Dr, Reeves Dr, N Canon Dr (Wall Closure), S Canon Dr. PENDI NDING NG: North alleys between N Cañon Dr and Crescent Dr and between Beverly Dr and N Cañon Dr may be closed in M-F piling rather than weekends

  • NOTE: Each intersection may take several weekends to complete during north and south side

piling operations

Anticipated weekend closures for piling intersections and alleys

N Cañon wall LEGEND Approximate Pile Line Intersection Closures

slide-27
SLIDE 27

Piling Plan

27

NORTH SIDE E PILING NG:

  • Start

t Date: September 2019*

  • End Date: January 2020* (with work

during holiday moratorium)

  • Closure

ures Required: ired:

  • Beverly Dr
  • Alley between Beverly Dr and N Cañon Dr
  • N Cañon Dr (Wall Closure)
  • Alley between N Cañon Dr and Crescent Dr

*Dates subject to change

SOUTH SIDE E PILING NG:

  • Start

t Date: January 2020*

  • End Date: May 2020*
  • Closure

ures Required: ired:

  • Beverly Dr
  • Reeves Dr
  • S Cañon Dr

Piling will last approximately 4 months each side

Utility Work Completion (September 2019) N Cañon Dr Wall Completion (September 2019) Piling North Side (September 2019 – January 2020) Piling South Side (January 2020 – May 2020) Decking (Beginning May 2020)

slide-28
SLIDE 28

Decking

Following Piling: Anticipated May 2020*

28

  • Construction of a concrete deck, curb-to-curb
  • n Wilshire Bl
  • Decking will serve as the temporary street

surface

  • Metro will work closely with first responders on

emergency access and safety Durat ation:

  • n: Anticipated 13 weekends

Work rk Hours: : Full closures Friday, 8pm through Monday, 7am Ad Addi ditional tional activitie ivities unde der r decking cking closure ures:

  • Ground improvements, piling, temporary civil

improvements, dewatering system installation and geotechnical instrumentation

Asphalt removal on Wilshire Bl near Detroit St Steel beams welding prior to concrete deck panel installation

*Dates subject to change

slide-29
SLIDE 29

Help lping g loca cal l bu busines esses ses as we bu build. Purp rple le Line Ext xten ensio sion n Update te

slide-30
SLIDE 30

BIF Information and Eligibility

> Financial assistance to small “mom and pop” businesses with 25 or fewer full-time employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > Businesses are eligible for up to $50,000 per impact year

slide-31
SLIDE 31

BIF Information and Eligibility

> To date, 932 grants have been awarded with a total value of more than $22.3 million along all three project areas > Crenshaw/LAX Transit Project > Regional Connector, Little Tokyo area > Purple Line Extension Section 1 and Section 2 > February 2019 Metro’s Board of Directors authorized the expansion of the BIF to Section 3 of the Purple Line Extension

slide-32
SLIDE 32

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion n Secti tion

  • n 1 (as

s of 6/ f 6/28/19) 8/19) > BIF Grants Awarded: 198 > BIF Grant Amount Awarded: $5,142,660.09 > Number of small businesses awarded: 76 > City of Beverly Hills only > BIF Grants Awarded: 34 > BIF Grant Amount Awarded: $884,886.20 > Number of small businesses awarded: 15 > BIF Business Advisor: Brian Lazo, PCR, 213.739.2999

slide-33
SLIDE 33

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion n Secti tion

  • n 2 (as

s of 6/ f 6/28/19) 8/19) > BIF Grants Awarded: 50 > BIF Grant Amount Awarded: $1,393,595.28 > Number of small businesses awarded: 30 > City of Beverly Hills only > BIF Grants Awarded: 44 > BIF Grant Amount Awarded: $1,244,510.21 > Number of small businesses awarded: 26 > BIF Business Advisor: Darrell Smith, PCR, 213.739.2999

slide-34
SLIDE 34

34

107 S Robertson Bl Beverly Hills, CA 90211 424.777.0481

slide-35
SLIDE 35

Construction Updates on La Cienega and Rodeo Stations Wednesday, August 7 6:30pm – 8pm

Beverly Hills City Hall 2nd Floor Municipal Gallery 445 N Rexford Dr Beverly Hills, CA 90210

2 hour free parking before 5pm Free after 5pm, no validation necessary

35

Next Construction Update

Beverly Hills

slide-36
SLIDE 36

Section 2: Construction Community Meeting Thursday, August 15, 2019 6:30pm – 8pm

Century Park Towers 2029 Century Park East Concourse Level D, Conference Room A Los Angeles, CA 90067

*Parking will be validated

36

Next Community Meeting

Section 2

slide-37
SLIDE 37

Stay in Touch

37