Purple Line Extension
Wilshire/La Cienega and Wilshire/Rodeo Stations July 11, 2018
1
Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo - - PowerPoint PPT Presentation
Purple Line Extension Wilshire/La Cienega and Wilshire/Rodeo Stations July 11, 2018 1 Agenda Project oject Overvi rview ew Section ion 2 Pre-Con onst struction uction Upda dates tes Wilshire/Rodeo Station Section
Wilshire/La Cienega and Wilshire/Rodeo Stations July 11, 2018
1
2
rview ew
ion 1 Constr nstruc ucti tion
dates tes
Detours
ion 2 Pre-Con
struction uction Upda dates tes
Demolition
ness ss Inter terru rupt ption
tions & Answ swer ers
Project Alignment
3
4
Forecasted Schedule Section
Section 1 Section 2 Section 3
Length
3.92 Miles 2.59 Miles 2.59 Miles
New Stations
Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital
Pre-Construction Activities
2014 – 2015 2016 – 2018 2018 – 2020
Construction
2015 – 2023 2018 – 2025 2019 – 2026
Operations
2023 2025 2026
*Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Wilshire/La Cienega Station
5
6
Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr
*As of June 2018, subject to change 7
Installing Sound Wall
8
Installing sound wall at Gale Staging Yard
Excavation Below Deck
9
Excavation under Wilshire Bl
Jet Grouting, West of La Cienega starting June – Fall 2018
10
Carson and La Cienega, for 4 to 6 months
in each direction.
and Le Doux at Wilshire
weekend directional closures are anticipated.
Location of the new work zone that will be installed on Wilshire Bl between Carson Rd and La Cienega Bl *Per City Staff Approval
Weekend Directional Closures, June - Fall 2018
11
d direc ecti tion
d directi ction
: Westbound Wilshire closed at La Cienega
*Pending City Staff Approval
Jet Grouting Work Zone
12
Jet grouting work zone on Wilshire Bl and Stanley Dr
Jet Grouting Work Zone
13
Inside jet grouting work zone
Eastbound Wilshire Weekend Directional Detour, June - Fall 2018
14
*Pending City Staff Approval *Westbound Wilshire may be reduced to one lane during this closure
Westbound Weekend Directional Detour, June - Fall 2018
15
*Pending City Staff Approval *Eastbound Wilshire may be reduced to one lane during this closure
Replacement Parking Locations
One Hour r Free Parking ng available at:
garage from N Hamilton
garage from S Tower Alternative replacement parking west of La Cienega is being pursued Replacement parking locations
16
New Metro Bus Service locations:
re Bl Bl: :
Cienega, in front of 8484 Wilshire
re Bl Bl: :
in front of 8370 Wilshire
Bus Stop Update
17
Metro bus stop locations
und d Wilshire ire Bl Bl: :
8677 Wilshire Blvd.
4-5 months.
Public Information Graphics
To be implement ed on soundwall when K-rail is removed , Summer 2018
Wilshire/Rodeo Station
19 19
Section 2 Alignment
20
Station Box
Rendering shows length of the underground station box
21
*As of July 2018, subject to change. Pending Council approval. 22
conditions including fault characteristics relative to the proposed Metro tunnels
Seismic Boring Study - Underway
FI-B-07 FI-B-06 FI-B-05 FI-B-04 FI-B-03 FI-B-02 FI-B-01 FI-B-08 FI-B-10 FI-B-09
23
FI-B-07 FI-B-06 FI-B-05 FI-B-04 FI-B-03 FI-B-02 FI-B-01 FI-B-08 FI-B-10 FI-B-09
24
Seismic Boring Study
Boring behind noise mitigation blankets
Orange = AT&T Yellow= Gas
Combined Traffic Control
simultaneously within work zone
February through October 2018
26
Current AUR work on Reeves Dr Excavating during AUR
27
Current AUR work on Reeves Dr
28
Placing gas line conduit End of day clean up
Combined Traffic Control * Dates subject to change
working hours
29
direction, from west of Beverly to east of Canon
removed from work zone
Stage 4: 24 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
30
No Left t Turn rns: (if split phasing cannot be implemented)
Closed:
Stage 5: 5days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
31
Stage 6: 12 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
32
Stage 7: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
33
No Left t Turn rns: EB Wilshire to NB Beverly
Stage 8: 6 days / Mon-Fri: 7am-7pm, Sat-Sun: 10am-6pm
34
Bus Stop Relocations
ly Dr Dr: 20/720 WB/EB Wilshire Bl between Rexford Dr and Crescent Dr
rly y Dr Dr: 20/720 WB/EB Wilshire Bl between Camden Dr and Rodeo Dr
35
Former Ace Gallery, future Construction Staging Yard
36
Reeves Mini Park
park rental fee for the closure of the park
park closure
Wilshire Blvd Beverly Drive Reeves Drive 9430 Wilshire Blvd Reeves Mini Park
Proposed temporary closure area
Former Ace Gallery
Site Addres dress: s: 943 430 0 Wilsh shir ire Bl Schedu edule le
Traffi ffic c Impacts cts
(intermittently throughout duration of demolition)
piles and prefabricated noise panels
Information Graphics
39
Example ample of prefa fab noise se panel els Draft Stag aging ng Yard rd layout
40
Public Information Graphics
To be implemented on soundwall, Fall 2018
41
Noise Control
Metro
reduce noise levels at the site
42
Vibratio ion
will be minimized
implemented
Dust
construction equipment
Construction Air Quality Compliance
District (SCAQMD) Rule 403, the reduction and control of fugitive dust
California Air Resource Board (CARB)
compliance
43
Site Addres dress: s: 9383-9393 and 9395-9399 Wilshire Bl Sched edule ule
44
*Pending City Council Approval
Overview
45
Pile – A long, slender column of steel, reinforced concrete or timber Piling g – The process by which a “pile” is drilled deep into the ground to support soil removal and building structures Piling is necessary to ensure strong, solid soil foundations that resist ground
the station box on Wilshire, from Beverly to Crescent
46
Piling on Wilshire between Gale and La Cienega
Schedule
47
Weekd kdays ays and Weekend kends
Duration tion
*Pending City of Beverly Hills Council Approval
Overview
48
Decking king is a construction process that includes excavating the street and sidewalks, then replacing them with temporary concrete deck panels placed
the normal flow of traffic while maintaining pedestrian access to sidewalks and driveways
construction crews can continue working underground
49
Installation of deck beams across Wilshire at Tower
Schedule
50
Pro roposed
rk Hours rs
Dura ration
*Pending City of Beverly Hills Council Approval
51
Wilshire traffic set up during the weeks in between decking
*Pending City of Beverly Hills Council Approval
52
from Thanksgiving to New Years
Overview
53
Appendage work extends off Wilshire into Canon and Beverly. This work will include piling and decking to shorter depths than the underground station. Work will take place over weekend closures and is anticipated for 2020. Anticip icipated ated Work Hours
Loca cations tions
*Pending City of Beverly Hills Council Approval
Overview
54
Jet t Gro routi uting ng is a construction process by which a cement-soil mixture is injected into the ground at high velocity. Jet Grouting improves soil strength and permeability. Propos posed ed Work rk Ho Hours, , 7 day ays/wee /week
Durat ation
Locat ations ions
*Pending City of Beverly Hills Council Approval
55
Jet grouting on Wilshire Bl/San Vicente Bl
*Subject to final, approved MOA
56
Exca cava vation tion is removing soil from the underground station area. Traffic ffic Requirements uirements
Overview
*Pending City of Beverly Hills Council Approval
57
Duration: tion: Approximately 9 months at night Weekd kdays ays and weeken kends ds (8pm pm – 7am) am)
Duration: Approximately 18 months during the day
Schedule
*Pending City of Beverly Hills Council Approval
58
Typica ical yard elements and activities
Work Hours rs:
Example - storing deck beams at Wilshire/Fairfax Yard
59
Wilshire/La Brea Staging Yard
k Hours: s:
nd Wall: ll: 20 feet
60
Soundwall Installation
61
reduce noise levels at the site
Overview
62
the street for traffic
Overview
Business Mitigation Assistance (BMA)
63
Wilshire/Rodeo Station
64 64
City y Coun uncil il Approvals* provals*
*Subject to change
North Canon Drive Closure
In response to stakeholder concerns, MOA included requirement for a feasibility study
North Canon Drive Closure
North Canon Drive Closure
MOA included reqirement for a feasibility study
North Canon Drive Closure
MOA included reqirement for a feasibility study
North Canon Drive Closure
MOA included reqirement for a feasibility study
North Canon Drive Closure
MOA included reqirement for a feasibility study
North Canon Drive Closure
MOA included reqirement for a feasibility study
North Canon Drive Closure
MOA included reqirement for a feasibility study
North Canon Drive Closure
North Canon Drive Closure
North Canon Drive Closure
North Canon Drive Closure
Facing southbound
North Canon Drive Closure
North Canon Drive Closure
City Council Formal Meeting July 24, 2018 7:00 pm Council Chambers
Help lping g loca cal l bu busines esses ses as we bu build. Update te as o
f 7/3/18 18
> Financial assistance to small “mom & pop” businesses with 25 or fe r fewe wer r emp mplo loyees yees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > To date, 696 grants have been awarded with a total value of more than $15.5 million along all three projects
> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion
> BIF Grants Awarded: 169 > BIF Grant Amount Awarded: $4,165,150.11 > Number of small businesses awarded: 78 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999
> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion
> BIF Grants Awarded: 12 > BIF Grant Amount Awarded: $341,282.12 > Number of small businesses awarded: 12 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999
83
Beverly Hills
84
Section 2
85
Purp rple le Lin ine Ext xten ensio sion 24/7 Project Hotline - 213.922.6934 Email – purplelineext@metro.net On Metro ro Tra ransit See Something, Say Something 888-950-SAFE (7233) Constru ruct ction
fety y Aware renes ness s Pro rogr gram Glyssa Alcazar, Community Relations Officer Email: alcazarg@metro.net Phone: 323.900.2192 Cit ity of f Beve verl rly y Hil ills PurpleLine@beverlyhills.org Public Works Customer Service: (310) 285-2467
86