Purple Line Extension Section 1 Construction Community Meeting January 17, 2019 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Fossils Project-wide Tunneling Wilshire/Western Wilshire/La Brea


slide-1
SLIDE 1

Purple Line Extension

Section 1 Construction Community Meeting January 17, 2019

1

slide-2
SLIDE 2

Agenda

Section 1

2

  • MOW 64 Facility
  • Project Construction Updates:
  • Fossils
  • Project-wide Tunneling
  • Wilshire/Western
  • Wilshire/La Brea
  • Wilshire/Fairfax
  • Wilshire/La Cienega
slide-3
SLIDE 3

Purple Line Extension

Project Alignment

3

slide-4
SLIDE 4

Sections 1, 2 & 3 Status

4 *Subject to change. The PLE project team is working to deliver the project consistent with Measure M

Forecasted Schedule Section

Section 1 Section 2 Section 3

Length

3.92 Miles 2.59 Miles 2.56 Miles

New Stations

Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital

Pre-Construction Activities

2014 – 2015 2016 – 2018 2018 – 2020

Construction

2015 – 2023 2018 – 2025 2019 – 2026

Operations

2023 2025 2026

slide-5
SLIDE 5

Purple Line Extension

Section 1 Alignment

5

slide-6
SLIDE 6

Purple Line Extension

Section 1 Schedule

6 *As of January 2019, subject to change

slide-7
SLIDE 7

Purple Line Maintenance Facility

7

Maintena tenance nce Faci cility ity

  • Located in the Arts District, north of 6th St Bridge
  • 590 S Santa Fe Av

Current ent Work

  • Started installing exterior steel building panels
  • Installed windows
  • Finishing interior walls
  • Location 64 Site utilities complete
slide-8
SLIDE 8

Purple Line Maintenance Facility

8

Sealant being installed around windows. Working on electrical pathways in storage area.

slide-9
SLIDE 9

Purple Line Maintenance Facility

9

Finish coat applied to the third floor.

slide-10
SLIDE 10

Project-wide Tunneling

10

One of two tunnels, looking into tail of TBM.

slide-11
SLIDE 11

Fossils

The treasure trove grows

11

slide-12
SLIDE 12

Fossils

“One of the most unsual digs in the country” - CBS

12

slide-13
SLIDE 13

Wilshire/Western Connection Schedule

Schedule

13 *As of January 2019, subject to change

slide-14
SLIDE 14

Wilshire/Western Connection

Upcoming Work

14

Construction activities between Wilshire Bl/Manhattan Pl and Wilshire Bl/Western Av behind work zone:

  • Excavation
  • Dewatering
  • Instrumentation

Work zone will be in place until the end of January 2019

Location of construction on Wilshire Bl at Western Av, instrumentation and dewatering work will intermittently extend onto Manhattan Pl

slide-15
SLIDE 15

Wilshire/Western Connection

Excavation

15

Leveling the ground to create the TBM slab

slide-16
SLIDE 16

Wilshire/La Brea Station

16

slide-17
SLIDE 17

Wilshire/La Brea Station Box

17

Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St

slide-18
SLIDE 18

Wilshire/La Brea Station

Schedule

18 *As of January 2019, subject to change

slide-19
SLIDE 19

Wilshire/La Brea Station

Station Construction

19

Shoring for future concourse deck.

slide-20
SLIDE 20

Wilshire/La Brea Station

Station Construction

20

Construction the interior walls.

slide-21
SLIDE 21

Wilshire/Fairfax Station

21

slide-22
SLIDE 22

Wilshire/Fairfax Station Box

22

Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west

  • f Fairfax Av to just west of Ogden Dr
slide-23
SLIDE 23

Wilshire/Fairfax Station Schedule

*As of January 2019, subject to change 23

slide-24
SLIDE 24

Wilshire/Fairfax Station

Excavation

24

Excavation progress.

slide-25
SLIDE 25

Wilshire/Fairfax Station

Concrete and Rebar – Winter 2019

  • Concrete and rebar (steel) work

anticipated to start in February 2019

  • Work will require worksite traffic

control on the south side of Wilshire Bl from Orange Grove Av to Ogden Dr

  • Night time work: 7pm – 6am
  • Ventilation vans now running at full

capacity during nighttime hours for safety of workers and to continue excavation

  • More details to be provided in future

construction notices and briefings

Concrete work shown from the street level at Wilshire/La Brea. Concrete is being pumped underground from the street level. Similar

work will be done at the Wilshire/Fairfax.

25

slide-26
SLIDE 26

Wilshire/Crescent Heights

Tunnel Investigation, January 2019

26

Approximate work locations at Wilshire/Crescent Heights.

  • Investigative drilling in advance of

tunneling anticipated at Wilshire Bl/Crescent Heights Bl beginning January 2019

  • Expected traffic control:
  • Non-rush hour weekday lane

reductions on Wilshire Bl

  • Typical work hours, 9am – 3:30pm
  • Weekend directional closures of

Wilshire Bl and/or Crescent Heights Bl

  • Typical work hours 7am – 11pm.
  • Intermittent sidewalk closures with

pedestrian detours

slide-27
SLIDE 27

Upcoming Restoration Work

Bus Pads and Water Crossings

Beginning February 2019, design-builder will restore bus pads and water crossings at the following locations:

  • Wilshire Bl/Bronson Av
  • Wilshire Bl/Lorraine Bl
  • Wilshire Bl/McCadden Pl
  • Wilshire Bl/Citrus Av
  • Wilshire Bl/Cloverdale Av
  • Wilshire Bl/McCarthy Vista
  • Wilshire Bl/San Vicente Bl

The following traffic control will be in place:

  • Wilshire Bl in the work area will be

reduced to one lane

  • This lane reduction will be begin on

Saturday mornings and will be removed

  • n Monday mornings
  • More details will be provided in future

construction notices Example of bus pad on Wilshire Bl

slide-28
SLIDE 28

Wilshire/La Cienega Station

28

slide-29
SLIDE 29

Wilshire/La Cienega Station Box

29

Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr

slide-30
SLIDE 30

Wilshire/La Cienega Station

*As of January 2019, subject to change 30

slide-31
SLIDE 31

Wilshire/La Cienega

Construction Staging Yards

Typical Activities/Equipment:

  • Excavation
  • Steel work
  • Deliveries
  • Hauling
  • Typical hours are 7am – 11pm;

yard use is permitted 24/7

  • All noise levels must remain in

compliance with MOA and FEIR requirements

31

Excavator in the La Cienega shaft

slide-32
SLIDE 32

Wilshire/Gale

Intermittent Daily Gale Closure

  • Gale Dr will be intermittently

closed Monday to Friday, 6am to *10pm, and Saturday 7am to 6pm

  • This closure is a public safety

measure due to high volumes of ingress/egress from the property

  • Access to N Gale Dr will be

maintained from San Vicente Bl

32

Gale Dr from north of Wilshire Bl

*Pending City of Beverly Hills Approval

slide-33
SLIDE 33

Wilshire/La Cienega

Excavation

33

Moving excavated material to the removal shaft

slide-34
SLIDE 34

Wilshire/La Cienega – Upcoming Work

Instrumentation Work & Street Maintenance

When: Winter r 2019 Instrume ument ntation ion work on Wilshire ire Bl and La Cienega ga Bl

  • Intermittent lane reductions on

Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Street Maintenanc nce, e, Dewatering ing Well Maintenanc nce, e, and Utility ty Work on Wilshire ire Bl Bl

  • Intermittent lane reductions on Wilshire

Bl and side streets during off-peak hours (non-rush hour)

34

Example of instrumentation drilling

slide-35
SLIDE 35

Staging Yard Mitigation

La Cienega ga Yard  Active ventilation fans and fan lines were wrapped with sound blankets  24’ steel frame placed around the ventilation system with sound blankets

35

Gale Yard  14’ fences with sound blankets placed around the crane (reduced the noise by 3 dbA)  Applied an acoustic dampening material to the 895 crane engine enclosure  Added a muffling panel on the exhaust door and engine compartment door  Relocated slew alarm  Added a noise barrier rubber mat to the lower engine panels  Acoustic plate under mounted on the crane counterweight  Adjusted the crane start up schedule, when possible  Started closing the gate, when feasible

slide-36
SLIDE 36

36

621 S Western Ave #100 Los Angeles, CA 90005 (213)384-2244

slide-37
SLIDE 37

37

805 S. La Brea Ave, Los Angeles, CA 90036 (323) 285-5348

slide-38
SLIDE 38

Afgh ghan ani i Kabob

  • b House

se 8560 Wilshire Blvd Beverly Hills, CA 90211 (310) 854-1020 Cong ngrats ats Afgha ghani ni Kabob

  • b House!

se! Small Business Saturday Video Ad on Social Media Over r 10K Views ws Onli line ne

slide-39
SLIDE 39

Help lping g loca cal l bu busines esses ses as we bu build. Update te as o

  • f

f 1/4/19 19

slide-40
SLIDE 40

BIF Information and Eligibility

> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > To date, 809 grants have been awarded with a total value of more than $18.9 million along all three projects

40

slide-41
SLIDE 41

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion

  • n 1

> BIF Grants Awarded: 181 > BIF Grant Amount Awarded: $4,604,665.33 > Number of small businesses awarded: 71 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999

41

slide-42
SLIDE 42

BIF Grant Award Update

> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion

  • n 2

> BIF Grants Awarded: 29 > BIF Grant Amount Awarded: $780,320.11 > Number of small businesses awarded: 19 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999

42

slide-43
SLIDE 43

Updates on La Cienega and Rodeo Stations Wednesday, February 6, 2019 6:30pm – 8pm Beverly Hills City Hall Municipal Gallery, 2nd Floor 455 N Rexford Dr Beverly Hills, CA 90210 *On-site parking free after 5pm

43

Next Community Meeting

Beverly Hills

slide-44
SLIDE 44

Section 1: Construction Community Meeting Thursday, April 18, 2019 6:30pm – 7:30pm SAG-AFTRA 5757 Wilshire Bl Los Angeles, CA 90036 *On-site parking will be validated

44

Next Community Meeting

Section 1

slide-45
SLIDE 45

Section 1 Halfway There Celebrate 50% Completion of the Project Saturday, May 11, 2019 11am – 3pm Lawn West of the Tar Pits Museum 5801 Wilshire Bl Los Angeles, CA 90036

45

Halfway There

Section 1

slide-46
SLIDE 46

Help Us Keep You Safe

46

Purp rple le Lin ine Ext xten ensio sion 24/7 Project Hotline - 213.922.6934 Email – purplelineext@metro.net On Metro ro Tra ransit See Something, Say Something 888.950.SAFE (7233) Constru ruct ction

  • n Safe

fety y Aware renes ness s Pro rogr gram Glyssa Robles, Community Relations Officer Email: roblesgl@metro.net Phone: 323.900.2192 Cit ity of f Beve verl rly y Hil ills PurpleLine@beverlyhills.org Public Works Customer Service: 310.285.2467