Purple Line Extension
Section 1 Construction Community Meeting January 17, 2019
1
Purple Line Extension Section 1 Construction Community Meeting - - PowerPoint PPT Presentation
Purple Line Extension Section 1 Construction Community Meeting January 17, 2019 1 Agenda Section 1 MOW 64 Facility Project Construction Updates: Fossils Project-wide Tunneling Wilshire/Western Wilshire/La Brea
Section 1 Construction Community Meeting January 17, 2019
1
Section 1
2
Project Alignment
3
4 *Subject to change. The PLE project team is working to deliver the project consistent with Measure M
Forecasted Schedule Section
Section 1 Section 2 Section 3
Length
3.92 Miles 2.59 Miles 2.56 Miles
New Stations
Wilshire/La Brea Wilshire/Fairfax Wilshire/La Cienega Wilshire/Rodeo Century City/ Constellation Westwood/UCLA Westwood/VA Hospital
Pre-Construction Activities
2014 – 2015 2016 – 2018 2018 – 2020
Construction
2015 – 2023 2018 – 2025 2019 – 2026
Operations
2023 2025 2026
Section 1 Alignment
5
Section 1 Schedule
6 *As of January 2019, subject to change
7
8
Sealant being installed around windows. Working on electrical pathways in storage area.
9
Finish coat applied to the third floor.
10
One of two tunnels, looking into tail of TBM.
The treasure trove grows
11
“One of the most unsual digs in the country” - CBS
12
Schedule
13 *As of January 2019, subject to change
Upcoming Work
14
Construction activities between Wilshire Bl/Manhattan Pl and Wilshire Bl/Western Av behind work zone:
Work zone will be in place until the end of January 2019
Location of construction on Wilshire Bl at Western Av, instrumentation and dewatering work will intermittently extend onto Manhattan Pl
Excavation
15
Leveling the ground to create the TBM slab
16
17
Rendering shows length of the Wilshire/La Brea underground station box on Wilshire Bl from Orange Dr to Detroit St
Schedule
18 *As of January 2019, subject to change
Station Construction
19
Shoring for future concourse deck.
Station Construction
20
Construction the interior walls.
21
22
Rendering shows length of the Wilshire/Fairfax underground station box on Wilshire Bl from west
*As of January 2019, subject to change 23
Excavation
24
Excavation progress.
Concrete and Rebar – Winter 2019
anticipated to start in February 2019
control on the south side of Wilshire Bl from Orange Grove Av to Ogden Dr
capacity during nighttime hours for safety of workers and to continue excavation
construction notices and briefings
Concrete work shown from the street level at Wilshire/La Brea. Concrete is being pumped underground from the street level. Similar
work will be done at the Wilshire/Fairfax.
25
Tunnel Investigation, January 2019
26
Approximate work locations at Wilshire/Crescent Heights.
tunneling anticipated at Wilshire Bl/Crescent Heights Bl beginning January 2019
reductions on Wilshire Bl
Wilshire Bl and/or Crescent Heights Bl
pedestrian detours
Bus Pads and Water Crossings
Beginning February 2019, design-builder will restore bus pads and water crossings at the following locations:
The following traffic control will be in place:
reduced to one lane
Saturday mornings and will be removed
construction notices Example of bus pad on Wilshire Bl
28
29
Rendering shows length of the La Cienega underground station box on Wilshire Bl from La Cienega Bl to Tower Dr
*As of January 2019, subject to change 30
Construction Staging Yards
Typical Activities/Equipment:
yard use is permitted 24/7
compliance with MOA and FEIR requirements
31
Excavator in the La Cienega shaft
Intermittent Daily Gale Closure
closed Monday to Friday, 6am to *10pm, and Saturday 7am to 6pm
measure due to high volumes of ingress/egress from the property
maintained from San Vicente Bl
32
Gale Dr from north of Wilshire Bl
*Pending City of Beverly Hills Approval
Excavation
33
Moving excavated material to the removal shaft
Instrumentation Work & Street Maintenance
When: Winter r 2019 Instrume ument ntation ion work on Wilshire ire Bl and La Cienega ga Bl
Wilshire Bl, La Cienega Bl, and side streets during off-peak hours (non-rush hour) Street Maintenanc nce, e, Dewatering ing Well Maintenanc nce, e, and Utility ty Work on Wilshire ire Bl Bl
Bl and side streets during off-peak hours (non-rush hour)
34
Example of instrumentation drilling
La Cienega ga Yard Active ventilation fans and fan lines were wrapped with sound blankets 24’ steel frame placed around the ventilation system with sound blankets
35
Gale Yard 14’ fences with sound blankets placed around the crane (reduced the noise by 3 dbA) Applied an acoustic dampening material to the 895 crane engine enclosure Added a muffling panel on the exhaust door and engine compartment door Relocated slew alarm Added a noise barrier rubber mat to the lower engine panels Acoustic plate under mounted on the crane counterweight Adjusted the crane start up schedule, when possible Started closing the gate, when feasible
36
621 S Western Ave #100 Los Angeles, CA 90005 (213)384-2244
37
805 S. La Brea Ave, Los Angeles, CA 90036 (323) 285-5348
Afgh ghan ani i Kabob
se 8560 Wilshire Blvd Beverly Hills, CA 90211 (310) 854-1020 Cong ngrats ats Afgha ghani ni Kabob
se! Small Business Saturday Video Ad on Social Media Over r 10K Views ws Onli line ne
Help lping g loca cal l bu busines esses ses as we bu build. Update te as o
f 1/4/19 19
> Financial assistance to small “mom & pop” businesses with 25 or fewer employees directly impacted by Metro Rail construction along three project areas > Businesses must be located immediately adjacent to the rail corridor and meet other eligibility requirements > Grant amount determined by loss of business revenue related to period of construction disruption > To date, 809 grants have been awarded with a total value of more than $18.9 million along all three projects
40
> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion
> BIF Grants Awarded: 181 > BIF Grant Amount Awarded: $4,604,665.33 > Number of small businesses awarded: 71 > BIF Business Advisor: Brian Lazo > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999
41
> Purp rple le Lin ine Ext xten ensio sion, n, Secti tion
> BIF Grants Awarded: 29 > BIF Grant Amount Awarded: $780,320.11 > Number of small businesses awarded: 19 > BIF Business Advisor: Darrell Smith > Pacific Coast Regional Small Business Development Corporation (PCR) > Phone: 213.739.2999
42
43
Beverly Hills
44
Section 1
45
Section 1
46
Purp rple le Lin ine Ext xten ensio sion 24/7 Project Hotline - 213.922.6934 Email – purplelineext@metro.net On Metro ro Tra ransit See Something, Say Something 888.950.SAFE (7233) Constru ruct ction
fety y Aware renes ness s Pro rogr gram Glyssa Robles, Community Relations Officer Email: roblesgl@metro.net Phone: 323.900.2192 Cit ity of f Beve verl rly y Hil ills PurpleLine@beverlyhills.org Public Works Customer Service: 310.285.2467
47