  3. Project Schedule Overview - 2016 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Schematic Design Construction Design Development Documents Concept I Concept II Preliminary Public Hearing + SB Approval of Schematic Design Site Plan Council Hearing Development Special Use Permit (DSUP) Process Concept I (3 Op9ons) – Basic site plan with building footprint, parking/ circula3on, open spaces and approximate square footage and height • Final Site Plan Op3on endorsed by School Board May 19, 2016 Concept II – Refine layout, square footage, building height and materials, early u3lity studies, final number of parking spaces and vehicle/delivery access Preliminary Site Plan – Building architecture, final u3lity designs, site ligh3ng, landscaping and site scape www.acps.k12.va.us 3

  4. Project Update • Concept II Submission made on June 24 th • Selec3on of construc3on manager • Review of plans and systems with ACPS and RCPA Mechanical, electrical, plumbing • AV, IT, and Security • Food service and custodial • Educational • www.acps.k12.va.us 4

  5. Project Update – June 15 th Mee9ng What We Heard • Natural materials for exterior • Details of black box theatre • Parking details • Outdoor green roof spaces • Access to DSUP submissions • Comments on floor plans and site plan www.acps.k12.va.us 5

  6. Project Update – June 15 th Mee9ng What We’re Doing • Exterior of primarily brick and glass with metal panel accent • Mee3ngs with ACPS staff on black box theatre • Parking details under development • Green roof spaces being phased out by ACPS for safety and maintenance reasons • Plans provided for comment tonight www.acps.k12.va.us 6

  7. Project Update – Black Box Theatre What is a Black Box Theatre? • A black box is a bare room with a movable seating area, a • movable stage, and a Ulexible lighting system. Flexible use for instruc3on and performance • Music • Dance • Art display • Capacity of 75 – 150 spectators for in3mate performances • Allows for informal and formal performance • www.acps.k12.va.us 7

  8. Project Update – Black Box Theatre www.acps.k12.va.us 8

  9. Plans Review - Discussion • General comments within confines of Site Specific Program Document and Educa3onal Specifica3ons • Adjacencies • Opera3onal flow of facility NOT TO INCLUDE • Changes in program use • Changes to sizes of spaces www.acps.k12.va.us 9

  10. Plans Review – First Floor www.acps.k12.va.us 10

  11. Plans Review – Second and Third Floors www.acps.k12.va.us 11

  12. Plans Review – Site Plan www.acps.k12.va.us 12

  13. Plans Review – Site Plan www.acps.k12.va.us 13

  14. Plans Review – Site Plan www.acps.k12.va.us 14

  15. Plans Review – Site Plan www.acps.k12.va.us 15

  16. Plans Review – Development Areas • Access into Cafeteria from bus loop – revised loading for kitchen area • Pedestrian access off N. Latham Street (steps, ramps) • Incorpora3on of DSUP Review Comments in July www.acps.k12.va.us 16

  17. Next Steps – Advisory Group The Advisory Group will be involved in the following ways un3l the end of their year term (December 2016): • Keep community informed of the project and processes • Keep project team informed of community’s views • Provide comment on construc3on logis3cs and planning to maintain safe opera3ons of school and recrea3on center • Provide comment on general aspects such as exterior eleva3ons www.acps.k12.va.us 17

  18. Next Steps – Project Team • Onboarding of Construc3on Manager for es3ma3ng and constructability • Electronic project updates throughout the Summer • Board approval of schema3c design in August 2016 • Advisory Group Mee3ng in August • DSUP Completeness Submission in late August • Community Mee3ngs resume in September • Con3nua3on of itera3ve design process hPp://www.acps.k12.va.us/facili9es/ph/ www.acps.k12.va.us 18

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.