THORNTON MIDDLE SCHOOL CONVERSION BOARD UPDATE – May 20, 2020 Presented by: Kelle′ Lynch McMahon, Director of Facilities
FREMONT UNIFIED S C H O O L D I S T R I C T THORNTON MIDDLE SCHOOL - - PowerPoint PPT Presentation
FREMONT UNIFIED S C H O O L D I S T R I C T THORNTON MIDDLE SCHOOL CONVERSION BOARD UPDATE May 20, 2020 Presented by: Kelle Lynch McMahon, Director of Facilities 1 Project Overview 2 Updated Project Schedule Description 2020 2021
1
THORNTON MIDDLE SCHOOL CONVERSION BOARD UPDATE – May 20, 2020 Presented by: Kelle′ Lynch McMahon, Director of Facilities
2
3
Description M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D Inc 1 - Utilities Inc 3 - Play Fields Inc 2 - New Classrooms
Inc 3 - Modernization
Inc 4 - New Admin/Library
2020 2021 2022
4
Increment 1: Starts Summer 2020 Project Budget = $4,579,460 Includes;
Building (Value engineering in progress to address
CGS/DSA issues)
5
Increment 3 Fields: Summer 2020 Project Budget = $5,687,209 Includes;
6
Increment 3: Building Modernization and Parking, Starts Summer 2021 Project Estimate = $19,817,583 Includes;
Buildings
side of Campus
(Value engineering in progress to address ADA and existing conditions issues)
7
Increment 2: Starts Winter 2021 Project Budget = $35,932,022 Includes;
(Value engineering in progress to address CGS/DSA issues)
8
Increment 4: Starts Summer 2021 Project Budget = $9,984,524 Includes;
Building
(Value engineered to more efficiently deliver program)
9
10
Budget Challenges Additional geotechnical requirements from California Geologic Survey (CGS) Additional interior accessibility requirements Additional exterior Improvements to meet accessibility requirements Additional structural requirements at new buildings Unforeseen Conditions at Existing Buildings Additional Underground Utility Scope following video investigations Escalation of Increment 2 New Classroom Buildings
11
12
Board Approved Minimum Modernization Issues
New Buildings Requires CGS/DSA soils improvements, more extensive site utilities replacement and enhanced structural designs. Roofing No Issue Patch and Paint Ceilings and Walls Condition of classroom ceilings and walls worse than anticipated. Replace Asbestos Flooring Triggers DSA accessibility upgrades Accessibility Compliance in Restrooms and door hardware Triggers DSA exterior accessibility upgrades at classroom doors. Repair damaged beams No issues
13
Board Approved Minimum Modernization Issues
Replace broken windows and damaged louvers Replacement parts not available for louvers HVAC - Replace outdated units in kind Triggers DSA Title 24 upgrades Electrical – Replace/Repair non-functional or in poor condition Classroom lighting in poor condition, but not budgeted for lighting upgrades Plumbing – Replace or repair where necessary Triggers DSA Accessibility Replacements
Original Construction Budget $50,688,000 Current Construction Estimate $61,867,574
14