rix glankler early learning center
play

Rix-Glankler Early Learning Center Board Meeting January 22, 2020 - PowerPoint PPT Presentation

FREMONT UNIFIED S C H O O L D I S T R I C T Rix-Glankler Early Learning Center Board Meeting January 22, 2020 1 Background In the 1970s, FUSD purchased property and built the Rix school In 1985, FUSD sold property to Kidango


  1. FREMONT UNIFIED S C H O O L D I S T R I C T Rix-Glankler Early Learning Center Board Meeting January 22, 2020 1

  2. Background • In the 1970’s, FUSD purchased property and built the Rix school • In 1985, FUSD sold property to Kidango preschools • In July 2017, FUSD bought property back from Kidango • In February 2018, the Board approved the site renovation project budget of approximately $2.5 million • The original RIX project: • Renovate the existing buildings and site to accommodate the expansion of the Glankler Early Learning Center • Include Transitional Kindergarten (TK) • Seek State funding • Occupy by Fall 2019 2

  3. Background • Environmental, CDE, and DSA approval processes proceed • Project submitted to the Division of the State Architect (DSA) under the Rehabilitation (REH) process • DSA requires buildings to comply with current codes • DSA also requires a soils report and California Geological Survey (CGS) approvals • DSA’s required extensive structural upgrades costs exceed $14 million in project costs ($11.5 million over budget) 3

  4. Considerations • Alternate project approaches were explored as a result of DSA: • Rebuild site using modular buildings and demolish existing buildings • Pursue City of Fremont approvals instead of DSA (proposed approach) To pursue City of Fremont approvals, TK and state funding would • need to be excluded • Existing site and buildings have operated as a preschool through the City for decades by prior owner, Kidango • 5 of the 6 existing buildings were originally DSA approved, same as many of FUSD schools Existing buildings are City code compliant and no structural • upgrades required if no renovations • Any new renovations to the existing buildings would be subject to City approvals 4

  5. Current Progress • Presentations to site staff held on October 9 and December 11 • Received site concerns to meet basic program needs: Each classroom needs direct access to ADA restrooms • All educational spaces should be useable and ADA compliant • Equivalent storage to current classrooms • Secure canopy drop-off waiting area • Additional Staff parking • • Held meetings with District departments • Confirmed DSA not required for preschool • Clarified requirements from City of Fremont Building Department • Revised Option 1 to meet basic needs of Glankler program • Reviewed options with School Principal on January 16, 2020 5

  6. Option 1 • Exceeds original project budget of $2.5 million by $2.5 million for a new project budget of $5 million. • Omits transitional kindergarten • Waives state funding since not a DSA project • Add ADA restroom in each classroom • Add new staff parking lot • Add covered canopy and security fencing at drop-off area • Postpones occupancy to Fall 2021 • Additional scope as shown on following drawing 6

  7. Option 1 Budget includes infrastructure upgrade not limited to: Data, VOIP, Clock/Speakers, Cabling, and new marquee sign. Existing Fire Alarm will have minor modifications. 7

  8. Option 2 • Includes all scope in Option 1 • Exceeds original project budget of $2.5 million by $4 million for a new project budget of $6.5 million. • Enhanced scope provides more complete renovation • Additional scope as shown on following drawing (highlighted in yellow) • Postpones occupancy to Fall 2021 8

  9. Option 2 Budget includes infrastructure upgrade not limited to: Data, VOIP, Clock/Speakers, Cabling, and new marquee sign. Existing Fire Alarm will have minor modifications. 9

  10. Typical Classroom Building CONVERT EXISTING NON-ADA RESTROOMS INTO STORAGE TYPICAL CLASSROOMS: OPTION1: - REPAIR EXISTING CASEWORK - HAZARDOUS MATERIAL ABATEMENT IN AFFECTED AREAS (RESTROOMS AND 1 CLASSROOM) OPTION2: - HAZARDOUS MATERIAL ABATEMENT IN ENTIRE BUILDING - REPLACE FLOORING - REPLACE CASEWORK - REPLACE CEILING - REPLACE LIGHTING NEW ACCESSIBLE STUDENT RESTROOM WITH STORAGE AT EACH CLASSROOM 10

  11. Next Steps • Request Board approval of Option 1 and acceptance of budget increase 11

  12. Reference 12

  13. Existing Site Plan (Building Functions) 13

  14. 14

  15. 15

  16. 16

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend