FREMONT UNIFIED January 22, 2020 S C H O O L D I S T R I C T Centerville Middle School Conversion Drama Program Performance Space Site Plan Approved by the Board on June 26, 2019 2 Drama Classroom - Existing Drama Classroom: 1580sf;


slide-1
SLIDE 1

FREMONT UNIFIED

S C H O O L D I S T R I C T

Centerville Middle School Conversion

Drama Program Performance Space

January 22, 2020

slide-2
SLIDE 2

Site Plan

2

Approved by the Board on June 26, 2019

slide-3
SLIDE 3

Drama Classroom - Existing

3

Drama Classroom:

  • 1580sf; 450sf

performance area

  • Storage shared with

backstage area

  • Existing raised stage

and seating configuration not in DSA approved plans

  • Light and sound table

within seating area

  • Curtain separates

stage and seating area

slide-4
SLIDE 4

4

Option 1 – Original Schematic Design Presented to the Board 11/20/19

Highlights:

  • Acoustic improvements

to MPR for larger performances

  • Locker rooms

expanded in Bldg G

  • Art room in Bldg D
  • Drama room moves to

Bldg D

slide-5
SLIDE 5

5

Option 1 - Drama Classroom and Lockers Presented to the Board 11/20/19

Drama Classroom:

  • 1200sf; 430sf performance area; and 45-55 seat

capacity

  • 165sf of usable storage
  • No backstage area
  • No curtain

Locker Room Expansion:

  • (2) Locker Rooms at 1968 sf ea:
  • 772 Day Use Lockers ea
  • 255 PE Use Lockers ea
  • (2) Offices at 248 sf ea
  • (2) Storage at 255 sf ea
  • (2) Multi Occupant Restrooms and (2) Single

Occupant/Gender Neutral Restrooms MPR:

  • Acoustic improvements and portable lighting for

larger drama performances Design for drama meets approved Middle School Educational Specifications Scope of work is within current project budget

slide-6
SLIDE 6

Option 2 – Site Plan

6

Highlights:

  • Hardcourt space

extended

  • Square footage added to

Bldg G

  • Drama remains in Bldg G
  • Locker rooms expanded

in Bldg G

  • No improvements to

MPR

slide-7
SLIDE 7

7

Option 2 – Building Floor Plans

Drama Classroom:

  • 1580sf; 450 sf performance area; 50-60 seating capacity
  • 418 sf for backstage and storage
  • Curtain location in approximately same location as existing

Locker Room Expansion:

  • (2) Locker Rooms at 1,702 sf ea:
  • 772 Day Use Lockers ea
  • 255 PE Use Lockers ea
  • (2) Offices at 320 sf ea
  • (2) Storage at 265 sf ea
  • (2) Multi Occupant Restrooms and (2) Single Occupant/Gender Neutral

Restrooms MPR:

  • No improvements

Hardcourts:

  • Expansion to account for addition to Bldg G

Additional Cost: $3M Items to note:

  • Drama remains in current space
  • Smaller square footage for lockers than in SD option, no impact to locker

count

  • Creates additional flex lab in Bldg D
slide-8
SLIDE 8

Option 3 – Site Plan

8

Highlights:

  • Locker rooms

expanded in Bldg G

  • Drama moves to Bldg

D with larger sf

  • Art moves from Bldg D

to new modular

  • No improvements to

MPR

slide-9
SLIDE 9

9

Option 3 – Building Floor Plans

Drama Classroom:

  • In Bldg D, D2 and D3 combined to create larger space
  • 2,360 sf; 653 sf performance area; 85-95 seating capacity
  • Curtain locations to be developed
  • 240 sf for side stage
  • 318 sf for storage

Locker Room Expansion:

  • (2) Locker Rooms at 1,964 sf ea
  • 772 Day Use Lockers ea
  • 255 PE Use Lockers ea
  • (2) Offices at 250 sf ea
  • (2) Storage at 255 sf ea
  • (2) Multi Occupant Restrooms and (2) Single Occupant/Gender Neutral Restrooms

Art Room:

  • Moves to new modular
  • 1,440 sf

MPR:

  • No improvements

Additional Cost: $3.9M Items to note:

  • Drama room will have low ceiling and suboptimal sight lines
  • Drama program does not have history in this type of space
slide-10
SLIDE 10

10

Option 3 – Side View

slide-11
SLIDE 11

Next Steps

11

  • Complete Design Development phase
  • Develop phasing plan with Contractor, Construction Manager, and Site
  • Continue coordination of schedule, phasing, cost and constructability
slide-12
SLIDE 12

Reference Slides

12

slide-13
SLIDE 13

Centerville MS Campus

Original Design Direction/Goals for Conversion Project:

  • Student centric spaces for 6-8
  • 2 story Development
  • Update Centerville presence in community
  • Minimize Portables
  • Safe Student Drop-off
  • Outdoor learning spaces

Community/Board Input at 10/24/18 Meeting:

  • Expansion of Playfields
  • Space for Emergency Supplies
  • 2 story Development
  • Classrooms in New Construction
  • Minimize New Portables
  • Safe Student Drop-off

Updated Input from the District since then:

  • Old Enrollment Projections: 1822
  • Updated Enrollment Projections: 1545*

*Based on Jan 2019 Report to 2024/2025

  • Incorporation of Ed Specs

13