STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS SCHOOL BOARD INFORMATION MEETING 17 MARCH 2016 PROCESS STAKEHOLDER COLLABORATION 22 BLPC meetings 12 PFRC meetings 5 HALRB/DRC meetings/ work sessions
PROCESS
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 3
STAKEHOLDER COLLABORATION
- 22 BLPC meetings
- 12 PFRC meetings
- 5 HALRB/DRC meetings/
work sessions
- 2 Gallery Walks / Open
House
- Additional meetings
with community leaders, Department of Parks and Recreation, VDOT, Arlington County, and School Board Members.
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 4
WEST ADDITION WITH DRIVEWAY CONNECTION
APPROVED CONCEPT - 11/5/15
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 5
- 35,000 sf minimum
west addition
- Exit only driveway
connection onto Old Dominion Drive from Vacation Lane
- Expanded surface
parking ofg Vacation Lane to replace 50 spaces lost
- 144 parking spaces
BALL FIELD TENNIS COURTS BASKETBALL COURTS STRATFORD / HB WOODLAWN
- N. VACATION LANE
O L D D O M I N I O N / R O U T E 2 9 LORCOM LANE M I L I T A R Y R O A D
- N. VACATION LANE
2 3 R D S T R E E T N 22ND STREET N N
PLAYING FIELD C
LEGEND Property Line Phase 1 Parent Drop-off Possible Outdoor Learning Amenity Bus Drop-off New Building Entry
APPROVED CONCEPT SITE PLAN - 11/5/15
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 6
- No driveway
connection between Vacation Lane and Old Dominion Drive
- Provided in the
event that VDOT and/or Arlington County does not approve a vehicular exit at Old Dominion
BALL FIELD TENNIS COURTS BASKETBALL COURTS STRATFORD / HB WOODLAWN
- N. VACATION LANE
O L D D O M I N I O N / R O U T E 2 9 LORCOM LANE M I L I T A R Y R O A D
- N. VACATION LANE
2 3 R D S T R E E T N 22ND STREET N N
PLAYING FIELD C
LEGEND Property Line Phase 1 Parent Drop-off Possible Outdoor Learning Amenity Bus Drop-off New Building Entry
APPROVED ALTERNATIVE SITE PLAN - 11/5/15
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 7
APPROVED PROJECT COST AND FUNDING - 11/5/15
PROJECT COST (IN MILLIONS)
SITE WORK (RECOMMENDED SITE OPTION) $ 6.38 ADDITION (35,000 GSF) $ 17.56 RENOVATION $ 6.77 APS STAFF $ 0.55 TOTAL PROJECT COST $ 31.26
PROJECT FUNDING (IN MILLIONS) APS COUNTY TOTAL
BONDS $ 26.76 $ 0.00 $ 26.76 OTHER $ 0.80 $ 0.00 $ 0.80 JOINT FUND $ 1.85 $ 1.85 $ 3.70 TOTAL FUNDING $ 29.41 $ 1.85 $ 31.26
Note: Figures may not sum to totals due to rounding error.
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 8
- Total funding available for the project to range from a minimum of
$31.26 million to a maximum of $36.3 million.
- Additional costs beyond the $31.26 million maximum must be justifj
ed by the BLPC and APS stafg .
- Up to $250,000 of additional funding to be made available to provide
commemorative artwork/interpretation and signage regarding the historic signifj cance of the Stratford Building.
APPROVED PROJECT COST RANGE - 11/5/15
SCHEMATIC DESIGN
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 10
SITE AERIAL VIEW
- 40,000 sf addition
- Exit only driveway
connection from Vacation Lane to Old Dominion Drive
- Expanded surface
parking ofg Vacation Lane
- Renovation of
existing building to accommodate new program
- 144 parking spaces
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 11
DESIGN PRINCIPLES
- Accommodates program and provides quality learning environments
- Creates opportunity for new “heart of school”
- Connects to existing building circulation network
- Leaves existing historic building intact while interior renovations provide a unifj
ed Middle School
- Preserves views of historic south facades of existing building
- Maintains fm
- w from classroom wing to fj
eld
- Improves site circulation and accessibility for vehicles, bicycles and all pedestrians
- Provides a safer pedestrian experience with improvements to Vacation Lane
- Minimizes impact to Stratford Park renovation plan and schedule
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 12
SITE PLAN
DRIVEWAY CONNECTION TO OLD DOMINION
N . V A C A T I O N L A N E N 23RD ST OLD DOMINION DRIVE
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 13
ALTERNATE SITE PLAN
NO DRIVEWAY CONNECTION TO OLD DOMINION
N . V A C A T I O N L A N E N 23RD ST OLD DOMINION DRIVE
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 14
BASEMENT PLAN
- 0’
20’ 40’
N
LIBRARY FOOD SERVICE PHYSICAL EDUCATION THEATER/ARTS MUSIC TECHNOLOGY WORK & FAMILY STUDY BUILDING SUPPORT TEACHER & STORAGE ADMIN COUNSELING/CLINIC CORE CLASSROOMS SPECIAL EDUCATION ELECTIVE CLASSROOMS CIRCULATION ENTRANCE
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 15
FIRST FLOOR PLAN
- 0’
20’ 40’
N
LIBRARY FOOD SERVICE PHYSICAL EDUCATION THEATER/ARTS MUSIC TECHNOLOGY WORK & FAMILY STUDY BUILDING SUPPORT TEACHER & STORAGE ADMIN COUNSELING/CLINIC CORE CLASSROOMS SPECIAL EDUCATION ELECTIVE CLASSROOMS CIRCULATION ENTRANCE
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 16
SECOND FLOOR PLAN
0’ 20’ 40’
N
LIBRARY FOOD SERVICE PHYSICAL EDUCATION THEATER/ARTS MUSIC TECHNOLOGY WORK & FAMILY STUDY BUILDING SUPPORT TEACHER & STORAGE ADMIN COUNSELING/CLINIC CORE CLASSROOMS SPECIAL EDUCATION ELECTIVE CLASSROOMS CIRCULATION ENTRANCE
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 17
- THIRD FLOOR PLAN
0’ 20’ 40’
N
LIBRARY FOOD SERVICE PHYSICAL EDUCATION THEATER/ARTS MUSIC TECHNOLOGY WORK & FAMILY STUDY BUILDING SUPPORT TEACHER & STORAGE ADMIN COUNSELING/CLINIC CORE CLASSROOMS SPECIAL EDUCATION ELECTIVE CLASSROOMS CIRCULATION ENTRANCE
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 18
VIEW FROM OLD DOMINION
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 19
VIEW FROM EAST
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 20
SOUTH FACADE
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 21
ENTRY
HEART OF SCHOOL
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 22
COMMONS
HEART OF SCHOOL
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 23
MEDIA CENTER
HEART OF SCHOOL
PROGRAM
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 25
ED SPEC - PROGRAM BLOCKS - INITIAL CONCEPT
1,000 STUDENTS: EXISTING + 45,000 SF ADDITION
A d m i n C
- u
n s e l i n g S t u d e n t S e r v i c e s C l i n i c C a f e t e r i a T e a c h e r C
- l
a b L i b r a r y P e r f
- r
m i n g A r t C
- r
e C l a s s r
- m
A r t M u s i c W
- r
k & F a m i l y P E T e c h n
- l
- g
y E l e c t i v e S p e c i a l E d C u s t
- d
i a l B u i l d i n g S u p p
- r
t S t u d e n t S p a c e
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 26
A d m i n C
- u
n s e l i n g S t u d e n t S e r v i c e s C l i n i c C a f e t e r i a T e a c h e r C
- l
a b L i b r a r y P e r f
- r
m i n g A r t C
- r
e C l a s s r
- m
A r t M u s i c W
- r
k & F a m i l y P E T e c h n
- l
- g
y E l e c t i v e S p e c i a l E d C u s t
- d
i a l B u i l d i n g S u p p
- r
t S t u d e n t S p a c e
ED SPEC - PROGRAM BLOCKS - APPROVED CONCEPT
1,000 STUDENTS: EXISTING + 35,000 SF ADDITION
- Reduction of 10,000 gsf /
7,000 sf of program
- Renovated existing Media
Center in place
- Reduced Locker Rooms
- Reduced PE Storage and
Of ces
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 27
A d m i n C
- u
n s e l i n g S t u d e n t S e r v i c e s C l i n i c C a f e t e r i a T e a c h e r C
- l
a b L i b r a r y P e r f
- r
m i n g A r t C
- r
e C l a s s r
- m
A r t M u s i c W
- r
k & F a m i l y P E T e c h n
- l
- g
y E l e c t i v e S p e c i a l E d C u s t
- d
i a l B u i l d i n g S u p p
- r
t S t u d e n t S p a c e
ED SPEC - PROGRAM BLOCKS - SCHEMATIC DESIGN
1,000 STUDENTS: EXISTING + 40,000 SF ADDITION
- Increase of 5,000 gsf / 3,000 sf of
program
- New Media Center and Student
Commons
- Added Health Classroom
- Refj
nement to Ed Spec
- Added Special Ed Classroom
COST ANALYSIS
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 29
SCHEMATIC DESIGN COST ESTIMATE:
PROJECT COST ($ MILLIONS)
SITE WORK (DRIVEWAY OPTION) $ 8.15 ADDITION (40,000 SF) $ 20.14 RENOVATION $ 7.12 APS STAFF $ 0.55 TOTAL PROJECT COST $ 35.96 COMMEMORATIVE $ 0.25 $ 36.21
PROJECT FUNDING ($ MILLIONS) APS COUNTY TOTAL
BONDS $ 30.95 $ 0.00 $ 30.95 OTHER $ 0.80 $ 0.00 $ 0.80 JOINT FUND $ 2.11 $ 2.11 $ 4.21 TOTAL FUNDING $ 33.86 $ 2.11 $ 35.96
Note: Funding chart does not include commemorative budget
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 30
CONCEPT VS. SCHEMATIC BUDGET:
Library and Physical Education Programs + Heart of School = + 2.58 M Added site costs = + 1.77 M Additional accessibility improvements in new addition = + 0.35 M Total additional cost: + $4.7 M $ 0.3 M remaining of $5 M conditional additional funding
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 31
SCHEMATIC DESIGN ALTERNATES
POTENTIAL DEDUCT ALTERNATES (IN MILLIONS)
IMPLEMENT ALTERNATE (NO DRIVEWAY) SITE PLAN
- $ 0.23
NO NEW ELEVATOR AT EAST END OF THE BUILDING
- $ 0.35
PRE-FINISHED ALUM. PANEL / CEMENTITIOUS PANEL INSTEAD OF PRE-PATINATED COPPER
- $ 0.11
POTENTIAL DEDUCT ALTERNATES
The BLPC affi rmed that these elements should remain in the project.
QUINN EVANS ARCHITECTS
Arlington Public Schools Stratford Middle School - 32
SCHEMATIC DESIGN ALTERNATES
POTENTIAL ADD ALTERNATES (IN MILLIONS)
REPLACE EXISTING CEILINGS AND LIGHTING IN EXISTING INSTRUCTIONAL SPACES $ 1.30 ADD PHOTOVOLTAIC (PV) ARRAY TO AUXILIARY GYM ROOF $ 0.30 ADD GREEN ROOF TO AUXILIARY GYM ROOF $ 0.17 REPLACE ELEVATOR AT WEST END OF THE BUILDING $ 0.19 RESTORE GLASS BLOCK AT EXISTING CLASSROOMS (NOT INCLUDING HVAC) $ 0.51 GREYWATER SYSTEM $ 0.18
POTENTIAL ADD ALTERNATES
The BLPC identifi ed the highlighted item as the priority for spending remaining $$ within the funding available.