McKINLEY ELEMENTARY SCHOOL FINAL DESIGN REPORT | 01.22.2015 - - PowerPoint PPT Presentation

mckinley elementary school
SMART_READER_LITE
LIVE PREVIEW

McKINLEY ELEMENTARY SCHOOL FINAL DESIGN REPORT | 01.22.2015 - - PowerPoint PPT Presentation

McKINLEY ELEMENTARY SCHOOL FINAL DESIGN REPORT | 01.22.2015 RENOVATION AND ADDITION 1 McKinley Elementary School Renovation + Addition Final Design School Board Information January 22 nd 2015 Agenda 1. Project Schedule & Costs 2. Final


slide-1
SLIDE 1

McKINLEY ELEMENTARY SCHOOL

FINAL DESIGN REPORT | 01.22.2015 RENOVATION AND ADDITION 1

slide-2
SLIDE 2

Agenda

  • 1. Project Schedule & Costs
  • 2. Final Building Design
  • 3. Exterior Elevations
  • 4. Interior Views

McKinley Elementary School Renovation + Addition Final Design School Board Information

January 22nd 2015

slide-3
SLIDE 3

4

McKinley Elementary School Renovation and Addition

Project Schedule & Costs

3

slide-4
SLIDE 4

Grade Current Proposed Average Total # of Classrooms # of Classrooms Class Size Capacity Pre‐K 2 2 16.0 32.0 Kindergarten 4 4 23.3 93.2 Grade 1 5 4 23.3 93.2 Grade 2 4 4 23.3 93.2 Grade 3 5 4 23.3 93.2 Grade 4 4 Relocatables 4 23.3 93.2 Grade 5 3 Relocatables 4 23.3 93.2 Flex: k‐1 1 2 0.0 0.0 Flex 2‐5 1 4 23.3 93.2 Total # of classes 29 32 684.4

MORE SEATS FOR MORE STUDENTS :

4

slide-5
SLIDE 5

01

SCHEDULE :

PROJECT MILESTONES:

  • Concept Design ‐ School Board ‐ Information – Feb 6, 2014
  • Concept Design ‐ School Board ‐ Approval – Mar 6, 2014
  • Schematic Design to APS Board for Information– April 24, 2014
  • Schematic Design to APS Board for Action – May 8, 2014
  • Environmental Assessment Report – May, 2014
  • Design Development – July 15, 2014
  • Use Permit – September 2014
  • Construction Documents – November 30, 2014
  • Building Permit – February / March, 2015
  • Bidding – February 6, 2015
  • Construction – June 2015
  • Occupancy – September 2016

Exhibit: A Exhibit: A

5

slide-6
SLIDE 6

01

SCHEDULE :

PROJECT MILESTONES:

  • School Board Information item

January 22nd 2015

  • School Board Action Item

February 5th 2015

  • Issue Bid Documents

February 6th 2015

  • Open Bids

March 9th 2015

  • School Board Contract Award

March 19th 2015

  • Notice To Proceed

March 26th 2015

  • Building Permits

June / July 2015

  • Construction Start

June 22nd 2015

  • Occupancy

September 5th 2016

Exhibit: A Exhibit: A

6

slide-7
SLIDE 7

54

McKinley Elementary School Renovation and Addition

DEDUCT ALTERNATES

  • 1 ‐ Leave Existing Lighting In Minor Renovation

($133,780.44)

  • 2 ‐ Leave Existing Plumbing In Minor Renovation

($33,126.92)

  • 3 ‐ Leave Existing Casework In Minor Renovation

($111,350.27)

  • 4 ‐ Leave Existing Flooring In Area E

($44,864.02)

  • 5 ‐ Minimize Scope In Area A

($67,553.29)

  • 6 ‐ Minimize Scope In Area E

($127,837.53) ALTERNATES TOTAL ($518,512.47) * Communty Amenities funding to be finalized with County Staff prior to final approval

SUMMARY OF PROJECT COSTS: Cost Estimate

SCHEMATIC DESIGN FINAL DESIGN New Construction $ 8,100,000 $ 8,001,668 Renovations $ 3,450,000 $ 5,009,850 Site Work $ 2,100,000 $ 2,100,352 Contingencies $ 2,000,000 $ 1,101,130 Escalation $ 730,000 $ 300,000 Soft Costs $ 3,720,000 $ 3,587,000 Subtotal $ 20,100,000 $ 20,100,000 Community Amenities $ ‐ $ 750,000* TOTAL PROJECT COST $ 20,100,000 $ 20,850,000

7

slide-8
SLIDE 8

* Communty Amenities funding to be finalized with County Staff prior to final approval

SUMMARY OF PROJECT COSTS: Funding Sources

Funding authorized in 2012 / 2014 Bonds $ 17,600,000 Funding authorized from the 2010/2012 HVAC‐Roofing Bonds $ 1,866,500 Funding authorized from the 2015 MC/MM Fund $ 285,450 Funding authorized from the 2016 MC/MM Fund $ 348,050 TOTAL APS FUNDING PROPOSED FOR THE MCKINLEY PROJECT $ 20,100,000 Joint ACG/APS Fund (Community Amenities) $ 750,000* TOTAL PROJECT FUNDING $ 20,850,000

8

slide-9
SLIDE 9

* Communty Amenities funding to be finalized with County Staff prior to final approval

SUMMARY OF PROJECT COSTS: Proposed joint ACG / APS funded Items

  • New McKinley Road crosswalk: (Safe routes to school)

$35,392

  • New 11th street access ramp: (Safe routes to school)

$53,048

  • Streetscape improvments along McKinley Rd

$84,388

  • County emergency repeater system

$156,918

  • Fire access lane

$35,000

  • Fire access wet standpipe lane

$15,000

  • Utility Undergrounding

$133,000

  • New fire hydrant @ 11th street

$7,500

  • ConnectArlington Conduit

$68,575

  • Construction Contingency

$23,424

  • Soft Costs: 22.5%

$137,755 Subtotal McKinley $750,000

9

slide-10
SLIDE 10

01

Project Specific Costs Items: BEYOND THE

NORM

  • Strom Water Management: McKinley Elementary

school has some significant storm water drainage issues. These will be corrected through enhanced storm water management.

  • Steep terrain: The 60 foot grade change across the site,

(5 stories high) results in a high number of retaining walls.

  • Pentagon Wing Replacement: The unanticipated

replacement of the pentagon wing results in an increased scope of work.

  • Site Accessibility & Community improvements: The

proposed new off campus cross walk on McKinley Road and new accessible ramp from 11th street are scope of work increases.

  • Site Landscaping: Through creative design of the new

storm water management system, several existing trees may be saved. However, additional piping, landscaping and other measures are required.

10

slide-11
SLIDE 11

01

McKinley Ashlawn Projected new school total area: 95,780 97,363 Sq. Ft. Projected area of new addition; Including pentagon replacement: 34,225 28,010 Sq. Ft.

  • Cost per square foot of total building:

$209.86 $209.53

  • Cost per square foot of new addition only:

$413.24 $468.09

  • Cost per total new projected school capacity: $29,385.96 $29,781.02

(684 seats new school capacity)

  • Cost per seat new added capacity:

$83,402.49 $90,999.67 (684 seats projected – 443 seats current)

Unit Project Costs:

11

slide-12
SLIDE 12

01

Risk Management:

POTENTIAL RISK EXPOSURE ITEMS

  • Building Permit Conditions:

Building Permit requirements causing additional costs

  • Challenging Project Schedule:

Occupied renovations necessitating a tight construction schedule controls, a slip the schedule can result in project delays

  • Storm Water Management:

Additional costs and compliance with new MS4 stormwater permit and resulting learning process for APS, County and State stakeholders

  • Improved Market Costs:

A continued resurgence of the construction sector, translating to potential General Constrictors being more conservative with Bid numbers

  • Off site improvements:

Improvements to McKinley Boulevard cross walk and striping and accessible ramp from 11th Street

  • Unforeseen renovation issues:

Abatement, connections to existing systems, existing construction anomalies and other unforeseen circumstances

12

slide-13
SLIDE 13

FINAL BUILDING DESIGN

13

slide-14
SLIDE 14

SITE AREA: 7.54 Acres PARKING: 36 Spaces on site 26 Spaces along McKinley Road STUDENT DROP OFF ZONE: Along McKinley Road (North of Site Driveway) RELOCAT ABLE CLASSROOMS: 3 Buildings on site SITE AMENITIES: 2 Playgrounds Paved Play Area Outdoor Classroom Rain Garden SITE GRADE: High Point (South): +346.0’ Low Point (North): +280.0’

SITE OVERVIEW

EXISTING SITE PLAN

14

slide-15
SLIDE 15

Concept Design 4 Concept Design 3 Concept Design 2 Concept Design 1

CONCEPT + SCHEMATIC DESIGN

SITE DESIGN PROGRESSION

15

slide-16
SLIDE 16

CONCEPT + SCHEMATIC DESIGN

SITE PLAN

EXTERIOR MA TERIALS red brick colored accent glass cement panel

3 STORY CLASSROOM ADDITION 1 STORY CLASSROOM ADDITION 1 STORY ENTRY ADDITION

16

slide-17
SLIDE 17

FINAL DESIGN

SITE PLAN

LANDSCAPE CONCEPT The site development and landscape improvements for McKinley Elementary School focus on creating new outdoor activity and learning spaces and preserving open space.

17

slide-18
SLIDE 18

FINAL DESIGN

FLOOR PLAN MAIN LEVEL: 319’-4”

3 STORY CLASSROOM ADDITION

1ST 1ST 1ST 1ST 2ND

FLE X

2ND

MEDIA CENTER - MAJOR RENOVA TION

2ND

DINING - MAJOR RENOVA TION

2ND

1 STORY ENTRY ADDITION

FLE X PRE- K

K K

PRE- K

K K 3RD 3RD 3RD 3RD

FLE X FLE X

1 STORY CLASSROOM ADDITION

18

slide-19
SLIDE 19

FINAL DESIGN

3 STORY CLASSROOM ADDITION, MAIN LEVEL: 319’-4”

AR T VOCAL MUSIC INSTRUMENT AL MUSIC SMALL GROUP INSTRUCTION

19

slide-20
SLIDE 20

FINAL DESIGN

3 STORY CLASSROOM ADDITION, GYM LEVEL: 307’-2”

GYM ST AGE SMALL GROUP INSTRUCTION 4TH GRADE CLASSROOM FLEX CLASSROOM

20

slide-21
SLIDE 21

FINAL DESIGN

3 STORY CLASSROOM ADDITION, FIELD LEVEL: 293’-2”

5TH GRADE CLASSROOM FLEX CLASSROOM

21

slide-22
SLIDE 22

FINAL DESIGN

MEDIA CENTER - MAJOR RENOVATION, MAIN LEVEL:

CIRCULA TION DESK ST ACKS COMPUTERS STORY TELLING SMALL STORY TELLING MEDIUM STORY TELLING LARG E

22

319’-4”

slide-23
SLIDE 23

ARLINGTON PUBLIC SCHOOLS

FINAL DESIGN REPORT | 01.22.2015

FINAL DESIGN

DINING - MAJOR RENOVATION, MAIN LEVEL: 319’-4”

KITCHEN BUIL T IN SEA TS, TYPICAL QUIET DINING ZONE DINING

23

slide-24
SLIDE 24

FINAL DESIGN

1 STORY ENTRY ADDITION, MAIN LEVEL: 319’-4”

MAIN ENTRY RECEPTION ASST . PRINCIPAL PRINCIPAL COUNSELOR PSYCHOLOGIS T

24

slide-25
SLIDE 25

FINAL DESIGN

1 STORY CLASSROOM ADDITION, MAIN LEVEL: 319’-4”

GIFTED RESOURCE TEACHER 3RD GRADE CLASSROOM SMALL GROUP INSTRUCTION

25

slide-26
SLIDE 26

EXTERIOR VIEWS

26

slide-27
SLIDE 27

FINAL DESIGN NORTHEAST VIEW 3 STORY ADDITION

27

slide-28
SLIDE 28

FINAL DESIGN EAST ELEVATION 3 STORY ADDTITION

28

slide-29
SLIDE 29

North Perspective

CONCEPT + SCHEMATIC DESIGN NORTH ELEVATION OF 3 STORY ADDITION

29

slide-30
SLIDE 30

CONCEPT + SCHEMATIC DESIGN NORTH ELEVATION OF 3 STORY ADDITION

30

slide-31
SLIDE 31

CONCEPT + SCHEMATIC DESIGN NEW 1 STORY MAIN ENTRY

31

slide-32
SLIDE 32

FINAL DESIGN

COMMUNITY ENTRANCE

32

slide-33
SLIDE 33

FINAL DESIGN

NEW 1 STORY MAIN ENTRY

33

slide-34
SLIDE 34

INTERIOR VIEWS

34

slide-35
SLIDE 35

FINAL DESIGN

INTERIOR DESIGN CONCEPT

MAIN STREET , MAJOR ACCESS LOCA TIONS FOR TEMPORARY ART LOCA TIONS FOR PERMANENT ART ADDED TRANSPARENCY COLLABORA TIVE BREAKOUT SPACE

35

slide-36
SLIDE 36

FINAL DESIGN

MAIN ENTRY / MAIN STREET

36

slide-37
SLIDE 37

FINAL DESIGN

3 STORY ADDITION, MAIN LEVEL CORRIDOR - COLLABORATION | ART | PERFORMANCE

37

slide-38
SLIDE 38

FINAL DESIGN

3 STORY ADDITION, GYM LEVEL CORRIDOR - COLLABORATION | ART | PERFORMANCE

38

slide-39
SLIDE 39

FINAL DESIGN

COMMUNITY ENTRANCE

39

slide-40
SLIDE 40

FINAL DESIGN

COMMUNITY ENTRANCE - SECTION PERSPECTIVE

40

slide-41
SLIDE 41

FINAL DESIGN

GYMNASIUM + STAGE

41

slide-42
SLIDE 42

FINAL DESIGN

GYMNASIUM LOOKING NORTH

42

slide-43
SLIDE 43

FINAL DESIGN

DINING LOOKING EAST

43

slide-44
SLIDE 44

FINAL DESIGN

DINING LOOKING WEST

44

slide-45
SLIDE 45

FINAL DESIGN

MEDIA CENTER

45

slide-46
SLIDE 46

ARL

FINAL DESIGN

WAY FINDING, FLOOR MATERIALS + ACCENTS

PRE K + K 1 STORY CLASSROOM ADDITION 3 STORY CLASSROOM ADDITION

1ST GRADE 2ND GRADE 5TH GRADE 4TH GRADE 3RD GRADE

PT

GYM, MUSIC + ART

FT

FIELD COLORS

CPT

MEDIA CENTER CORRIDOR WAINSCOTS

FT FT CPT FT FT FT PT PT PT PT PT PT PT

FT

  • LINOLEUM FLOOR

TILE CPT - CARPET TILE PT

  • WALL

PAINT

46

slide-47
SLIDE 47

2000 Duke Street Suite 105 Alexandria, VA 22314 571.388.7761 www.hcm2.com 750 East Pratt Street Suite 1100 Baltimore, MD 21202 410.837.7311 www.hcm2.com

McKINLEY ELEMENTARY SCHOOL

FINAL DESIGN REPORT | 01.22.2015 RENOVATION AND ADDITION 47