Wickersham Elementary School –Renovation / Addition Initial Presentation
Wickersham Elementary School School Board Presentation October 8, - - PowerPoint PPT Presentation
Wickersham Elementary School School Board Presentation October 8, - - PowerPoint PPT Presentation
Wickersham Elementary School Renovation / Addition Initial Presentation Wickersham Elementary School School Board Presentation October 8, 2019 Wickersham Elementary School - Site Plan Concept 2 Wickersham Elementary School Option A Gym
SLIDE 1
SLIDE 2
2
Wickersham Elementary School - Site Plan Concept
SLIDE 3
3
Wickersham Elementary School Option A – Gym Addition
SLIDE 4
4
Wickersham Elementary School – Option A 3D View
SLIDE 5
5
Wickersham Elementary School Option B – Classroom Addition
SLIDE 6
6
Wickersham Elementary School – Option B 3D View
SLIDE 7
7
Wickersham Elementary School – Draft Schedule
SLIDE 8
8
Wickersham Elementary School – Cost Estimate
PHASE III CONSTRUCTION PROJECTS – WICKERSHAM ELEMENTARY SCHOOL - Renovations / Additions
Renovated Square Footage Cost per SF New Construction Square Footage Cost per SF Final Build-Out Square Footage Construction Costs Project Cost Multiplier Project Cost 51,450 SF $192.00 15,900 SF $290.50 67,350 SF $14,497,350 116% $16,816,926
SLIDE 9
9
Questions / Discussion
SLIDE 10
10
Wickersham Elementary School – Phasing Option
Phasing Options
- 1. Occupied renovation / addition.
- 2. Modular Classrooms on site, use common spaces.
- 3. Investigate possible use of existing Buchanan ES.
SLIDE 11