STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS PFRC JANUARY 24, 2017 PROJECT UPDATE AND SCHEDULE | 1 PROJECT SCHEDULE 2016 2017 2018 2019 USE PERMIT 2/2017 CERT. OF APPROP. 2/2017 DESIGN DEV. CONST. DOCS.


  1. STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS PFRC JANUARY 24, 2017

  2. PROJECT UPDATE AND SCHEDULE | 1

  3. PROJECT SCHEDULE 2016 2017 2018 2019 USE PERMIT 2/2017 CERT. OF APPROP. 2/2017 DESIGN DEV. CONST. DOCS. BUILDING PERMIT Fall 2017 CONSTRUCTION SCHOOL OPEN Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 3

  4. PROJECT MILESTONES • Concept Design approved November 2015 • Schematic Design approved June 2016 • Use Permit submitted: September 8, 2016 • EA submitted: September 8, 2016 • Water Quality Impact Assessment submitted: September 15, 2016 • Certifj cate of Appropriateness submitted: September 22, 2016 • Presenting to Commissions: (Fall/Winter 2016/2017) • Resubmission of Use Permit / COA: December 21, 2016 • County Board (projected): March 2017 • Building Permit (projected): Fall 2017 Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 4

  5. STAKEHOLDER INVOLVEMENT • 23 BLPC meetings • 13 PFRC meetings • 7 HALRB/DRC meetings/work sessions • 2 Gallery Walks / Open Houses • Additional meetings with: • Community leaders • Department of Parks and Recreation • VDOT • Arlington County • School Board Members Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 5

  6. USE PERMIT UPDATE | 2

  7. USE PERMIT MILESTONES • Use Permit: September 8, 2016 / December 21, 2016 • Environmental Assessment: September 8, 2016 • Water Quality Impact Assessment: September 15, 2016 • Certifj cate of Appropriateness: September 22, 2016 / December 21, 2016 • Commission Presentations: • E2C2 - September 26, 2016 • Urban Forestry - October 27, 2016 • HALRB - December 21, 2016 • Parks and Recreation - TBD • Transportation - TBD • Planning - TBD • County Board - March 18, 2017 Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 7

  8. USE PERMIT COMMENT AND RESPONSE • Stormwater approach • Vacation Lane sidewalks • Coordination with DPR • Historic/COA • Real Estate Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 8

  9. STORMWATER MANAGEMENT PLAN WWW.QUINNEVANS.COM STRATFORD MIDDLE SCHOOL RENOVATION & ADDITION 4100 Vacation Ln, Arlington, VA 22207 QEA # 31406600 WATER QUALITY DRAINAGE AREA MAP USE PERMIT 09/08/2016 REVISIONS NO. DESCRIPTION DATE A REVISION 12/21/2016 C-610 ARLINGTON, VIRGINIA DEPARTMENT OF ENVIRONMENTAL SERVICES STRATFORD MIDDLE SCHOOL 4100 VACATION LANE, ARLINGTON, VA 22007 SCALE: AS NOTED DESIGNED: K.RYAN CHECKED: S.PANDISH 1 4 7 9 10 8 11 Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 9

  10. VACATION LANE SIDEWALK EXISTING SIDEWALK PROPOSED SIDEWALK • PROPOSED • EXISTING Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 10

  11. NEW ADDITION Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 11

  12. HISTORIC COMMITTEE UPDATE | 3

  13. HISTORIC COMMITTEE • Committee kickofg was on January 11, 2017 • Determine how to best recognize history of site while respecting the building/site design process and timeline • T ree stages: • Exploration and Discovery • Analysis and Evaluation • Expression and Design • Interpretive Planner to be chosen shortly • Present concept to School Board in late spring/early summer 2017 Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 13

  14. SITE PLAN Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 14

  15. HISTORIC PATH 302 STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. SEAT WALL WITH INTERPRETIVE 300 SIGN INTEGRATED. SEE CHARACTER TW 303.50 IMAGE 3/SHEET L2.0H. TW 306.50 TW 302.50 2 9 1 . 6 0 (26) PROPOSED TW 306.50 298 BIKE RACKS OLD DOMINION ROAD TW 300.50 9 7 . 7 0 292 296 2 9 4 . 0 0 2 9 2 T W 2 9 4 . 2 294 TW 304.50 5 9 5 . 2 0 TW 294.25 1 0 9 5 . 9 5 . 2 0 294 TW 296.00 2 9 6 TW 299.50 TW 303.50 296 TW 291.17 BIOFILTER 290 290 TS 291.75 T 288 TW 300.50 9 7 . 7 0 TW 289.85 286 298 CONCRETE RETAINING WALLS. TS 285 306 2 8 4 304 SEE DETAIL 1/L4-1H. 282 BS 280.75 300 280 ADA PATH CHANGED TO FLAGSTONE TW 302.50 TW 302.50 AT POINTS WHERE IT CROSSES THE TW 306.50 HISTORIC PATH. SEE CHARACTER 302 SEE DETAIL 2/L4-1H. IMAGE 2/SHEET L2.0H. LOW WALL WITH INTEGRATED SEATING, TYP. 304 SEE CHARACTER IMAGE 2/SHEET L2.0H. 302 300 298 296 294 TW 306.50 292 290 288 286 284 282 3 0 6 308 FIELD STONE MARKERS RECALL ORIGINAL 3 PATH STUDENTS TOOK ON INTEGRATION DAY 1 0 TO ENTER THE SCHOOL. SEE CHARACTER IMAGE 2/SHEET L2-0H. STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. 312 SEE CHARACTER IMAGE 1/SHEET L2-0H. 310 312 Peirce Mill, QEA Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 15

  16. HISTORIC PATH A 302 STONE BOULDER WITH MARKER FOR INTERPRETATION OF HISTORIC PATHWAY. SEE CHARACTER IMAGE 1/SHEET L2-0H. SEAT WALL WITH INTERPRETIVE 300 SIGN INTEGRATED. SEE CHARACTER TW 303.50 A IMAGE 3/SHEET L2.0H. TW 306.50 TW 302.50 2 9 1 . 6 0 (26) PROPOSED TW 306.50 298 BIKE RACKS OLD DOMINION ROAD TW 300.50 9 7 . 7 0 292 296 2 9 4 . 0 0 2 9 2 T W 2 9 4 . 2 294 TW 304.50 5 9 5 . 2 0 TW 294.25 1 0 9 5 . 9 5 . 2 0 294 TW 296.00 2 9 6 TW 299.50 TW 303.50 296 TW 291.17 BIOFILTER B 290 290 TS 291.75 T 288 TW 300.50 9 7 . 7 0 TW 289.85 286 298 CONCRETE RETAINING WALLS. TS 285 306 2 8 4 304 SEE DETAIL 1/L4-1H. 282 C BS 280.75 300 280 B ADA PATH CHANGED TO FLAGSTONE TW 302.50 TW 302.50 AT POINTS WHERE IT CROSSES THE TW 306.50 HISTORIC PATH. SEE CHARACTER 302 SEE DETAIL 2/L4-1H. C IMAGE 2/SHEET L2.0H. LOW WALL WITH INTEGRATED SEATING, TYP. 304 SEE CHARACTER IMAGE 2/SHEET L2.0H. 302 300 298 296 294 TW 306.50 292 290 B 288 286 284 282 3 0 6 308 FIELD STONE MARKERS RECALL ORIGINAL 3 PATH STUDENTS TOOK ON INTEGRATION DAY 1 0 TO ENTER THE SCHOOL. SEE CHARACTER IMAGE 2/SHEET L2-0H. C STONE BOULDER WITH MARKER FOR A INTERPRETATION OF HISTORIC PATHWAY. 312 SEE CHARACTER IMAGE 1/SHEET L2-0H. 310 312 Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 16

  17. BUILDING SECTION OPPORTUNITY FOR COMMEMORATION AT HEART OF SCHOOL FEATURE WALL ������������������������������� � � ����������������������� ����������� ������������������� ������������� ������������� �������������� �������������� ���������������� ������������� ������������� ������������� �������� ������ ������������� ���������������������� ������������ ������������� ������ ��������� ������� ������������ �������������� ��������� �������������� ������������� ����� � ������������ ����������� ������������� Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 17

  18. CONSTRUCTION PHASING | 4

  19. CONSTRUCTION PHASING • Possible Scope for Early Construction Work: • Expanded Vacation Lane parking lot • Construction entrance at Old Dominion Drive • Considerations • Minimize impact to Stratford Program • Field access during 2018 spring season • Construction access and routes • Separating school and construction zones Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 19

  20. CONSTRUCTION SCHEDULE • Construction Schedule Milestones • GMP Fall 2017 • Early Work Phase - January 2018 • Construction Start - June 2018 • Completion - August 2019 Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.