STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS SCHOOL BOARD ACTION MEETING 02 JUNE 2016 SITE AERIAL VIEW EXHIBIT A 40,000 sf addition Exit only driveway connection from Vacation Lane to Old Dominion Drive


  1. STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS SCHOOL BOARD ACTION MEETING 02 JUNE 2016

  2. SITE AERIAL VIEW EXHIBIT A • 40,000 sf addition • Exit only driveway connection from Vacation Lane to Old Dominion Drive • Expanded surface parking ofg Vacation Lane • Renovation of existing building to accommodate new program • 144 parking spaces Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 2

  3. SITE PLAN EXHIBIT B DRIVEWAY CONNECTION TO OLD DOMINION N 23RD ST OLD DOMINION DRIVE N . V A C A T I O N L A N E Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 3

  4. ADA PATH FROM OLD DOMINION Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 4

  5. VACATION LANE IMPROVEMENTS EXHIBIT C Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 5

  6. BASEMENT PLAN EXHIBIT D �� LIBRARY TEACHER & STORAGE FOOD SERVICE ADMIN PHYSICAL EDUCATION COUNSELING/CLINIC THEATER/ARTS N CORE CLASSROOMS 20’ 0’ 40’ MUSIC SPECIAL EDUCATION TECHNOLOGY ELECTIVE CLASSROOMS WORK & FAMILY STUDY CIRCULATION Arlington Public Schools BUILDING SUPPORT ENTRANCE QUINN EVANS ARCHITECTS Stratford Middle School - 6

  7. FIRST FLOOR PLAN EXHIBIT E �� �� LIBRARY TEACHER & STORAGE FOOD SERVICE ADMIN PHYSICAL EDUCATION COUNSELING/CLINIC THEATER/ARTS N CORE CLASSROOMS 20’ 0’ 40’ MUSIC SPECIAL EDUCATION TECHNOLOGY ELECTIVE CLASSROOMS WORK & FAMILY STUDY CIRCULATION Arlington Public Schools BUILDING SUPPORT ENTRANCE QUINN EVANS ARCHITECTS Stratford Middle School - 7

  8. SECOND FLOOR PLAN EXHIBIT F LIBRARY TEACHER & STORAGE FOOD SERVICE ADMIN PHYSICAL EDUCATION COUNSELING/CLINIC THEATER/ARTS N CORE CLASSROOMS 20’ 0’ 40’ MUSIC SPECIAL EDUCATION TECHNOLOGY ELECTIVE CLASSROOMS WORK & FAMILY STUDY CIRCULATION Arlington Public Schools BUILDING SUPPORT ENTRANCE QUINN EVANS ARCHITECTS Stratford Middle School - 8

  9. THIRD FLOOR PLAN EXHIBIT G �� �� �� �� �� �� �� LIBRARY TEACHER & STORAGE FOOD SERVICE ADMIN PHYSICAL EDUCATION COUNSELING/CLINIC THEATER/ARTS N CORE CLASSROOMS 20’ 0’ 40’ MUSIC SPECIAL EDUCATION TECHNOLOGY ELECTIVE CLASSROOMS WORK & FAMILY STUDY CIRCULATION Arlington Public Schools BUILDING SUPPORT ENTRANCE QUINN EVANS ARCHITECTS Stratford Middle School - 9

  10. COST ESTIMATE EXHIBIT H PROJECT COST ($ MILLIONS) 1 SITE WORK $ 8.15 ADDITION $ 20.14 RENOVATION $ 7.12 APS STAFF $ 0.55 EXPAND SCOPE OF LIGHTING REPLACEMENT 2 $ 0.34 SUBTOTAL PROJECT COST 3 $ 36.30 HISTORIC COMMEMORATION ALLOWANCE $ 0.25 TOTAL PROJECT COST $ 36.55 NOTES: 1. Based on two independent professional cost estimates. 2. Recommended to enhance Universal Design, improve the quality of the instructional environment, and reduce energy. 3. Matches maximum approved by the School Board at Concept Design. Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 10

  11. FUNDING AVAILABLE EXHIBIT J PROJECT FUNDING ($ MILLIONS) MAJOR CONSTRUCTION BONDS $ 31.29 CAPITAL RESERVE 1 $ 0.25 OTHER 2 $ 0.80 SUBTOTAL $ 32.34 COUNTY/SCHOOL BOARD JOINT FUND APS FUNDING $ 2.11 COUNTY FUNDING $ 2.11 SUBTOTAL JOINT FUND $ 4.21 GRAND TOTAL FUNDING AVAILABLE 3 $ 36.55 NOTES: 1. Funding source for historic commemoration allowance. 2. Furniture and equipment that cannot be bond funded. 3. Figures may not total due to rounding. Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 11

  12. JOINT FUND ITEMS EXHIBIT K JOINT FUND OPTIONS ($ MILLIONS) ESTIMATE 1 # DESCRIPTION ROADWAY CONNECTION BETWEEN VACATION LANE 1 AND OLD DOMINION DRIVE INCLUDING FIRE ACCESS $ 2.15 IMPROVEMENTS 2 VACATION LANE IMPROVEMENTS $ 1.02 3 SIGNAL AT OLD DOMINION DRIVE $ 0.51 4 UTILITY UNDERGROUNDING $ 0.25 5 EMERGENCY RESPONDER NETWORK $ 0.25 PUBLICLY ACCESSIBLE RESTROOM ADJACENT TO 6 $ 0.03 STRATFORD PARK TOTAL $ 4.21 NOTES: 1. Includes construction, soft, and contingency costs. Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 12

  13. MILESTONE DATES • Use Permit Submission - July 2016 • Use Permit Approval - November 2016 • Final Design - June 2017 • School Opening - September 2019 Arlington Public Schools QUINN EVANS ARCHITECTS Stratford Middle School - 13

  14. STRATFORD MIDDLE SCHOOL RENOVATION AND ADDITION ARLINGTON PUBLIC SCHOOLS SCHOOL BOARD ACTION MEETING 02 JUNE 2016

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.