Arlington Career Center
Summer Work 2019
May 9, 2019
Arlington Career Center Summer Work 2019 May 9, 2019 Agenda - - PowerPoint PPT Presentation
Arlington Career Center Summer Work 2019 May 9, 2019 Agenda Enrollment growth at Arlington Tech Summer 2019 work Career Center Expansion Project 2 Enrollment Growth at Arlington Tech Arlington Tech growth will reach 600 students
Summer Work 2019
May 9, 2019
Agenda
2
Enrollment Growth at Arlington Tech
3
Career Center Students 2018-19 Enrollment Seats for Future Classes
2019-20 2020-21 2021-22 2022-23
Total 1,018 1,197 1,319 1,403 1,451
Arlington Tech Students (-grads/+9th grade)
196 346
(-0/+150)
468
(-28/+150)
552
(-66/+150)
600
(-102/+150)
Other Full-Time Students
171 200 200 200 200
Part-Time CTE
651 651 651 651 651
school year 2022-23
Strategies for Increasing Arlington Tech to 600 Students
so that it can be used by Arlington Tech during the school day and the Library at other times
used as swing space to allow moderate and larger interior renovation projects to continue into the school year if necessary
coordinated with the overall concept design for the Career Center Expansion Project to be approved by the School Board in March 2020
the overall concept design for the Career Center Expansion to be approved by the School Board in March 2020
construction of a third floor over the two-story section of the Career Center as soon as possible, and before receiving the Use Permit for the overall Career Center Expansion project in 2021, using remaining funding already approved in the FY 2017-26 and FY 2019-28 CIPs, and possibly additional funding approved in the FY 2021-30 CIP; earliest likely delivery date September 2022
4
Summer 2019 Plans in Preparation for 2019-20 Current Conditions
internal renovations to add capacity have been completed.
through major internal renovations is possible but must be coordinated with the concept design for the Career Center Expansion Project.
5
September 2019 Needs
additional Arlington Tech students.
spaces (relocatables).
service model comparable to other high schools.
Update on Summer 2019 Work
contractor before school opens.
renovations posted on April 15, 2019; due on May 14, 2019.
Services.
relocatable classrooms.
6
Summer Work 2019 Next Steps
May 23, 2019: School Board Information:
(will include a budget update for total anticipated summer 2019 expenses) June 6, 2019: School Board Action or Consent:
June 24, 2019:
7
Career Center Expansion Project
(CIP) includes two projects at the Career Center site:
start of school September 2021 for a maximum total project cost of $18,750,000, bringing the total capacity of Arlington Tech to 600 seats.
field and parking garage by start of school 2023 and 800-seat addition with performing arts facility by start of school September 2025 for a maximum total project cost of $184,700,000.
Phase of the Career Center Expansion Project which will include both CIP projects.
8
Potential Changes in FY 2021-30 CIP
Changes in enrollment projections, new information and opportunities, and design proposals developed during the BLPC/PFRC process often cause the funding, timing and phasing of CIP projects that have not proceeded beyond the Concept or Schematic Design phases to change in the next CIP adopted by the School Board. Given continued changes in enrollment growth, and the complexities,
BLPC, PFRC and staff will recommend some changes to the funding, timing and phasing of the Arlington Tech and Career Center capital projects in the FY 2021-30 CIP.
9
Career Center Expansion Updates
Manager at-Risk (CMR) on April 11, 2019; qualifications due May 9, 2019.
to support the concept design phase.
(CCWG):
Casey https://www.apsva.us/wp-content/uploads/2019/05/190501_CampCasey_FinalReport.pdf .
Transportation Analysis (MMTA); work has commenced and is scheduled to be largely complete before BLPC/PFRC process starts in September.
10
Career Center Expansion Next Steps 2019
11
May 9 School Board Information on Policy F-5.7 Construction and Maintenance Amendment to Policy stating School Board will appoint chair to and adopt charge for BLPC May 23 School Board Action on Policy F-5.7 Construction and Maintenance May 31 Superintendent approves revision to Policy Implementation Procedure F-5.7 PIP-2 Building Level Planning Committees Complete revision of existing PIP June 3 APS staff commence process of selecting members for appointment to Career Center Expansion BLPC June 6
chair and adoption of charge for Career Center Expansion BLPC
Architecture/Engineering team fee for Concept Design phase
Career Center Expansion Next Steps 2019
12
* Dates for BLPC meetings and School Board meetings during School Year 2019-20, are tentative and have not been finalized.
June 18
Integrated Program Pathways (IPP)
and adoption of charge for Career Center Expansion BLPC
Architecture/Engineering team fee for Concept Design phase for Career Center Expansion July 25* School Board Information on appointment of members to Career Center Expansion BLPC
School Board Action on appointment of members to Career Center Expansion BLPC
School Board Information on Construction Manager at Risk contract for pre-construction services Week of
Joint School Board/County Board work session
If required
BLPC/PFRC Meeting #1 First meeting of Concept Design Phase
Career Center Expansion Next Steps 2019
13
* Dates for BLPC meetings and School Board meetings during School Year 2019-20, are tentative and have not been finalized.
Sep 19* School Board Action on Construction Manager at Risk contract for pre-construction services
BLPC/PFRC Meeting #2 Agenda to be developed
School Board Information on Educational Specifications
BLPC/PFRC Meeting #3 Agenda to be developed
School Board Action on Educational Specifications
BLPC/PFRC Meeting #4 Agenda to be developed
BLPC/PFRC Meeting #5 Agenda to be developed
BLPC/PFRC Meeting #6 Agenda to be developed
BLPC/PFRC Meeting #7 Agenda to be developed
Career Center Expansion Next Steps 2020
14
* Dates for BLPC meetings and School Board meetings during School Year 2019-20, are tentative and have not been finalized.
BLPC/PFRC Meeting #8 Agenda to be developed
BLPC/PFRC Meeting #9 BLPC & PFRC complete draft recommendations to School and County Boards
BLPC/PFRC Meeting #10 BLPC & PFRC complete final recommendations to School and County Boards based on reconciled Concept Design total project cost estimates
School Board Information on Concept Design
School Board Action on Concept Design
BLPC/PFRC Meeting #11 First meeting of Schematic Design Phase May 27 BLPC/PFRC Meeting #12 June 4* School Board Information on FY 2021-30 CIP June 25* School Board Action on FY 2021-30 CIP