Acknowledgments INAC Akaitcho Dene Northern Contaminated Sites - - PowerPoint PPT Presentation

acknowledgments
SMART_READER_LITE
LIVE PREVIEW

Acknowledgments INAC Akaitcho Dene Northern Contaminated Sites - - PowerPoint PPT Presentation

Great Slave Lake Remediation Project COMMUNITY ENGAGEMENT AND APPLICATION OF INNOVATIVE REMEDIATION AND RESTORATION Breadmore, R 1 Hoyt, J 2 , Wilson, J 1 1 Aboriginal Affairs and Northern Development Canada Contaminants and Remediation


slide-1
SLIDE 1

Great Slave Lake Remediation Project

COMMUNITY ENGAGEMENT AND APPLICATION OF INNOVATIVE REMEDIATION AND RESTORATION

Breadmore, R1 Hoyt, J2 , Wilson, J1

  • 1Aboriginal Affairs and Northern Development Canada – Contaminants and Remediation Directorate
  • 2 Public Works and Government Services Canada

2016 RPIC Federal Contaminated Sites National Workshop Montreal, QC April 25-27, 2016

slide-2
SLIDE 2

Acknowledgments

INAC

  • Northern Contaminated Sites Program
  • Contaminants and Remediation Division
  • Governance and Partnerships

PWGSC

  • Northern Contaminated Sites Group

ARCADIS Rowe’s Construction Ltd Akaitcho Dene

  • Lutsel K’e Dene First Nation
  • Deninu Kue First Nation
  • Yellowknives Dene First Nation

NWT Métis

  • Fort Resolution Métis Council

Tlicho Government

slide-3
SLIDE 3
  • Site location and history
  • Innovative remediation and restoration

approaches

  • Engagement strategies
  • Project Status
  • Wrap up and questions

Presentation Overview

slide-4
SLIDE 4

GSL Project – Site Locations

slide-5
SLIDE 5

Outpost Island Mine History

  • gold/copper/tungsten
  • operated sporadically

between 1935 and 1952

  • 1955 fire destroyed most

structures

slide-6
SLIDE 6

Blanchet Island Mine History

  • cobalt and nickel
  • staking began in 1960s
  • exploration and mining

until 1970-71

slide-7
SLIDE 7

7

Wilson Island

  • Former gold exploration site
  • Mineral assessment work started in 1916!
  • Exploration activities 1920-1930s

Waldron River

  • Former copper exploration site
  • First claims staked in 1939
  • Exploration in 1940s and 1960s
slide-8
SLIDE 8

8

Contaminated Site Legacies

  • Mine openings (2 shafts, adit and trenches)
  • Exposed tailings and arsenic-rich waste ore
  • PHC and metal impacted soils/sediments
  • Hazardous materials
  • Unfired blasting explosives
  • Site infrastructure
  • Metal debris
slide-9
SLIDE 9

Outpost Island Mine Remediation Challenge SOLUTION

  • Tailings pulled back from the bay above water line
  • Rock armour to stabilize slope and prevent continued erosion and sediment

transport

North Bay Stabilization

slide-10
SLIDE 10

10

Outpost Island Mine Remediation Shafts #1 and #2 Challenge

slide-11
SLIDE 11

Outpost Island Mine Remediation

Shafts #1 and #2 SOLUTION

Site preparation Steel I-beam support Polyurethane foam plug Rock armour cap and vent

slide-12
SLIDE 12

12

Outpost Island Mine Restoration Re-Vegetation Challenge

slide-13
SLIDE 13

Outpost Island Mine Restoration

Revegetation SOLUTION

Area sloped and graded at remediation Local Vegetation Being Planted

slide-14
SLIDE 14

14

Blanchet Island Mine Remediation Mine Adit Closure Challenge

slide-15
SLIDE 15

Blanchet Island Mine Remediation

Mine Adit Closure SOLUTION

Engineered cap Consolidated waste rock and impacted oils

Rock back fill of adit

slide-16
SLIDE 16

16

Blanchet Island Mine Remediation Beach Head Restoration Challenge

Ore concentrate at abandonment

Abatement program (2010)

slide-17
SLIDE 17

Blanchet Island Mine Remediation

Beach Head Restoration

Log in fill as SEC Organics top layer for future re-veg Impacted soil excavation

SOLUTION

slide-18
SLIDE 18

18

Wilson Island and Waldron River Mine Opening Remediation CHALLENGE

slide-19
SLIDE 19

19

Wilson Island and Waldron River Mine Opening Remediation

Polyurethane foam plugs

SOLUTION

slide-20
SLIDE 20
  • Community Engagement Plan is a regulatory requirement
  • > Plan and strategies were updated in 2015
  • Project update meeting in February 2015
  • > led to Site Blessing in June 2015
  • Majority of site workers were from local communities
  • Elders and Land and Water Tour in September
  • Project close-out celebration in December 2015
  • Community based monitoring training in Q4 2015-16
  • Long Term Monitoring Plan (commencing in 2016) will be

community-based

Community Engagement Strategy

slide-21
SLIDE 21

Aboriginal Stakeholders:

Akaitcho Dene (Interim Measures Agreement)

  • Yellowknives Dene First Nation (YKDFN)
  • Lutsel K’e Dene First Nation (LKDFN)
  • Deninu K’ue First Nation (DKFN)

NWT Métis (Interim Measures Agreement)

  • Fort Resolution Métis Council (FRMC)

Tlicho (Tlicho Final Agreement)

  • Tlicho Government
slide-22
SLIDE 22

Executing Community Engagement

Spring 2013

  • Project Planning

Summer 2013

  • Site Tour
  • Community

Briefing 2014/15

  • Community

Update Meetings Summer 2015

  • Site Blessing and

Tour

  • Elders and Board

Site Tour

  • Local Workforce

Winter 2015

  • Project Closeout

Celebration

PROJECT EXECUTION

slide-23
SLIDE 23

Project Update Meeting February 2015

  • Update Akaitcho stakeholders on the

progress of GSL Project and plans for upcoming remediation work

  • Received input on how communities

could be involved > Site Blessing ceremony >Local workforce employment

slide-24
SLIDE 24

Site Blessing June 2015

slide-25
SLIDE 25

Elders and Board Tour September 2015

slide-26
SLIDE 26

Project Close-out Celebration

Elders Committee Meeting Community feast and presentations

slide-27
SLIDE 27

27

Project Closure Celebration !

slide-28
SLIDE 28

28

Faces of the Great Slave Lake Remediation Project

AANDC-PWGSC ARCADIS Rowe’s-Outcome Mackenzie Valley Land and Water Board

slide-29
SLIDE 29

29

Faces of the Great Slave Lake Remediation Project

Site Crew Community leadership and technical resources Community Elders and Youth

slide-30
SLIDE 30

Project Take-Aways

  • Obtain and Maintain Social Licence with

communities

  • Engage stakeholders at all stages of project

(planning-remediation-closure)

  • Allow Remediation Contractor freedom and

flexibility facilitates to design and execute innovative remediation and restoration strategies

  • Take time and effort to celebrate project

completion

  • Recognize the efforts of all those involved
slide-31
SLIDE 31

QUESTIONS ?

Thank you