I -70 over SR 121 Pre-Bid Meeting March 4, 2016 Slide 1 Meeting - - PowerPoint PPT Presentation

i 70 over sr 121 pre bid meeting
SMART_READER_LITE
LIVE PREVIEW

I -70 over SR 121 Pre-Bid Meeting March 4, 2016 Slide 1 Meeting - - PowerPoint PPT Presentation

I -70 over SR 121 Pre-Bid Meeting March 4, 2016 Slide 1 Meeting Objectives Solicit feedback from General Contractors and Specialty Contractors Share Preliminary Construction Details (60% Plans) Solidify Design Concept for Final


slide-1
SLIDE 1

I -70 over SR 121 Pre-Bid Meeting

March 4, 2016

Slide 1

slide-2
SLIDE 2

Meeting Objectives

 Solicit feedback from General Contractors and

Specialty Contractors

 Share Preliminary Construction Details (60%

Plans)

 Solidify Design Concept for Final Plan

Development

Slide 2

slide-3
SLIDE 3

Project Objectives

 Safe Project

 During Construction  I n Service

 Successful Project

 Completed on time, according to plan and within budget  Learn from a “conventional” (non-Milton Madison) ABC

project for future implementation

 Positive experience for Owner, User and Contractor

Slide 3

slide-4
SLIDE 4

Project Objectives

 Accelerated Construction Schedule

 Minimize User Cost  Minimize MOT Cost  Other states are focusing on this type of work as the

primary interstate replacement method

Slide 4

slide-5
SLIDE 5

Current Plan Set

 Finalized Details

 Limits of Construction along I -70  Limits of Construction along SR 121  I nterstate Lane Closure Exception – 13 days per MOT

Phase

 Maintenance of Traffic (mostly)  Superstructure Geometry  Superstructure Type

Slide 5

slide-6
SLIDE 6

Current Plan Set

 Dual Design (Bid Option)

 Superstructure I nstallation Method

UDOT 4500 South over I -215 ODOT OR 213 over Washington St. SPMT (Self-Propelled Modular Transporters) Slide-I n

Slide 6

slide-7
SLIDE 7

Current Plan Set

 Details Under Development

 Foundation Type  Substructure Configuration  Bridge will be in service during construction of

substructure

Slide 7

slide-8
SLIDE 8

Contract Structure

 Design Bid Build  A + B

 A = Construction Cost  B = User Cost for I -70 daytime closures (per hour)  B = User Cost for SR 121 when 1 lane is not provided

(per day)

 Monetary amounts still under development

Slide 8

slide-9
SLIDE 9

Project Site

 I -70 over SR 121 just outside of Richmond

Slide 9

slide-10
SLIDE 10

Project Site

 High bedrock 3’ – 9’ below surface  Bridge staging area

(BSA) in SE corner

 Overhead Utilities on

west edge of project

Slide 10

slide-11
SLIDE 11

Project Site

 High bedrock 3’ – 9’ below surface  Bridge staging area

(BSA) in SE corner

 Overhead Utilities on

west edge of project

Slide 11

slide-12
SLIDE 12

Existing Structure

 Simple Span Steel Beam with RC Girder Approach

Spans

 Built in 1959  27.15 Deg. Skew  End Bent on Piles  Pier on Spread

Footing

Slide 12

slide-13
SLIDE 13

Existing Structure

 Built Horizontally in Wrong Location  41’-3” instead of 45’-8”

Slide 13

slide-14
SLIDE 14

Constructability Discussion

 Maintenance of Traffic/ Duration  Construction Staging  Substructure

 Foundation  Wingwalls  Closure Pours

Slide 14

slide-15
SLIDE 15

Maintenance of Traffic

 Finalized (mostly)  Pavement Design under development  Lane Closure Exception for 13 days per closure  Begins Friday after 9 p.m.  Ends Second Friday at 6 a.m.  For example

 Close 9:00 p.m. Friday 10/ 6/ 17  Open 5:59 a.m. Friday 10/ 20/ 17

Slide 15

slide-16
SLIDE 16

Maintenance of Traffic

 Phase I & Phase I I – Shoulder Strengthening

Slide 16

slide-17
SLIDE 17

Maintenance of Traffic

 Adjacent Bridges Cause Complications

Slide 17

slide-18
SLIDE 18

Maintenance of Traffic

 Shoulder Strengthening – 3000 ft. (3600 ft. barrier)  Temporary Traffic Barrier (currently shown)?

 Two lanes of traffic open  Can work during day  Length of barrier required

 Barrel Drop with Lane Closure?

 Must be in conformance with Lane Closure Policy

 Not a “Critical Path” item

Slide 18

slide-19
SLIDE 19

Maintenance of Traffic

 Phase I I I – Not Allowed in June, July or August  Maximum Duration of 13 Days

Slide 19

slide-20
SLIDE 20

Project Site

 Phase I V – Reset to Normal

Slide 20

slide-21
SLIDE 21

Maintenance of Traffic

 Phase V – Not Allowed in June, July or August  Maximum Duration of 13 Days

Slide 21

slide-22
SLIDE 22

Maintenance of Traffic

 Coordination

 Anticipate Back-ups  Fluid Maintenance of Traffic Alerts  Coordination with Ohio  Public Outreach

Slide 22

slide-23
SLIDE 23

Construction Staging - SPMT

 BSA in southeast corner - 0.6 acres

Slide 23

slide-24
SLIDE 24

Construction Staging - SPMT

 BSA

 On an approximate 5.5% slope south  Rock 3’-4’ below the surface  All temporary supports must be removed completely

after project completion

 Area must be restored to original condition

Slide 24

slide-25
SLIDE 25

Construction Staging - SPMT

 Contract Document Requirements - Submittal

 Provisions based on templates from FHWA and other

States

 Heavy Lift System Details  Contingency Plan  Temporary Supports (BSA)  Monitoring System and Tolerances  Schedule

Slide 25

slide-26
SLIDE 26

Construction Staging - SPMT

 I nstallation - After existing structure removed,

install Precast Bent Cap

 Grouted Couplers  Corrugated Metal Pipe (CMP) Pocket (Preferable)

Slide 26

slide-27
SLIDE 27

Construction Staging - SPMT

 CMP Pocket

Slide 27

slide-28
SLIDE 28

Construction Staging - SPMT

 WB I nstallation – Fairly “Conventional” for SPMT

Slide 28

slide-29
SLIDE 29

Construction Staging - SPMT

 Backfill behind Wings and Cap (flowable fill)  Precast Approach Slabs

 Full approach slab with concrete transitions 209 k  Currently shown as three pieces with Transitions (75 k,

45 k, 45 k)

 Each concrete transition 8 k  Closure pours between sections and between abutment

and approach slab

 Roadwork and Appurtenances

Slide 29

slide-30
SLIDE 30

Construction Staging - SPMT

 EB I nstallation – More Complicated

Slide 30

slide-31
SLIDE 31

Construction Staging - SPMT

 EB I nstallation – More Complicated

Slide 31

slide-32
SLIDE 32

Construction Staging - SPMT

 EB I nstallation – More Complicated  Bridge Rail may be left off during move, but other

precautions must be made

 Other than the actual installation, remainder of

the activities same as WB

 Each installation needs to be completed in less

than the allowable closure time

Slide 32

slide-33
SLIDE 33

Construction Staging - Slide

 Contract Document Requirements - Submittal

 Provisions based on templates from FHWA and other

States

 Contingency Plan  Monitoring System and Tolerances  Schedule

Slide 33

slide-34
SLIDE 34

Construction Staging - Slide

 Existing Bridges Built too Close Together

 Causes 1 lane in each direction to be closed in Phase III (A+ B)

Slide 34

slide-35
SLIDE 35

Construction Staging - Slide

 1’-7 ½ ” Clearance between Existing and Proposed

Slide 35

slide-36
SLIDE 36

Construction Staging - Slide

 End Diaphragm set up to allow for 3 Slide Methods

 Temporary Slide Shoe with Track  Slide on Teflon Bearings  Slide on Rollers

Slide 36

slide-37
SLIDE 37

Construction Staging - Slide

 End Diaphragm set up to allow for 3 Slide Methods

Temporary Slide Shoe Slide on Teflon Bearings Slide on Rollers

Slide 37

slide-38
SLIDE 38

Construction Staging - Slide

 I nstallation

 Once Existing Bridge is removed, slide new WB

superstructure into place

 I t is important to have a system that is capable of

pushing and pulling in case complications arise during installation

 I nstall Temporary Shoring as required  Backfill behind diaphragm

Slide 38

slide-39
SLIDE 39

Construction Staging - Slide

 I nstall Temporary Shoring and Wings

Slide 39

slide-40
SLIDE 40

Construction Staging - Slide

 I nstall Temporary Shoring and Wings

 Currently shown as MSE Wall  Precast

Concrete?

Slide 40

slide-41
SLIDE 41

Construction Staging - Slide

 Precast Approach Slabs  Roadwork and Appurtenances  Repeat for EB Bridge  Each installation needs to be completed in less

than the allowable closure time

Slide 41

slide-42
SLIDE 42

Foundation

 Planned to be built while existing bridge is in

service

 To minimize foundation size, looking at ways of

limiting horizontal force on abutments

 MSE with straps attached to abutment  Expanded Polystyrene Blocks (Geofoam)  Cellular Concrete Fill  Constructability concerns (access)?

Slide 42

slide-43
SLIDE 43

Foundation

 Currently two options shown  Spread Footings

 Main concern is depth of excavation under bridge and

backslope into existing end bent

 Temporary shoring feasible under bridge

Slide 43

slide-44
SLIDE 44

Foundation

 Excavation

Slide 44

slide-45
SLIDE 45

Foundation

 Micropiles

 Logical Choice  Current Provision is as a “Design Build” I tem  Provide two configurations with loads and Contractor

designs final configuration

Max Pile Load = 400 k Min Pile Load = -50 k Max Pile Load = 200 k Min Pile Load = 0 k

Slide 45

slide-46
SLIDE 46

Foundation

 Micropiles - Testing

 Two Verification Tests  Proof Test on 5% of piles  Testing applies actual loads to installed piles to test

grout strength and capacity

 Micropile Casing

 Buy America Clause needs to be satisfied  Mill Certification is required

Slide 46

slide-47
SLIDE 47

Foundation

 Third Option – Drilled Shaft with Straddle Bent

 Conventionally Reinforced Straddle Bent  Still need to determine if viable option due to concrete

shrinkage between shafts

 May require Straddle Bent to be built first and then

connected to drilled shafts

Slide 47

slide-48
SLIDE 48

Foundation

 Third Option – Drilled Shaft with Straddle Bent

Slide 48

slide-49
SLIDE 49

Foundation

 For Spread Footing and Drilled Shaft Option,

abutment would go full width (SPMT and Slide)

 For Micropile option with SPMT, median may use

MSE walls with pile sleeves for future widening

Slide 49

slide-50
SLIDE 50

Wingwalls and Closures

 Main concern is time within the closure period  All options are proposing MSE Walls for the outer

wings

 Precast concrete or MSE for Median wall closure?  Precast concrete or MSE for Wing Closure?

Slide 50

slide-51
SLIDE 51

Wingwalls and Closures

 MSE or Precast Concrete  Wing angle cause access concern?

Slide 51

slide-52
SLIDE 52

Specialty I tem Payment

 Goal is to get usable information for future

projects

 SPMT – Payment separated

 Engineering  Temporary Substructure and BSA  I nstallation and other items  50% payment after first move. Remainder after second

Slide 52

slide-53
SLIDE 53

Specialty I tem Payment

 Goal is to get usable information for future

projects

 Slide – Payment separated

 Engineering  I nstallation and other items  50% payment after first move. Remainder after second

Slide 53

slide-54
SLIDE 54

Specialty I tem Payment

 Goal is to get usable information for future

projects

 Micropile

 Testing  I nstallation  All payment made after work completed

Slide 54

slide-55
SLIDE 55

Contractor I nformation

 Prequalification is required for this Project  http:/ / www.in.gov/ indot/ 2740.htm

Slide 55

slide-56
SLIDE 56

Closing Comments

 Current Design Plan Status approximately 60%

Complete

 Plan Development Scheduled for Completion

October 17, 2016

 Anticipated Letting Date February 8, 2017  WE APPRECI ATE ANY FEEDBACK TO HELP MAKE

THI S A BETTER PROJECT!!

Slide 56

slide-57
SLIDE 57

Closing Comments

QUESTI ONS/ COMMENTS?

Topics

 Barrel Drop versus TTB during Phase I & I I  Slide Option – 1’-7 ½ ” clearance between bridges  Precast Concrete Closures or MSE  Excavation/ backfill for new abutment (shoring)

Slide 57

slide-58
SLIDE 58

Future Questions/ Comments

Additional Questions/ Comments can be sent to the I NDOT Project Manager until 5:00 p.m. 3/ 18/ 2016. Comments and Responses will be compiled and put

  • n the website for the project

jwooldridge@indot.in.gov

http:/ / www.in.gov/ dot/ div/ contracts/ abc/ i70/ i70.htm

Slide 58