A UBURN S CHOOL D ISTRICT N O . 408 CAPITAL PROJECTS DEPARTMENT WORK IN PROGRESS July 2010 Admin. Bldg. Computer Room HVAC Improvements New air-conditioning equipment for Computer Room and Telecommunications Room. Admin. Bldg. Computer Room


slide-1
SLIDE 1

AUBURN SCHOOL DISTRICT NO. 408 CAPITAL PROJECTS DEPARTMENT

WORK IN PROGRESS July 2010

slide-2
SLIDE 2
slide-3
SLIDE 3
  • Admin. Bldg. Computer Room HVAC Improvements

New air-conditioning equipment for Computer Room and Telecommunications Room.

slide-4
SLIDE 4
  • Admin. Bldg. Computer Room HVAC Improvements

Existing Computer Room that will receive new air-conditioning system.

slide-5
SLIDE 5
  • Admin. Bldg. Computer Room HVAC Improvements

New air-conditioning equipment in Telecommunications Room.

slide-6
SLIDE 6
slide-7
SLIDE 7

Alpac Elementary Mech. & Elec. Improvements

Worker preparing to set concrete form for new light pole base.

slide-8
SLIDE 8

Alpac Elementary Mech. & Elec. Improvements

Existing light pole with new energy efficient light fixtures installed at top

  • f pole.
slide-9
SLIDE 9

Alpac Elementary Mech. & Elec. Improvements

New energy efficient water heater.

slide-10
SLIDE 10
slide-11
SLIDE 11

Athletic Fields & Running Track Improvements

Auburn Riverside High School: Cleaning of existing pad that remains in place at the football / soccer field.

slide-12
SLIDE 12

Athletic Fields & Running Track Improvements

Auburn Riverside High School: Installation of concrete forming material for football goalpost footing.

slide-13
SLIDE 13

Athletic Fields & Running Track Improvements

Auburn Riverside High School: Installation of new synthetic turf.

slide-14
SLIDE 14

Athletic Fields & Running Track Improvements

Auburn Riverside High School: Installation of new game lines at football / soccer field.

slide-15
SLIDE 15

Athletic Fields & Running Track Improvements

Auburn Riverside High School: Synthetic turf infill material being spread

  • ver new synthetic turf.
slide-16
SLIDE 16

Athletic Fields & Running Track Improvements

Auburn Riverside High School: Removal of existing rubberized running track.

slide-17
SLIDE 17

Athletic Fields & Running Track Improvements

Auburn Riverside High School: Football / soccer field after removal of existing synthetic turf.

slide-18
SLIDE 18

Athletic Fields & Running Track Improvements

Auburn Riverside High School:

slide-19
SLIDE 19
slide-20
SLIDE 20

Athletic Fields & Running Track Improvements

Auburn Memorial Stadium: Removal of existing synthetic turf at new drain line trenches.

slide-21
SLIDE 21

Athletic Fields & Running Track Improvements

Auburn Memorial Stadium: Removal of existing synthetic turf.

slide-22
SLIDE 22

Athletic Fields & Running Track Improvements

Auburn Memorial Stadium: Removal of existing synthetic turf.

slide-23
SLIDE 23

Athletic Fields & Running Track Improvements

Auburn Memorial Stadium: Partial removal of existing synthetic turf at midfield.

slide-24
SLIDE 24

Athletic Fields & Running Track Improvements

Auburn Memorial Stadium: Trench for new underground drain lines.

slide-25
SLIDE 25

Athletic Fields & Running Track Improvements

Auburn Memorial Stadium: New trenches and partial removal of existing synthetic turf.

slide-26
SLIDE 26

Athletic Fields & Running Track Improvements

Auburn Memorial Stadium: Existing rubber pad where synthetic turf removed.

slide-27
SLIDE 27

Athletic Fields & Running Track Improvements

Auburn Memorial Stadium: Existing rubber pad where patching will be done.

slide-28
SLIDE 28
slide-29
SLIDE 29

Auburn Memorial Stadium Structural Bracing

Concrete panels at end of Home grandstand where seismic bracing will be installed.

slide-30
SLIDE 30

Auburn Memorial Stadium Structural Bracing

Cracks in existing concrete panels where new seismic bracing will be installed at opposite side of wall.

slide-31
SLIDE 31

Auburn Memorial Stadium Structural Bracing

Interior surface of existing concrete panels where new seismic bracing will be installed.

slide-32
SLIDE 32
slide-33
SLIDE 33

Auburn Pool Boiler Replacement

Six-lane pool with water being heated by new energy efficient condensing boilers.

slide-34
SLIDE 34

Auburn Pool Boiler Replacement

New condensing boilers located in Mechanical Room.

slide-35
SLIDE 35

Auburn Pool Boiler Replacement

Control panel at new condensing boiler.

slide-36
SLIDE 36
slide-37
SLIDE 37

Cascade Middle School Generator Replacement

The new generator will provide electrical power for emergency lighting and communication systems throughout the school during a power

  • utage.
slide-38
SLIDE 38

Cascade Middle School Generator Replacement

Existing emergency generator that no longer functions and will be replaced.

slide-39
SLIDE 39

Cascade Middle School Generator Replacement

Underground electrical conduit at generator pad that is being modified to accommodate the new generator.

slide-40
SLIDE 40

Cascade Middle School Generator Replacement

New chainlink gate installed at generator enclosure to provide improved access.

slide-41
SLIDE 41
slide-42
SLIDE 42

Curbs and Sidewalk Improvements

Administration Building: Replacement of damaged and uneven sidewalk at J St. NE.

slide-43
SLIDE 43

Curbs and Sidewalks Improvements

Auburn High School: New wheelchair ramp at front entry to 100 Unit.

slide-44
SLIDE 44

Curbs and Sidewalk Improvements

Hazelwood Elementary School: New wheelchair ramp at bus loading area and staff parking lot.

slide-45
SLIDE 45

Curbs and Sidewalks Improvements

Auburn Riverside High School: New wheelchair ramp at bus loading area.

slide-46
SLIDE 46

Curbs and Sidewalk Improvements

Pioneer Elementary School: New wheelchair ramp at front of school.

slide-47
SLIDE 47
slide-48
SLIDE 48

HVAC Improvements

Auburn Riverside High School: Computer classroom that will receive additional air-conditioning to address overheating caused by computer equipment.

slide-49
SLIDE 49

HVAC Improvements

Auburn Riverside High School: Existing air-conditioning chiller unit that will receive new compressors.

slide-50
SLIDE 50

HVAC Improvements

Auburn Riverside High School: Existing mechanical unit that will be replaced with larger unit to increase air-conditioning capacity.

slide-51
SLIDE 51
slide-52
SLIDE 52

Auburn High School Renewal

The post-occupancy survey conducted at Auburn Mountainview High School will be used to create a list of lessons learned and lessons will be considered in the design of the Auburn High School Renewal project.

slide-53
SLIDE 53

Auburn High School Renewal

Aerial photograph of existing campus.