HVAC Systems Overview New Marblehead Elementary School at the Bell - - PowerPoint PPT Presentation

hvac systems overview
SMART_READER_LITE
LIVE PREVIEW

HVAC Systems Overview New Marblehead Elementary School at the Bell - - PowerPoint PPT Presentation

HVAC Systems Overview New Marblehead Elementary School at the Bell School Site Marblehead, MA GARCIA GALUSKA DESOUSA Consulting Engineers Inc. Life Cycle Cost Analysis HVAC System Options HVAC System


slide-1
SLIDE 1

HVAC Systems Overview

New Marblehead Elementary School at the Bell School Site Marblehead, MA

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

slide-2
SLIDE 2

Life Cycle Cost Analysis HVAC System Options

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

HVAC System Options Overview 1. Baseline: VAV System (ASHRAE Baseline) 2. Option 1: Induction Unit System with DOAS (Dedicated Outdoor Air System) 3. Option 2: Dehumidification Displacement System with DOAS (Dedicated Outdoor Air System) 4. Option 3: Fully Air-Conditioned Displacement System with DOAS (Mixed-Air System)

slide-3
SLIDE 3

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

Goal of Life Cycle Economic Analysis

The goal of the mechanical lifecycle engineering economic analysis is to assess the performance of various mechanical systems in comparison to a baseline mechanical system. Each option is compared to the baseline system to determine the lowest combined savings over a 30 year cycle to determine the most advantageous system considering electrical costs, gas costs, maintenance costs, and initial construction costs. By comparison of each option to the baseline system, the option with the greatest total life-cycle savings is generally recommended. To further enhance controllability and overall system performance, additional

  • ptions should be considered that will enhance year round temperature control and comfort at a possible

marginal increase in capital cost.

slide-4
SLIDE 4

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

Variable Air Volume (VAV) System

Pros:

  • Lower piping installed costs due to two-pipe system as

chilled water piping is not required

  • Moderate to high overall installed costs
  • Chiller plant and distribution systems not required
  • Low maintenance; no condensate drains, fans, or filters at

terminal units

  • Reduced automatic temperature controls installed costs

resulting from reduced control components Cons:

  • Moderate noise levels
  • Reduced temperature control if several rooms

are served by the same V A V unit

  • Reduced indoor air quality as a result of being a

mixed-air system

  • Maintenance of equipment is in occupied area
  • Higher energy consumption due to increased fan

energy

  • Higher energy consumption as summertime use
  • f hot water system is required for hot water

reheats of V A V boxes

  • Overall ductwork costs are greater due to the

larger supply and return ductwork systems providing mixed-air rather than ventilation only

slide-5
SLIDE 5

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

Induction Units (Full Air Conditioning)

  • Ventilation air is provided from

high efficiency packaged gas-fired heat/DX cooling RTU w/ ERV

  • Primary (Ventilation) Air is

supplied to plenum and discharges through nozzles

  • Room air is induced through

the heating/cooling coils

  • Mixture of Primary and Room

air is delivered to room through diffuser slots.

  • Condensate drain pans and

piping system for condensate removal

slide-6
SLIDE 6

Induction Units

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

Pros:

  • Energy efficient
  • Ventilation air & ductwork

minimized

  • Low Noise Levels
  • Flexibility of Installation
  • Moderate first cost
  • Simplified Controls (No Fans)
  • Lower Maintenance (No Terminal

Filters) Cons:

  • Requires increased coordination

with “ceiling” system. (e.g. additional piping, HW , CHW & condensate piping)

  • Requires additional ventilation

air in some cases

  • Increase Energy Consumption
  • vs. Dehumidified Air Systems
slide-7
SLIDE 7

Option 1 – Induction Unit Classroom Section

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

slide-8
SLIDE 8

HVAC System Comparison

Mixing vs. Displacement Systems AIR CONDITIONING

  • VENTILATION AIR COOLED AND SUPPLIED

AT 55 DEG F. TO SPACE

  • MAINTAINS SPACE TEMP. AT 75 DEG F.
  • ADDITIONAL EQUIP. REQD. WITH

INCREASED CAP. TO MAINTAIN 75 DEG F.

  • INCREASED DUCT SIZES OR NEED FOR

ADDITIONAL PIPING SYSTEM

  • INCREASED CONSTRUCTION COST BY 20%

(Dependent upon AC System)

  • INCREASED OPERATIONAL COST BY 20%

(APPROX. $1.75/SF, BASELINE VAV)

DEHUMIDIFIED AIR

  • VENTILATION AIR COOLED BY

DEHUMIDIFICATION AND REHEATED BY HOT GAS HEAT RECOVERY TO 68 DEG F.

  • TEMP. FLOATS IN SPACE WITHIN COMFORT

ZONE

  • REDUCED DUCT SIZES OR NEED FOR

SECONDARY EQUIPMENT

  • REDUCED CONSTRUCTION COST WHEN

COMPARED TO CONVENTIONAL NON- CONDITIONED BUILDINGS

  • SIMILAR OPERATIONAL COST WHEN

COMPARED TO CONVENTIONAL NON AIR CONDITIONED BUILDINGS (APPROX. $1.39/SF FOR DEHUMIDIFICATION DISPLACEMENT OR $1.47/SF FOR FULL AC DISPLACEMENT)

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

slide-9
SLIDE 9

Displacement System (Classrooms, Cafeteria, Gymnasium, Corridors)

Mixed Systems DV Systems Ec= 0.8 Ec=1.2 - 1.4 GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

  • Ventilation air is provided from high

efficiency packaged gas-fired heat/DX cooling RTU w/ ERV

  • Air is delivered at low velocity and at low

levels within the space

  • The system uses naturally occurring

buoyant forces within the space to create a vertical rise of the air throughout the space.

  • 2-4˚ F differential supply air to space
  • Supply air rises when heat source is

contacted

  • Displaces room air upward
  • Air rises with pollutants to ceiling
  • Air returns at ceiling back to air handling

unit

70-75°F 80°F + 65-68°F

slide-10
SLIDE 10

Displacement System

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

Pros:

  • Excellent pollution removal
  • Very low noise levels
  • Very low air velocity
  • Low moisture levels
  • Reduced cooling loads
  • Reduced initial cost
  • Variable volume reheat is not required
  • High ventilation effectiveness

Cons:

  • Requires Perimeter Radiation Heating
  • Does not provide Cooling Setpoint temperature control

Displacement Diffuser Options

slide-11
SLIDE 11

Displacement System – Energy Conservation

Load Calculation Reductions

  • Conventional System: All heat generated in

room is included in air flow calculation since all airflow is mixed.

  • Displacement System: Only loads which
  • ccur in the Occupied Zone are factored
  • Results in: Smaller equipment & systems

and lower installed and operating costs for Displacement Systems Additional Energy Efficiency Measures & Features

  • Energy Recovery: Transfers energy from the

return air stream to the supply air stream to pre-heat or pre-cool the outside air.

  • Full AC - Variable Air Volume w/ CO2

Demand Control Ventilation: Modulates the airflow to large single zone areas in accordance to space mounted thermostat and CO2 sensors reducing energy consumption due to reduced air changes.

Occupied Zone Unoccupied Zone

slide-12
SLIDE 12

Option 2 - Dehumidification Displacement Classroom Section

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

slide-13
SLIDE 13

Option 3 – Full AC Displacement Classroom Section

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

slide-14
SLIDE 14

High Efficiency Heating Hot Water and Chilled Water Plant

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

Boiler Plant

  • High efficiency (90%+) gas-fired

condensing boilers

  • Boiler temperature reset controls
  • Variable speed pumps with VFD’s

Chiller Plant

  • High efficiency air-cooled chiller
  • Chilled water temperature reset controls
  • Variable speed pumps with VFD’s
slide-15
SLIDE 15

Building Automation and Energy Management System

  • System (Zone) Scheduling
  • Occupied-Unoccupied Control
  • Night Setback Operation
  • Lighting Control System Integration
  • Increased Energy Savings
  • Integrate with Preventative Maintenance

Scheduling

slide-16
SLIDE 16

Energy Economics Methodology

  • Architecture
  • Weather data
  • Building occupancy &

usage

  • System Operating

Characteristics

  • Utility Rates

Energy Simulation

  • Installation costs
  • Maintenance cost

Energy Economics Life Cycle Cost Analysis

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

slide-17
SLIDE 17

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

  • Computer Simulation of Building Energy Usage

using Department of Energy (DOE-2)/eQuest.

  • Model consists of project specific:

– Architectural features (geometry, orientation, envelope) – Local Weather Data – Occupancy, Lighting, and Equipment schedules – HVAC System Data (specific to each system option) – Local Utility Rates

Energy Model Methodology

slide-18
SLIDE 18

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

  • Computer calculation of HVAC System economics

utilizing NIST BLCC 5.

  • Calculation factors:

– Annual Building Energy Consumption – HVAC System and Maintenance Cost Estimates

  • Prepared in house using recent project cost data and

industry standard estimating references. – Standard Industry Discount, Inflation and Interest Rates

slide-19
SLIDE 19

Summary of Results

slide-20
SLIDE 20

Conclusions and Recommendations

Our observations of the Mechanical System Payback Summary suggest that Option 2, variable air volume dehumidification displacement ventilation systems, represents the lowest life cycle cost by yielding an approximate $1,453,155 savings over the 30 year study period with an instant payback as it has a lower installed cost than the code baseline system.

slide-21
SLIDE 21

GARCIA • GALUSKA • DESOUSA

Consulting Engineers Inc.

Thank You Questions and Discussions