Overview of the Environmental Management System for HVac/HVdc - - PowerPoint PPT Presentation

overview of the environmental management system
SMART_READER_LITE
LIVE PREVIEW

Overview of the Environmental Management System for HVac/HVdc - - PowerPoint PPT Presentation

Overview of the Environmental Management System for HVac/HVdc Transmission Line Construction Lower Churchill Power Project October 8, 2015 1 2 Project Overview 4 Muskrat Falls HVac/HVdc Project Components Two 315 kilovolt High Voltage


slide-1
SLIDE 1

Overview of the Environmental Management System for HVac/HVdc Transmission Line Construction Lower Churchill Power Project

October 8, 2015

1

slide-2
SLIDE 2

2

slide-3
SLIDE 3

Project Overview

slide-4
SLIDE 4

4

slide-5
SLIDE 5

Muskrat Falls HVac/HVdc Project Components

  • Two 315 kilovolt High Voltage alternating current (HVac)

transmission lines between Muskrat Falls & Churchill Falls (Labrador Transmission Assets)

  • 1,100 km High Voltage direct current (HVdc) transmission line

between Muskrat Falls & Soldiers Pond near St. John’s (Labrador-Island Transmission Link)

  • Strait of Belle Isle Marine Cable Crossing (3 X 30 km long

cables)

5

slide-6
SLIDE 6

AC Transmission: Muskrat to Churchill Falls

  • Clearing for right-of-way complete

– 250 km – Clearing: 2,450 hectares

  • Towers and foundations

– 1,250 Towers – 8,125 foundations

  • Conductors and Fiber Optic cables

– 2-315 Kv, 3 phase conductors – Fiber Optic Cable – Approx. 40% complete

  • Work will be substantially

complete in 2015

slide-7
SLIDE 7

7

slide-8
SLIDE 8

8

slide-9
SLIDE 9

DC Transmission: Labrador-Island Link

  • Clearing for right-of-way ongoing across

province

– 1,100 km – ROW Clearing – 6,554 ha

  • Towers and foundations

– First tower erected in Labrador in April 2015 – 1,760 Towers (Labrador) – 2,225 Towers (Island) – Tower erection ongoing in Labrador; start

tower assembly on island in October 2015

slide-10
SLIDE 10

10

slide-11
SLIDE 11

11

slide-12
SLIDE 12

Conductor Stringing HVac Line

12

slide-13
SLIDE 13

Strait of Belle Isle Marine Cable Crossing

  • First land cables installed in Shoal Cove, Sept. 2015
  • Marine cable manufacturing underway in Japan; last
  • f three cables expected in September each 30 kms.

in length

  • Successfully completed horizontal directional drilling

(HDD) program; longest landfall application in world

  • On track for marine cable installation across the

Strait next year

13

slide-14
SLIDE 14

14

slide-15
SLIDE 15

15

slide-16
SLIDE 16

Environmental Management System

Integration of EMS into Project Execution – All Components

  • Design Requirements
  • Technical Specifications
  • Procurement Packages
  • Bidder Evaluation
  • Kick-Off Meeting Support
  • Weekly Reports to

Stakeholders

  • On-Going Field Monitoring
  • Use of Powerline by all

stakeholders

16

slide-17
SLIDE 17

Collaborative Regulatory Framework

  • Blanket Permits

– Water crossings (>1900) – Quarries (>500) – Historic resources – Vegetation clearing

  • Proactive Reporting

– Online reporting – Powerline updated constantly – Weekly report to all regulators

  • Monitoring Tools

– Electronic forms (iPad) – Real-time field reports and

constraint monitoring

17

slide-18
SLIDE 18

HVac/HVdc Construction Monitoring

  • Dedicated on-site environmental monitors at each work front
  • Real-time access to all EMS components via satellite and

internet connections

  • All monitors use an interactive prontoform database and iPad

that provide inspection forms and direct connection to Powerline and the project office

  • Dedicated environmental permit coordinators, engineers and

planners

18

slide-19
SLIDE 19

Real-Time Internet Reporting

  • Pre-set Prontoform templates
  • GIS / GPS Mapping functions
  • Real-time photograph

transfers

  • Immediate distribution to

project office coordinators and engineers

  • Field (Camp) access to

Powerline database and constraint mapping

19

slide-20
SLIDE 20

20

Environmental Effects Monitoring Program

  • Purpose is to monitor the overall project

effects and to confirm the predictions of EA and fulfill EA commitments

  • LCP has implemented more than 15

comprehensive environmental effects monitoring programs

  • Key programs include:

RWM caribou

MM caribou

Newfoundland marten

Newfoundland caribou

Avifauna

HHRA

slide-21
SLIDE 21

LCP Powerline

(Internet Based Environmental Management )

slide-22
SLIDE 22

LCP Powerline

22

  • Web-based
  • Project GIS database
  • Real-time data upload
  • Real-time connection to:

Project documents/permits Government databases Contractor work locations Photograph library

slide-23
SLIDE 23

LCP Powerline - Layers

23

GROUP SUB-GROUP DISPLAY NAME

Upper Labrador Lower Labrador Lower Island Upper Island Churchill River 2006 Public Water Supplies Drainage Outside Protected Stream Crossing Salmon Rivers - 30m Buffer Salmon Rivers - 200m Buffer Wetlands Archaeological Site Archaeological Sites - 50m Buffer Portage Trails Nesting Site - Raptors Nesting Sites - Raptors (Construction - 200m Buffer) Nesting Sites - Raptors (Helicopter - 300m Buffer) Nesting Sites - Raptors (Blasting - 500m Buffer) Nesting Sites - Raptors (Clearing - 800m Buffer) Bird Surveys (Edited) Bird Surveys (Buffer Zone) Listed Plants - Critical Habitat Regionally Uncommon Plants - obs Red Pine Stands Caribou - Winter Habitat (Labrador) Caribou - Calving Habitat (Labrador) Caribou - Core Habitat (Island) Marten - Core Habitat Marten - Critical Habitat Beaver Lodge / Dam Parks and Nature Reserves PPWSA - Stream Buffer Winter Head Pond - 25m Full Supply Level - 39m Outfitters

AQUATIC

ENVIRONMENT

WILDLIFE OTHER VEGETATION / PLANTS AVIFAUNA N/A

IMAGERY WATER SUPPLIES

N/A HISTORIC RESOURCES

GROUP SUB-GROUP DISPLAY NAME

N/A

Work Camps

N/A

Quarries - New Applications

N/A

Quarries - Permits Centerlines Towers Tower Boxes ROW ROW Chainage (250m) ROW Chainage (5km) As-built Access Road (Valard) Plan of the Day AC (Valard) Centerline Towers Tower Boxes ROW Electrode Lines ROW Chainage (250m) - Labrador ROW Chainage (5km) - Labardor ROW Chainage (250m) - Island ROW Chainage (5km) - Island Approved Access Trails (Valard) As-built Access Road (Valard) Plan of the Day DC (Valard) LCP Transmission Corridor Access Study (iii, 2011-2012) Forest Density Clearing Status Forest Density Clearing Status Construction Blocks Grants Easements License To Occupy Permission To Occupy LCP - Private Lands Municipal Boundaries Planning Area Boundaries NL Road Network

INFRASTRUCTURE - DC Line

TRANSMISSION - INFRASTRUCTURE

INFRASTRUCTURE - AC Line

LANDS

N/A

CLEARING

DC LINE AC LINE

slide-24
SLIDE 24

LCP Powerline – Basemaps/Imagery

24

slide-25
SLIDE 25

LCP Powerline – Bog & Watercourse Constraint Layers

25

slide-26
SLIDE 26

Typical Watercourse Crossing and Bog Access

26

slide-27
SLIDE 27

Powerline – Caribou Constraint Layers

27

slide-28
SLIDE 28

Powerline – Raptor Buffer Constraint

28

slide-29
SLIDE 29

LCP Powerline – Field Integration

29

slide-30
SLIDE 30

LCP Powerline – Permit Compliance

30

slide-31
SLIDE 31

Thank you / Questions?

31