overview of the environmental management system
play

Overview of the Environmental Management System for HVac/HVdc - PowerPoint PPT Presentation

Overview of the Environmental Management System for HVac/HVdc Transmission Line Construction Lower Churchill Power Project October 8, 2015 1 2 Project Overview 4 Muskrat Falls HVac/HVdc Project Components Two 315 kilovolt High Voltage


  1. Overview of the Environmental Management System for HVac/HVdc Transmission Line Construction Lower Churchill Power Project October 8, 2015 1

  2. 2

  3. Project Overview

  4. 4

  5. Muskrat Falls HVac/HVdc Project Components • Two 315 kilovolt High Voltage alternating current (HVac) transmission lines between Muskrat Falls & Churchill Falls (Labrador Transmission Assets) • 1,100 km High Voltage direct current (HVdc) transmission line between Muskrat Falls & Soldiers Pond near St. John’s (Labrador-Island Transmission Link) • Strait of Belle Isle Marine Cable Crossing (3 X 30 km long cables) 5

  6. AC Transmission: Muskrat to Churchill Falls • Clearing for right-of-way complete – 250 km – Clearing: 2,450 hectares • Towers and foundations – 1,250 Towers – 8,125 foundations • Conductors and Fiber Optic cables – 2-315 Kv, 3 phase conductors – Fiber Optic Cable – Approx. 40% complete • Work will be substantially complete in 2015

  7. 7

  8. 8

  9. DC Transmission: Labrador-Island Link • Clearing for right-of-way ongoing across province – 1,100 km – ROW Clearing – 6,554 ha • Towers and foundations – First tower erected in Labrador in April 2015 – 1,760 Towers (Labrador) – 2,225 Towers (Island) – Tower erection ongoing in Labrador; start tower assembly on island in October 2015

  10. 10

  11. 11

  12. Conductor Stringing HVac Line 12

  13. Strait of Belle Isle Marine Cable Crossing • First land cables installed in Shoal Cove, Sept. 2015 • Marine cable manufacturing underway in Japan; last of three cables expected in September each 30 kms. in length • Successfully completed horizontal directional drilling (HDD) program; longest landfall application in world • On track for marine cable installation across the Strait next year 13

  14. 14

  15. 15

  16. Environmental Management System Integration of EMS into Project Execution – All Components • Design Requirements • Technical Specifications • Procurement Packages • Bidder Evaluation • Kick-Off Meeting Support • Weekly Reports to Stakeholders • On-Going Field Monitoring • Use of Powerline by all stakeholders 16

  17. Collaborative Regulatory Framework Blanket Permits • – Water crossings (>1900) – Quarries (>500) – Historic resources – Vegetation clearing Proactive Reporting • – Online reporting – Powerline updated constantly – Weekly report to all regulators Monitoring Tools • – Electronic forms (iPad) – Real-time field reports and constraint monitoring 17

  18. HVac/HVdc Construction Monitoring • Dedicated on-site environmental monitors at each work front • Real-time access to all EMS components via satellite and internet connections • All monitors use an interactive prontoform database and iPad that provide inspection forms and direct connection to Powerline and the project office • Dedicated environmental permit coordinators, engineers and planners 18

  19. Real-Time Internet Reporting • Pre-set Prontoform templates • GIS / GPS Mapping functions • Real-time photograph transfers • Immediate distribution to project office coordinators and engineers • Field (Camp) access to Powerline database and constraint mapping 19

  20. Environmental Effects Monitoring Program Purpose is to monitor the overall project • effects and to confirm the predictions of EA and fulfill EA commitments LCP has implemented more than 15 • comprehensive environmental effects monitoring programs Key programs include: • RWM caribou – MM caribou – Newfoundland marten – Newfoundland caribou – Avifauna – HHRA – 20

  21. LCP Powerline (Internet Based Environmental Management )

  22. LCP Powerline  Web-based  Project GIS database  Real-time data upload  Real-time connection to: Project documents/permits Government databases Contractor work locations Photograph library 22

  23. LCP Powerline - Layers GROUP SUB-GROUP DISPLAY NAME GROUP SUB-GROUP DISPLAY NAME Upper Labrador N/A Work Camps IMAGERY N/A Quarries - New Applications Lower Labrador N/A Quarries - Permits N/A Lower Island Centerlines Upper Island Towers Churchill River 2006 TRANSMISSION - INFRASTRUCTURE Tower Boxes SUPPLIES WATER Public Water Supplies INFRASTRUCTURE - ROW N/A AC Line ROW Chainage (250m) Drainage Outside Protected ROW Chainage (5km) As-built Access Road (Valard) Stream Crossing Plan of the Day AC (Valard) Salmon Rivers - 30m Buffer AQUATIC Centerline Salmon Rivers - 200m Buffer Towers Wetlands Tower Boxes Archaeological Site HISTORIC ROW Archaeological Sites - 50m Buffer RESOURCES Portage Trails Electrode Lines ROW Chainage (250m) - Labrador Nesting Site - Raptors INFRASTRUCTURE - Nesting Sites - Raptors (Construction - 200m Buffer) ROW Chainage (5km) - Labardor DC Line Nesting Sites - Raptors (Helicopter - 300m Buffer) ROW Chainage (250m) - Island AVIFAUNA Nesting Sites - Raptors (Blasting - 500m Buffer) ROW Chainage (5km) - Island ENVIRONMENT Nesting Sites - Raptors (Clearing - 800m Buffer) Approved Access Trails (Valard) Bird Surveys (Edited) As-built Access Road (Valard) Bird Surveys (Buffer Zone) Plan of the Day DC (Valard) Listed Plants - Critical Habitat LCP Transmission Corridor Access Study (iii, 2011-2012) VEGETATION / Regionally Uncommon Plants - obs Forest Density PLANTS CLEARING AC LINE Red Pine Stands Clearing Status Caribou - Winter Habitat (Labrador) Forest Density Caribou - Calving Habitat (Labrador) DC LINE Clearing Status Caribou - Core Habitat (Island) Construction Blocks WILDLIFE Marten - Core Habitat Grants Marten - Critical Habitat Easements Beaver Lodge / Dam License To Occupy Parks and Nature Reserves LANDS Permission To Occupy PPWSA - Stream Buffer N/A LCP - Private Lands OTHER Winter Head Pond - 25m Municipal Boundaries Full Supply Level - 39m Planning Area Boundaries Outfitters NL Road Network 23

  24. LCP Powerline – Basemaps/Imagery 24

  25. LCP Powerline – Bog & Watercourse Constraint Layers 25

  26. Typical Watercourse Crossing and Bog Access 26

  27. Powerline – Caribou Constraint Layers 27

  28. Powerline – Raptor Buffer Constraint 28

  29. LCP Powerline – Field Integration 29

  30. LCP Powerline – Permit Compliance 30

  31. Thank you / Questions? 31

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend