high capacity micropiles high capacity micropiles in
play

High Capacity Micropiles High Capacity Micropiles in Mined Ground - PowerPoint PPT Presentation

High Capacity Micropiles High Capacity Micropiles in Mined Ground for in Mined Ground for Bridge Support: Bridge Support: Joplin County, Missouri Joplin County, Missouri Paper 4 Paper 4 LOAD TESTING LOAD TESTING Donald A. Bruce


  1. High Capacity Micropiles High Capacity Micropiles in Mined Ground for in Mined Ground for Bridge Support: Bridge Support: Joplin County, Missouri Joplin County, Missouri Paper 4 Paper 4 LOAD TESTING LOAD TESTING Donald A. Bruce Geosystems L.P. Donald A. Bruce Geosystems L.P. Wayne A. Duryee HNTB Wayne A. Duryee HNTB Michael C. Middleton Missouri DOT Michael C. Middleton Missouri DOT Timothy J. Myers Layne GeoConstruction Timothy J. Myers Layne GeoConstruction

  2. Scope Scope 1. Introduction Introduction 1. 2. Technical Requirements Technical Requirements 2. 2.1 Specifications Specifications 2.1 2.2.1 Verification Load Tests Verification Load Tests 2.2.1 2.1.2 Proof Tests Proof Tests 2.1.2 2.2 Contractor’s Conforming Submittal Contractor’s Conforming Submittal 2.2 3. Results of Verification Tests (4) Results of Verification Tests (4) - - (Paper 2: Foster, (Paper 2: Foster, 3. Peters, Bruce, Chuaqui and Norrish) Peters, Bruce, Chuaqui and Norrish) 4. Results of the Proof Tests (16) Results of the Proof Tests (16) 4. 5. Final Observations Final Observations 5.

  3. 2. Technical Requirements 2. Technical Requirements 2.1 Specifications 2.1 Specifications – Minimum – Minimum anticipated anticipated cased and bond zone cased and bond zone lengths provided per pile. lengths provided per pile. – Minimum load requirements provided per pile. – Minimum load requirements provided per pile. – GBR bond values to be verified by 4 – GBR bond values to be verified by 4 preproduction Verification piles, and directed preproduction Verification piles, and directed thereafter by the Engineer. thereafter by the Engineer. – Contractor to design and conduct load tests and – Contractor to design and conduct load tests and collect all load/movement data. collect all load/movement data. – Proof testing of production piles: one per each of – Proof testing of production piles: one per each of the 16 bents to 1.2 DL. the 16 bents to 1.2 DL.

  4. 2.1.1 Verification Load Tests: Summary 2.1.1 Verification Load Tests: Summary – 4 vertical piles in different ground conditions. – 4 vertical piles in different ground conditions. – Test cyclically to 2.0 DL. – Test cyclically to 2.0 DL. – Conduct creep tests. – Conduct creep tests. – No acceptance criteria, i.e., no pass – No acceptance criteria, i.e., no pass- -fail. fail.

  5. Actual Verification Pile Dimensions and Ground Conditions

  6. Details of Verification Pile Testing Details of Verification Pile Testing

  7. 2.1.2 Proof Tests 2.1.2 Proof Tests – – Total of 220 production piles (vertical and inclined). Total of 220 production piles (vertical and inclined). – – 16 Proof Tests – – locations at each bent to be selected in locations at each bent to be selected in 16 Proof Tests the field by the Engineer. the field by the Engineer. – – Simple incremental tensile loading to 1.2 DL, with 60- - Simple incremental tensile loading to 1.2 DL, with 60 minute creep test (Modified ASTM D3689 Quick Test). minute creep test (Modified ASTM D3689 Quick Test). – – Acceptance criteria: Acceptance criteria: 1. No failure at TL. No failure at TL. 1. 2. Debonding at TL ≤ 50% bond length. Debonding at TL ≤ 50% bond length. 2. 3. Creep rate ≤ 1 mm per log cycle (1 Creep rate ≤ 1 mm per log cycle (1- -10 mins.) or ≤ 2mm 10 mins.) or ≤ 2mm 3. per log cycle (6- -60 mins.). 60 mins.). per log cycle (6 – – If failure occurs, test another pile in the same bent, and If failure occurs, test another pile in the same bent, and consider modifications, down rating, replacement, etc. consider modifications, down rating, replacement, etc. – – Each test paid for on lump- -sum basis. sum basis. Each test paid for on lump

  8. 2.2 Contractor’s Conforming Submittal 2.2 Contractor’s Conforming Submittal

  9. Tension Test Setup Tension Test Setup

  10. Load Testing in Progress

  11. 4. Results of the Proof Tests 4. Results of the Proof Tests – Every micropile reached the test loads (986 – Every micropile reached the test loads (986- -2,269 2,269 kN). kN). – At TL debonded lengths were exceptionally small – At TL debonded lengths were exceptionally small and in only one case did it extend beyond the and in only one case did it extend beyond the cased length. cased length. – Permanent movements at TL ranged from 0.34 to – Permanent movements at TL ranged from 0.34 to 6.45 mm (typically < 3 mm). 6.45 mm (typically < 3 mm). – All load – All load- -movement curves were very linear. movement curves were very linear. – Every pile comfortably satisfied the creep criteria. – Every pile comfortably satisfied the creep criteria. – Paper contains full details (Table 7). – Paper contains full details (Table 7).

  12. 5. Final Observations 5. Final Observations – The “chaotic” ground had the potential to: – The “chaotic” ground had the potential to: � render design very challenging; render design very challenging; � � cause difficulties and dangers during construction; cause difficulties and dangers during construction; � � cause performance problems during service. cause performance problems during service. � – An intensive site investigation, relying also on historical data – An intensive site investigation, relying also on historical data, , permitted a bent- -specific GBR to be prepared. specific GBR to be prepared. permitted a bent – The GBR drove the concept and details of pretreatment by – The GBR drove the concept and details of pretreatment by grouting as an exploratory tool grouting as an exploratory tool as well as a ground remediation/ as well as a ground remediation/ preparation in advance of advance of preparation micropiling or spread footing micropiling or spread footing construction. construction.

  13. 5. Final Observations (continued) 5. Final Observations (continued) – The Verification Piles allowed the preliminary design of – The Verification Piles allowed the preliminary design of bond lengths to be confirmed/modified. bond lengths to be confirmed/modified. – During construction, no exceptional problems were – During construction, no exceptional problems were encountered, and the pretreatment was monitored and encountered, and the pretreatment was monitored and directed in real time. directed in real time. – All Proof Tests were successful and no remedial piles – All Proof Tests were successful and no remedial piles were required. were required. – The field program was implemented within an acceptable – The field program was implemented within an acceptable schedule and with only minor changes/ overruns. schedule and with only minor changes/ overruns. – The keys to success were technical risk management at – The keys to success were technical risk management at every phase of the project, and efficient collaboration every phase of the project, and efficient collaboration between a team of specialists of different but between a team of specialists of different but complimentary skills and experiences. complimentary skills and experiences.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend