8 th international 8 th international workshop workshop
play

8 th International 8 th International Workshop Workshop on - PowerPoint PPT Presentation

8 th International 8 th International Workshop Workshop on Micropiles on Micropiles Toronto Toronto September 26 to 29, 2007 September 26 to 29, 2007 Axial Compression, Axial Tension and Lateral Load Response of Pre-Production Micropiles


  1. 8 th International 8 th International Workshop Workshop on Micropiles on Micropiles Toronto Toronto September 26 to 29, 2007 September 26 to 29, 2007 Axial Compression, Axial Tension and Lateral Load Response of Pre-Production Micropiles for the CPR Mile 62.4 Nipigon Subdivision Bridge

  2. Case History Case History � Underpinning and jacketing of existing Canadian Pacific Railway (CPR) bridge foundations at Mile 62.4, Nipigon Subdivision (near Thunder Bay, Ontario) • Capital cost savings of 20 % compared to replacement. • First of its kind project in Canada. � Approximately 130 year old structure • Steel Superstructure • Stone Masonry Piers (3 Piers) • Timber Piles and Mat Foundations (overstressed)

  3. Project Team Project Team � Canadian Pacific Railway (Owner) � Golder (Geotechnical Consultant, Micropile Designer and Construction Monitoring) • Donald Bruce (Advisor) � HMM (Construction Manager) � LAS (General Contractor) � GFC (Micropiling Contractor) • Isherwood Associates

  4. Golder Project Team Golder Project Team � Calgary • Dennis Becker • Peter Thomson • Blake Leew � Mississauga • Paul Dittrich • Arash Zakeri � Saskatoon • Greg Misfeldt • Dean Lorras

  5. Ground Conditions Ground Conditions � Pier 1 • Sand, cobbles and masonry rubble fill • Compact to dense sand and gravel • Compact to very dense silt • Very stiff silty clay � Pier 2 • Compact to dense sand and gravel • Compact to very dense silt � Pier 3 • Sand, cobbles and masonry rubble fill • Compact to dense sand and gravel • Dense to very dense silt

  6. Design Criteria (Single Pile) Design Criteria (Single Pile) � Service loading conditions: • Maximum axial load = 1,200 kN • Maximum lateral load = 100 kN • Maximum moment = 100 kN-m � At design serviceability loading: • Settlement ≤ 6 mm • Differential settlement ≤ 3 mm • Lateral displacement ≤ 13 mm

  7. Design and Analysis Design and Analysis � Preliminary micropile sections and lengths selected using conventional methods � Micropile sections and lengths refined and finalized using 3D finite element program ( FB-Pier ) � Manual checks following AREMA

  8. Micropile Section Details Micropile Section Details � Total pile lengths varied between 17.9 m (Pier 3) and 20.6 m (Pier 2) • Outer steel casing: – 273 mm diameter ; 5.8 m to 9.3 m long – 13 mm wall thickness • Central steel reinforcement: – DSI #20 (69 mm diameter) threadbar – 80 ksi (551 MPa) • Additional inner casing at Pier 1: – to resist high bending moments – 168 mm diameter and 6.6 m long – 9.5 mm wall thickness

  9. Pre-Production Load Testing Pre-Production Load Testing � Important to load axially to failure to determine ultimate bond values for: • Verification of design assumptions and installation methodology • Assess if micropiles lengths and/or diameters can be reduced � Instrumentation adds value in refining design and understanding behaviour:

  10. Installation Methodology Installation Methodology � Duplex drilling system with eccentric down-hole hammer

  11. Micropile Load Testing Micropile Load Testing � Pre-production axial load tests: • Compression Test to 2.5 DL (3000 kN) • Lateral Test to 2.5 DL (250 kN) • Tension Test to 2.3 DL (2760 kN) • Two Sets (East Side and West Side) � Proof Tests: • Tension Test to 1.3 DL (1560 kN) • 12 piles tested (4 at each pier)

  12. Compression Test Compression Test

  13. Compression Test Results – East Side Compression Test Results – East Side 3500 Total Displacement 3000 Theoretical Elastic Response, Full Length Theoretical Elastic 2500 Response, Cased Length Axial Load, kN 2000 1500 1000 Micropile CE-2 (Pier 1) 500 Avg. Bond = 220 kPa (post- grouted) 0 0 5 10 15 20 25 30 35 40 Axial Displacement, mm

  14. Tension (Uplift) Test Results Tension (Uplift) Test Results 3000 2500 2000 Axial Load, kN 1500 1000 Pile R-E2 (Pier1) 500 Avg. Bond = 150 kPa (No post- grouting) 0 0 10 20 30 40 50 60 70 Displacement, mm

  15. Compression Test Results – West Side Compression Test Results – West Side 4000 Micropile C-W (Pier 3) 3500 Avg. Bond = 350 kPa (post-grouted) 3000 2500 Axial Load, kN 2000 1500 Total Displacement 1000 Theoretical Elastic Response, Full Length 500 Theoretical Elastic Response, Cased Length 0 0 5 10 15 20 25 30 35 40 Displacement, mm

  16. Comparison Between Design and Comparison Between Design and Measured Bond values Measured Bond values � Pier 3 (Sand and Gravel): Design Value = 140 and 250 kPa Measured Value = +190 to 350 kPa � Pier 1 (Dense Silt): Design = 190 kPa Measured = +150 to 220 kPa

  17. Lateral Load Test Lateral Load Test Piles Instrumented with In-Place Inclinometers

  18. Lateral Test Results Lateral Test Results -1 Ground Surface 0 1 2 Depth, m 3 4 5 LR-E1 Pile response was LL-E1 Predicted (design) stiffer than 6 -5 0 5 10 15 20 25 expected Horizontal Displacement, mm

  19. Proof (Uplift) Axial Load Tests Proof (Uplift) Axial Load Tests

  20. Proof Test Results Proof Test Results CPR Mile 62.4 Nipigon: Proof Tests 25.00 20.00 Movement (mm) 15.00 10.00 5.00 0.00 0 200 400 600 800 1000 1200 1400 1600 1800 Load (kN) P2-2 P2-7 P2-11 P3-24 P2-8 P3-10 P3-3 P3-18 P1-34 P1-31 P1-3 P1-14

  21. Test Results Summary Test Results Summary � Failures were not induced during pre- production load tests � Pre-production results confirmed design bond estimates and micropile sections and lengths � Proof tests satisfied acceptance criteria developed by CPR

  22. Summary Summary � Micropiles successfully applied as a cost-effective foundation upgrade system � Proven resistance to high axial and lateral loads and to applied moments � Existing state-of-practice and tools appear to be sufficient for design purposes

  23. QUESTIONS? QUESTIONS?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend