8 th International 8 th International Workshop Workshop on - - PowerPoint PPT Presentation

8 th international 8 th international workshop workshop
SMART_READER_LITE
LIVE PREVIEW

8 th International 8 th International Workshop Workshop on - - PowerPoint PPT Presentation

8 th International 8 th International Workshop Workshop on Micropiles on Micropiles Toronto Toronto September 26 to 29, 2007 September 26 to 29, 2007 Axial Compression, Axial Tension and Lateral Load Response of Pre-Production Micropiles


slide-1
SLIDE 1

Axial Compression, Axial Tension and Lateral Load Response of Pre-Production Micropiles for the CPR Mile 62.4 Nipigon Subdivision Bridge

8th International Workshop

  • n Micropiles

Toronto September 26 to 29, 2007

8th International Workshop

  • n Micropiles

Toronto September 26 to 29, 2007

slide-2
SLIDE 2

Case History Case History

Underpinning and jacketing of existing Canadian Pacific Railway (CPR) bridge foundations at Mile 62.4, Nipigon Subdivision (near Thunder Bay, Ontario)

  • Capital cost savings of 20 % compared to

replacement.

  • First of its kind project in Canada.

Approximately 130 year old structure

  • Steel Superstructure
  • Stone Masonry Piers (3 Piers)
  • Timber Piles and Mat Foundations

(overstressed)

slide-3
SLIDE 3
slide-4
SLIDE 4
slide-5
SLIDE 5

Project Team Project Team

Canadian Pacific Railway (Owner) Golder (Geotechnical Consultant, Micropile Designer and Construction Monitoring)

  • Donald Bruce (Advisor)

HMM (Construction Manager) LAS (General Contractor) GFC (Micropiling Contractor)

  • Isherwood Associates
slide-6
SLIDE 6

Golder Project Team Golder Project Team

Calgary

  • Dennis Becker
  • Peter Thomson
  • Blake Leew

Mississauga

  • Paul Dittrich
  • Arash Zakeri

Saskatoon

  • Greg Misfeldt
  • Dean Lorras
slide-7
SLIDE 7

Ground Conditions Ground Conditions

Pier 1

  • Sand, cobbles and masonry rubble fill
  • Compact to dense sand and gravel
  • Compact to very dense silt
  • Very stiff silty clay

Pier 2

  • Compact to dense sand and gravel
  • Compact to very dense silt

Pier 3

  • Sand, cobbles and masonry rubble fill
  • Compact to dense sand and gravel
  • Dense to very dense silt
slide-8
SLIDE 8

Design Criteria (Single Pile) Design Criteria (Single Pile)

Service loading conditions:

  • Maximum axial load = 1,200 kN
  • Maximum lateral load = 100 kN
  • Maximum moment = 100 kN-m

At design serviceability loading:

  • Settlement ≤ 6 mm
  • Differential settlement ≤ 3 mm
  • Lateral displacement ≤ 13 mm
slide-9
SLIDE 9

Design and Analysis Design and Analysis

Preliminary micropile sections and lengths selected using conventional methods Micropile sections and lengths refined and finalized using 3D finite element program (FB-Pier) Manual checks following AREMA

slide-10
SLIDE 10

Micropile Section Details Micropile Section Details

Total pile lengths varied between 17.9 m (Pier 3) and 20.6 m (Pier 2)

  • Outer steel casing:

– 273 mm diameter ; 5.8 m to 9.3 m long – 13 mm wall thickness

  • Central steel reinforcement:

– DSI #20 (69 mm diameter) threadbar – 80 ksi (551 MPa)

  • Additional inner casing at Pier 1:

– to resist high bending moments – 168 mm diameter and 6.6 m long – 9.5 mm wall thickness

slide-11
SLIDE 11
slide-12
SLIDE 12
slide-13
SLIDE 13

Pre-Production Load Testing Pre-Production Load Testing

Important to load axially to failure to determine ultimate bond values for:

  • Verification of design assumptions

and installation methodology

  • Assess if micropiles lengths and/or

diameters can be reduced

Instrumentation adds value in refining design and understanding behaviour:

slide-14
SLIDE 14

Installation Methodology Installation Methodology

Duplex drilling system with eccentric down-hole hammer

slide-15
SLIDE 15

Micropile Load Testing Micropile Load Testing

Pre-production axial load tests:

  • Compression Test to 2.5 DL (3000

kN)

  • Lateral Test to 2.5 DL (250 kN)
  • Tension Test to 2.3 DL (2760 kN)
  • Two Sets (East Side and West Side)

Proof Tests:

  • Tension Test to 1.3 DL (1560 kN)
  • 12 piles tested (4 at each pier)
slide-16
SLIDE 16

Compression Test Compression Test

slide-17
SLIDE 17

Compression Test Results – East Side Compression Test Results – East Side

500 1000 1500 2000 2500 3000 3500 5 10 15 20 25 30 35 40 Axial Displacement, mm Axial Load, kN Total Displacement Theoretical Elastic Response, Full Length Theoretical Elastic Response, Cased Length

Micropile CE-2 (Pier 1)

  • Avg. Bond = 220 kPa (post-

grouted)

slide-18
SLIDE 18

Tension (Uplift) Test Results Tension (Uplift) Test Results

500 1000 1500 2000 2500 3000 10 20 30 40 50 60 70 Displacement, mm Axial Load, kN

Pile R-E2 (Pier1)

  • Avg. Bond = 150 kPa (No post-

grouting)

slide-19
SLIDE 19

Compression Test Results – West Side Compression Test Results – West Side

500 1000 1500 2000 2500 3000 3500 4000

5 10 15 20 25 30 35 40 Displacement, mm Axial Load, kN Total Displacement Theoretical Elastic Response, Full Length Theoretical Elastic Response, Cased Length

Micropile C-W (Pier 3)

  • Avg. Bond = 350 kPa (post-grouted)
slide-20
SLIDE 20

Comparison Between Design and Measured Bond values Comparison Between Design and Measured Bond values

Pier 3 (Sand and Gravel): Design Value = 140 and 250 kPa Measured Value = +190 to 350 kPa Pier 1 (Dense Silt): Design = 190 kPa Measured = +150 to 220 kPa

slide-21
SLIDE 21

Lateral Load Test Lateral Load Test

Piles Instrumented with In-Place Inclinometers

slide-22
SLIDE 22

Lateral Test Results Lateral Test Results

  • 1

1 2 3 4 5 6

  • 5

5 10 15 20 25 Horizontal Displacement, mm Depth, m LR-E1 LL-E1 Predicted (design) Ground Surface

Pile response was stiffer than expected

slide-23
SLIDE 23

Proof (Uplift) Axial Load Tests Proof (Uplift) Axial Load Tests

slide-24
SLIDE 24

Proof Test Results Proof Test Results

CPR Mile 62.4 Nipigon: Proof Tests

0.00 5.00 10.00 15.00 20.00 25.00 200 400 600 800 1000 1200 1400 1600 1800 Load (kN) Movement (mm) P2-2 P2-7 P2-11 P3-24 P2-8 P3-10 P3-3 P3-18 P1-34 P1-31 P1-3 P1-14

slide-25
SLIDE 25

Test Results Summary Test Results Summary

Failures were not induced during pre- production load tests Pre-production results confirmed design bond estimates and micropile sections and lengths Proof tests satisfied acceptance criteria developed by CPR

slide-26
SLIDE 26

Summary Summary

Micropiles successfully applied as a cost-effective foundation upgrade system Proven resistance to high axial and lateral loads and to applied moments Existing state-of-practice and tools appear to be sufficient for design purposes

slide-27
SLIDE 27

QUESTIONS? QUESTIONS?