Load Test of Load Test of High Capacity Micropile Micropile High - - PowerPoint PPT Presentation
Load Test of Load Test of High Capacity Micropile Micropile High - - PowerPoint PPT Presentation
Load Test of Load Test of High Capacity Micropile Micropile High Capacity in Site in Site MASAO SAGARA MASAO SAGARA Load Test of Load Test of NEW- -High Capacity High Capacity NEW Micropile Micropile MASAO SAGARA MASAO SAGARA
Load Test of Load Test of NEW NEW-
- High Capacity
High Capacity Micropile Micropile
MASAO SAGARA MASAO SAGARA
Contents Contents
1. 1.Background(Construction Example of HMP) Background(Construction Example of HMP) 2.Purpose 2.Purpose 3.Outline of NEW 3.Outline of NEW-
- HMP
HMP 4.Result of the Pull Out Test with NEW 4.Result of the Pull Out Test with NEW-
- HMP
HMP 5.Conclusion 5.Conclusion
Contents Contents
1. 1.Background(Construction Example of HMP) Background(Construction Example of HMP) 2.Purpose 2.Purpose 3.Outline of NEW 3.Outline of NEW-
- HMP
HMP 4.Result of the pull out Test with NEW 4.Result of the pull out Test with NEW-
- HMP
HMP 5.Conclusion 5.Conclusion
Design & Construction Manual for Seismic Retrofit Design & Construction Manual for Seismic Retrofit Method for the Existing Bridge Foundation Method for the Existing Bridge Foundation
Content Contents s
Design & Construction Manual for Seismic Retrofit Method for the Design & Construction Manual for Seismic Retrofit Method for the Existing Bridge Foundation Existing Bridge Foundation
- Part 1 : General
Part 1 : General
- Part 2 : Design
Part 2 : Design
- Chapter 1 : General
Chapter 1 : General
- Chapter 2 : Material
Chapter 2 : Material
- Chapter 3 : Surveys
Chapter 3 : Surveys
- Chapter 4 : General Instructions
Chapter 4 : General Instructions
- Chapter 5 : General Instructions for Seismic Retrofit
Chapter 5 : General Instructions for Seismic Retrofit
- Chapter 6 : Elastic Design for Ordinary time and Level Earthquak
Chapter 6 : Elastic Design for Ordinary time and Level Earthquake e
- Chapter 7 : Ductility Design for Level
Chapter 7 : Ductility Design for Level Ⅱ Ⅱ Earthquake Earthquake
- Chapter 8 : Detail
Chapter 8 : Detail
- Part 3 : Construction
Part 3 : Construction
- Chapter 1 : General
Chapter 1 : General
- Chapter 2 : Construction Procedures
Chapter 2 : Construction Procedures
- Chapter 3 : Quality Control & Quality Assurance
Chapter 3 : Quality Control & Quality Assurance
L Lecture ecture to engineers to engineers about Design & about Design & Construction Manual Construction Manual
Contents Contents
1. 1.Background Background(Construction Example of HMP) (Construction Example of HMP) 2.Purpose 2.Purpose 3.Outline of NEW 3.Outline of NEW-
- HMP
HMP 4.Result of the pull out Test with NEW 4.Result of the pull out Test with NEW-
- HMP
HMP 5.Conclusion 5.Conclusion
Construction Example Construction Example
Seismic Retrofit of KAMENOKO Bridge Seismic Retrofit of KAMENOKO Bridge
Abutment A2 Abutment A1
Construction Example Construction Example
Seismic Retrofit of KAMENOKO Bridge Seismic Retrofit of KAMENOKO Bridge
- small bridge;
small bridge;
- 14m in length
14m in length
- 6m in width.
6m in width.
- There is a soft soil layer
There is a soft soil layer
- ver 10m in depth.
- ver 10m in depth.
- The influence on the
The influence on the house by the vibration house by the vibration
- f a large
- f a large-
- scale
scale machine was worried. machine was worried.
- HMP with a small
HMP with a small machine was applied. machine was applied.
Abutment A2 Abutment A1
Construction Example Construction Example
Seismic Retrofit of KAMENOKO Bridge Seismic Retrofit of KAMENOKO Bridge
- HMP penetrated
HMP penetrated through the abutment. through the abutment.
- Amount of piles
Amount of piles: : term ;17.5 term ;17.5m m× ×12 12piles, piles, 16.5 16.5m m× ×14 14piles, Total piles, Total 476m 476m
Abutment A2
Construction Example Construction Example
Seismic Retrofit of KAMENOKO Bridge Seismic Retrofit of KAMENOKO Bridge
Abutment A2 Abutment A1
Construction situation Construction situation
Construction Example Construction Example
Seismic Retrofit of KAMENOKO Bridge Seismic Retrofit of KAMENOKO Bridge
Abutment A2
Construction situation Construction situation (digging) (digging)
Construction Example Construction Example
Seismic Retrofit of KAMENOKO Bridge Seismic Retrofit of KAMENOKO Bridge
Abutment A1
Construction situation Construction situation (digging) (digging)
Construction Example Construction Example
Seismic Retrofit of KAMENOKO Bridge Seismic Retrofit of KAMENOKO Bridge
Abutment A1
Finished construction
Construction Example Construction Example
Seismic Retrofit of KAMENOKO Bridge Seismic Retrofit of KAMENOKO Bridge
Abutment A2
Finished construction
On the other hand On the other hand… …
Recently, the intersection in Recently, the intersection in the city always gets a traffic the city always gets a traffic jam. jam.
It is necessary to overpass the It is necessary to overpass the intersection in Japan intersection in Japan
Recently, the intersection in the city always gets a traffic jam. We need the
- verpass of the
intersection to cancel the traffic jam. When the
- verpass
is constructed without stopping the car in the city, an enough construction place might not be able to be secured. Then, the application of HMP is expected as a new foundation.
Application Application E Example xample to to O Overpass verpass of
- f
HMP HMP
HMP
Application to Abutment Application to Abutment Foundation Foundation
Problem and Measure Problem and Measure
- Problem
Problem
It is important that the overpass can be
constructed cheaply and early.
But HMP is necessary to construct a lot of pile
as a new foundation of the abutment or the pier.
- Measures
Measures
Then, HMP is improved so that the bearing capacity
may increase.
As a result, the total number of the HMP can be
decreased.
Moreover, the construction period can be short and the
cost can be made down.
Contents Contents
1. 1.Background(Construction Example of HMP) Background(Construction Example of HMP) 2.Purpose 2.Purpose 3.Outline of NEW 3.Outline of NEW-
- HMP
HMP 4.Result of the pull out Test with NEW 4.Result of the pull out Test with NEW-
- HMP
HMP 5.Conclusion 5.Conclusion
Purpose Purpose
Bond length of HMP is only bearing layer. We propose HMP of the improvement type by
which the whole area of the pile is bond length to increase the bearing capacity.
This is called NEW-HMP.
We executed the pull out load test of NEW-HMP,
and confirmed the bearing capacity.
I describe result of pull out test.
Contents Contents
1. 1.Background(Construction Example of HMP) Background(Construction Example of HMP) 2.Purpose 2.Purpose 3.Outline of NEW 3.Outline of NEW-
- HMP
HMP 4.Result of the pull out Test with NEW 4.Result of the pull out Test with NEW-
- HMP
HMP 5.Conclusion 5.Conclusion
Improvement of HMP Improvement of HMP
- New
New-
- HMP
HMP
- Diameter is
Diameter is larger than HMP. larger than HMP.
- Bond length of
Bond length of NEW NEW-
- HMP is
HMP is longer than that longer than that
- f HMP.
- f HMP.
G r
- ut
C oupl er f
- r
Def
- rm ed
Bar
Foot i ng Top Pl at e Def
- r
m ed Bar C oupl er f
- r
St eel pi pe D r i l l i ng casi ng
Sof t G r
- und
C ent r al i zer St eel pi pe Top Pl at e D r i l l i ng Bi t Bond Lengt h Bond Lengt h
Bear i ng G r
- und
New Type
Bond length of HMP is only bearing layer. Whole area of the NEW-HMP is Bond length.
HMP NEW-HMP
Construction Process of NEW Construction Process of NEW-
- HMP
HMP
Bear i ng Layer Sof t Layer
② Washing in hole & Remove inner drill bit & rod ③ Insertion of reinforcement 7in. steel pipe(outside diameter178㎜) ⑤ I ni ti al i nj ecti
- n
( Unti l
- ver
f l
- wi
ng) ⑥ Remove temporary casing ⑦ Inject grout under pressure ① Excavation (casing boring) 9-5/8in. Steel Pipes (outside diameter 244.5, inside diameter 220.5㎜)
Bond Length
⑧ Treatment of pile head ④ Insertion of deformed bar gr
- ut
deformed bar
Construction situation Construction situation
Construction situation Construction situation
Construction situation Construction situation
Contents Contents
1. 1.Background(Construction Example of HMP) Background(Construction Example of HMP) 2.Purpose 2.Purpose 3.Outline of NEW 3.Outline of NEW-
- HMP
HMP 4.Result of the pull out Test with NEW 4.Result of the pull out Test with NEW-
- HMP
HMP 5.Conclusion 5.Conclusion
Outline of Test Pile Outline of Test Pile
- The strain
The strain gages are put gages are put
- n the steel
- n the steel
pipe and the pipe and the deformed bar. deformed bar.
①( G L-1. 75m ) ②( G L-3. 25m ) ③( G L-4. 75m ) ④( G L-6. 25m ) ⑤( G L-7. 75m ) ⑥( G L-9. 25m ) ⑦( G L-12. 25m ) ⑧( G L-13. 50m ) ⑨( G L-14. 50m ) Bond Length(Bearing Layer) 5,000 Bond Length (Soft Layer) 10,000 2000 3000 500 178 244. 5 0点( G L+0. 10m ) 150
0 102030405060 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
N value D epth(m )
filling soil (FI) loam (L M ) fine sa nd (FS ) c lay (C L ) fine sand (FS ) silt (M) fine sa nd (FS ) 2.9m 4.0m 6.2m 7.7m 8.8m 10.5m
▽G round
- f
l
- ad
test
Strain Gage
Pull out test situation Pull out test situation
Curve of Load and Displacement Curve of Load and Displacement
10 20 30 40 50 60 500 1000 1500 2000 2500
Displacement(㎜) Load(k N) Design load ultimate load;1980kN yield load;1800kN New-HMP HMP
The load of NEW-HMP is larger than that of the design and HMP. The Bearing Capacity
- f NEW-HMP was about 40 percent larger
than that of HMP (value of the average).
400 800 1200 1600 2000 2400 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A xial Force (kN) Depth(m) 180.2(kN) 359.5(kN) 538.9(kN) 726.1(kN) 902.0(kN) 1080.5(kN) 1259.8(kN) 1454.8(kN) 1626.4(kN) 1799.7(kN) 1977.3(kN) 2156.7(kN) (a)A xial force requested from strain of Deformed B ar (b)A xial force requested from strain of Steel Pipe
400 800 1200 1600 2000 2400 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
A xial Force (kN) Depth(m)
0 20 40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
N value Depth(m)
filling soil (FI) loam (LM) fine sand (FS) clay (CL) fine sand (FS) silt (M) fine sand (FS) 2.9m 4.0m 6.2m 7.7m 8.8m 10.5m
①( GL-1. 75m ) ②( GL-3. 25m ) ③( GL-4. 75m ) ④( GL-6. 25m ) ⑤( GL-7. 75m ) ⑥( GL-9. 25m ) ⑦( GL-12. 25m ) ⑧( GL-13. 50m ) ⑨( GL-14. 50m ) Bond Length(Bearing Layer) 5,000 Bond Length (Soft Layer) 10,000 2000 3000 500 178 244. 5 150
▽Gr
- und
- f
l
- ad
t est
Axial force Axial force – – Depth Depth
The axial force has also decreased. It is understood that the whole area of the pile is bond length.
Maximum Skin Friction Maximum Skin Friction-
- Depth
Depth
0 20 40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
N value Depth(m)
filling soil (FI) loam (LM) fine sand (FS) clay (CL) fine sand (FS) silt (M) fine sand (FS) 2.9m 4.0m 6.2m 7.7m 8.8m 10.5m 100 200 300 400 500 600 700 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
M aximum Skin Friction(kN/m2) Depth(m) Design Test pile(No.1)
① ( GL-1. 75m ) ② ( GL-3. 25m ) ③ ( GL-4. 75m ) ④ ( GL-6. 25m ) ⑤ ( GL-7. 75m ) ⑥ ( GL-9. 25m ) ⑦ ( GL- 12. 25m ) ⑧ ( GL- 13. 50m ) ⑨ ( GL- 14. 50m ) Bond Length(Bearing Layer) 5,000 Bond Length (Soft Layer) 10,000 2000 3000 500 178 244. 5 150
▽ Gr
- und
- f
l
- a
d t es t
Maximum Skin Friction was also larger than the design.
Contents Contents
1. 1.Background(Construction Example of HMP) Background(Construction Example of HMP) 2.Purpose 2.Purpose 3.Outline of NEW 3.Outline of NEW-
- HMP
HMP 4.Result of the pull out Test with NEW 4.Result of the pull out Test with NEW-
- HMP
HMP 5.Conclusion 5.Conclusion
Conclusion Conclusion
- The Bearing Capacity of NEW
The Bearing Capacity of NEW-
- HMP was about 40
HMP was about 40 percent larger than that of HMP. percent larger than that of HMP.
- NEW
NEW-
- HMP is a calculation, which can reduce the
HMP is a calculation, which can reduce the number of the pile by about 20% compared with number of the pile by about 20% compared with HMP. HMP.
- The problem of NEW
The problem of NEW-
- HMP is negative friction
HMP is negative friction though it did not become a problem in the design though it did not become a problem in the design in HMP. It is necessary to examine the method of in HMP. It is necessary to examine the method of designing the skin friction in the soft layer. designing the skin friction in the soft layer.
- We want to make the cost down adding the
We want to make the cost down adding the improvement further in the future. improvement further in the future.
THE END THE END
Thank you for your attention!! Thank you for your attention!!
Construction Example Construction Example(2)
(2)
Seismic Retrofit of Seismic Retrofit of KAMEIDO water service station
KAMEIDO water service station
- In the upper part,
In the upper part, there are a baseball there are a baseball ground and tennis ground and tennis courts. courts.
Construction Example Construction Example(2)
(2)
Seismic Retrofit of Seismic Retrofit of KAMEIDO water service station
KAMEIDO water service station
- Built in 1970
Built in 1970
- height ; 7.7m
height ; 7.7m
- Width;
Width; 104m 104m× ×104m 104m
- Volume of
Volume of water kept in water kept in store; store; 60,000m 60,000m3
3
7. 7m
104m 104m
W ATER
ground plan a cross section
- Built in 1970
Built in 1970
- height ; 7.7m
height ; 7.7m
- Width;
Width; 104m 104m× ×104m 104m
- Volume of
Volume of water kept in water kept in store; store; 60,000m 60,000m3
3
104m 104m 7.7m Construction Example Construction Example(2)
(2)
Seismic Retrofit of Seismic Retrofit of KAMEIDO water service station
KAMEIDO water service station
Construction Example Construction Example(2)
(2)
Seismic Retrofit of Seismic Retrofit of KAMEIDO water service station
KAMEIDO water service station
Existing piles 35~48m φ600mm
- The number of existing
The number of existing piles are 1696. piles are 1696.
Construction Example Construction Example(2)
(2)
Seismic Retrofit of Seismic Retrofit of KAMEIDO water service station
KAMEIDO water service station
HMP
Existing piles 35~48m φ600mm 38~48m φ178mm
Construction Example Construction Example(2)
(2)
Seismic Retrofit of Seismic Retrofit of KAMEIDO water service station
KAMEIDO water service station
Height 6.3m
PWRI Collaboration Project PWRI Collaboration Project with Private Companies with Private Companies
- Development of
Development of Rapid Overpass Rapid Overpass Method Method
- The application of
The application of micropiles micropiles is is researched as a new researched as a new foundation. foundation.
Design and construction manual
PWRI Collaboration Project PWRI Collaboration Project with Private Companies with Private Companies
(Development of Rapid Overpass Method) (Development of Rapid Overpass Method)
橋 梁 区 間 高耐力マイクロパイル プレキャスト高欄 ア プ ロ ー チ 区 間 ( 補 強 盛 土 ) 15m 分割型ボックスカルバート 30m ア プ ロ ー チ 区 間 15m
※橋梁区間に充腹式アーチ橋を用いた例 ※
側 面 図 平 面 図
HMP
Curve of Load and Displacement Curve of Load and Displacement
10 20 30 40 50 60 500 1000 1500 2000 2500
Displacement(㎜) Load(k N ) No.1 No.2 No.3 Design load H M P NEW-H M P
The load of NEW-HMP is larger than that of the design and HMP. The Bearing Capacity
- f NEW-HMP was about 40 percent larger
than that of HMP.
Maximum Skin Friction Maximum Skin Friction-
- Depth
Depth
0 20 40
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
N value Depth(m)
filling soil (FI) loam (LM) fine sand (FS) clay (CL) fine sand (FS) silt (M) fine sand (FS) 2.9m 4.0m 6.2m 7.7m 8.8m 10.5m 100 200 300 400 500 600 700 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
M aximum Skin Friction(kN/m2) 深度(m) Design No.1 No2 No.3
① ( GL-1. 75m ) ② ( GL-3. 25m ) ③ ( GL-4. 75m ) ④ ( GL-6. 25m ) ⑤ ( GL-7. 75m ) ⑥ ( GL-9. 25m ) ⑦ ( GL- 12. 25m ) ⑧ ( GL- 13. 50m ) ⑨ ( GL- 14. 50m ) Bond Length(Bearing Layer) 5,000 Bond Length (Soft Layer) 10,000 2000 3000 500 178 244. 5 150
▽ Gr
- und
- f
l
- a
d t es t