Advanced Interpretation of Instrumented Micropile Load Tests - - PowerPoint PPT Presentation
Advanced Interpretation of Instrumented Micropile Load Tests - - PowerPoint PPT Presentation
Advanced Interpretation of Instrumented Micropile Load Tests International Workshop on Micropiles, Toronto September 28, 2007 Terence P. Holman, Ph.D., P.E. Senior Engineer-Geotec, MORETRENCH Thomas J. Tuozzolo, P.E. Vice President,
Introduction
- Two case histories of strain gauge
instrumented micropile load tests
– Case History No. 1 – 167 Johnson Street – Case History No. 2 – Dublin Road Pump Station (DRPS) – All piles Type B pressure grouted with typically developed pressures of 345 kPa
- Highlight aspects of pile mechanics
– Degradation of secant pile modulus – Nonuniform load distribution – Generation of micropile tip resistance and shaft resistance
Case History No. 1-167 Johnson St
Dense to v. dense m/c SAND (NYCBC 7-65) δv
- 40+ story residential high
rise on mixed mat/spread footing foundations
- Dense to v. dense sand
and sand/gravel deposits
- Excessive δv beneath
heavily loaded elevator core
- Minimize δvincorporate
micropiles to create “piled raft” effect
– Allow high δ and low F.S.
- 2 strain gauge
instrumented load tests
– 14 gauges per pile
Ground Conditions and Pile Design
SW Strain Gauge
0 m 6.1 m 9.1 m 12.2 m 13.7 m 15.2 m 17.8 m
384 mm Isolation Casing EB Strain Gauge
SR-2 SR-1 SG-1 SG-2 SG-3 SG-4 SG-5 SG-1 SG-2 SG-3 SG-4 SG-5
273 mm Casing
DL=1112 kN, TL=2224 kN
25 50 75 100 125 150 Uncorrected SPT N-value (blows/0.3 m) 24 21 18 15 12 9 6 3 Depth below Ground Surface (m)
LB-1 LB-2 LB-3 LB-4 LB-5 LB-6 LB-7 LB-8 LB-9
URBAN FILL SAND, SM TO TR GRAVEL (SP)
Instrumentation
- Spot-weldable gauges on bar (10 ea.)
– Accuracy=15 µε, Sensitivity=0.4 µε
- Embedment gauges in grout (4 ea.)
– Accuracy=15 µε, Resolution=1.0 µε
- Grout strength and unconfined modulus testing
– E=13.5 to 14.5 GPa (Unconfined secant at ε=0.11%) – f’c=44.8 MPa (cylinders) to 62.1 MPa (cubes)
Test Pile Installation
Left - Installation of 273 mm test element (pile) Top – Installation of 194 mm diameter reaction anchor, 1334 kN capacity
Test Pile Construction
Left - Installation of 273 mm test element (pile) Top – Buried old foundation wall and
- bstructions
Load Testing Data
1000 2000 3000 Applied Pile Top Load (kN) 50 40 30 20 10 Pile Butt Settlement (mm)
SR-1 (6.1 m Bond) SR-2 (9.1 m Bond) Net Permanent Settlement=29 mm Net Permanent Settlement=8 mm Plunging Failure at 2224 kN
- Max. Test
Load= 2669 kN
200 400 600 800 1000 Measured Strain (µε) 18 16 14 12 10 8 6 4 2 Depth below Ground Surface (m)
P=556 kN P=1112 kN P=1669 kN P=2224 kN Post Failure (1771 kN) Residual Tip Isolation Casing Geometry Change Tip Pile Casing Geometry Change
400 800 1200 1600 2000 Measured Strain (µε) 18 16 14 12 10 8 6 4 2 Depth below Ground Surface (m)
P=556 kN P=1112 kN P=1669 kN P=2224 kN P=2669 kN Tip Isolation Casing Geometry Change Tip Pile Casing Geometry Change
SR-1 SR-2
Case History No. 2-DRPS
- Ground loss, heave,
and settlement around 3 pump station structures following excavation and pile driving
- Complex ground
conditions
– Excess head/high groundwater levels – Marine glauconitic silty fine sand deposits
PUMP CHAMBER WET WELL INLET CHAMBER
SILT, SAND, AND CLAY FILL GLAUCONITIC F/M SAND SHEET PILES
(BUILT) (NOT BUILT) (NOT BUILT)
Ground Conditions and Pile Design
10 20 30 40 50 60 Uncorrected SPT N-value (blows/0.3 m) 24 21 18 15 12 9 6 3 Depth below Ground Surface (m)
B-1 (pre-failure) B-2 (pre-failure) B-3 B-4 B-5 B-6
SILTY SAND (SM)
GLAUCONITIC F/M SAND
SAND, SILT, AND CLAY (SM, ML, CL)
Zone of Ground Loss/Disturbance
SW Strain Gauges 0 m 13.6 m 16.8 m 20.3 m
DL=534 kN, TL=1067 kN
Isolation Casing 194mm OD Casing 1.5 m
Load Testing Data
200 400 600 800 1000 Applied Pile Top Load (kN) 50 40 30 20 10 Pile Butt Settlement (mm)
Net Permanent Settlement=26 mm Plunging Failure at 933 kN
200 400 600 800 1000 Measured Strain (µε) 21 20 19 18 17 16 15 14 13 Depth below Ground Surface (m)
P=267 kN P=534 kN P=801 kN P=934 kN Post Failure Full Unload
SG-3 Level SG-2 Level SG-1 Level
Analysis and Interpretation
- Nonlinear σ−ε behavior of composite pile
section
- Calculated load distribution along bond
length
- Deformation-based generation of micropile
tip resistance and bond resistance
Composite Micropile Behavior
200 400 600 800 1000 Measured Strain (µε) 20 22 24 26 28 Estimated Secant Modulus (GPa)
Esec (MPa)= -0.0063ε + 27.46
200 400 600 800 1000 1200 Measured Strain (µε) 10 20 30 40 50 60 70 Estimated Secant Modulus (GPa)
Cased Zone Secant Modulus
- Approx. Secant Modulus (Field Data)
Bond Zone Secant Modulus
Esec (GPa)= -0.0081ε + 42.89 (Cased) Esec (GPa)= -0.0104ε + 26.32 (Bond)
SR-1 DRPS-Bond Zone
- Interpretation of load
distribution
– P=εApEp
- Composite pile has
complex σ−ε behavior
- Secant modulus of
composite pile degrades with increasing strain
– Linear degradation model invoked
- Calculate Esec as f(ε)
Load Distribution
200 400 600 800 1000 Interpreted Load (kN) 21 20 19 18 17 16 15 14 13 Depth below Ground Surface (m)
P=267 kN P=534 kN P=801 kN P=934 kN Post Failure Full Unload
DRPS
400 800 1200 1600 2000 2400 Interpreted Load (kN) 18 16 14 12 10 8 6 4 2 Depth below Ground Surface (m)
P=556 kN P=1112 kN P=1669 kN P=2224 kN Post Failure (1771 kN) Residual
SR-1
500 1000 1500 2000 2500 3000 Interpreted Load (kN) 18 16 14 12 10 8 6 4 2 Depth below Ground Surface (m)
P=556 kN P=1112 kN P=1669 kN P=2224 kN P=2669 kN
SR-2
- Non-constant mobilized bond stress for piles with short
bond length (SR-1 and DRPS)
– Approaches constant value near failure – 16-23 kN/m for SR-1, 25-28.5 kN/m for SR-2, 8.5-12.1 kN/m for DRPS
- Significant ultimate tip resistance for SR-1 and DRPS
– 19-25% of total ultimate capacity (300-700 kN)
Generation of Tip Resistance
- Total pile deformation
- Tip resistance mobilizes
nonlinearly for piles with short bond length
– Initial yield at settlement ratio
- f 0.01 to 0.02
– Limiting values at settlement ratio of 0.08 to 0.10
- Small tip resistance
developed for SR-2
– No failure condition – Denser soils at pile tip
- Trends similar to larger
deep foundations
10 20 30 40
- Calc. Pile Tip Settlement (mm)
200 400 600 800 Mobilized Tip Load (kN)
SR-1 SR-2 DRPS
0.02 0.04 0.06 0.08 0.1 0.12 Normalized Tip Settlement δt/Db 0.2 0.4 0.6 0.8 1 1.2 Normalized Tip Load Qt/Qtmax
SR-1 SR-2 DRPS
t b c
δ δ δ δ + + =
∫
= +
L b c
εdz ) δ (δ
Generation of Bond Resistance
10 20 30 40
- Calc. Shaft Compression
and Tip Settlement (mm) 100 200 300 Average Bond Shear Stress (kPa)
SR-1 SR-2 DRPS
- Develops with compression of bond zone and tip
displacement (δb+δt)
- 6 to 8 mm of deformation required to initiate failure for
short bond length piles (≈0.1% Lb)
- Ultimate τ reached between 10 and 20 mm (≈ 0.2% Lb)
- No failure for SR-2 with long bond length
Summary and Conclusions
- Strain gauges can point out changes in
pile geometry
- Composite, nonlinear nature of micropiles
complicates stress-strain response
- Resistance distribution is nonuniform
along bond length
- Significant micropile tip resistance may be
mobilized for shorter bond length piles
- Instrument for better understanding!!
Summary and Conclusions
- Implications for analysis and design