advanced interpretation of instrumented micropile load
play

Advanced Interpretation of Instrumented Micropile Load Tests - PowerPoint PPT Presentation

Advanced Interpretation of Instrumented Micropile Load Tests International Workshop on Micropiles, Toronto September 28, 2007 Terence P. Holman, Ph.D., P.E. Senior Engineer-Geotec, MORETRENCH Thomas J. Tuozzolo, P.E. Vice President,


  1. Advanced Interpretation of Instrumented Micropile Load Tests International Workshop on Micropiles, Toronto September 28, 2007 Terence P. Holman, Ph.D., P.E. Senior Engineer-Geotec, MORETRENCH Thomas J. Tuozzolo, P.E. Vice President, MORETRENCH

  2. Introduction • Two case histories of strain gauge instrumented micropile load tests – Case History No. 1 – 167 Johnson Street – Case History No. 2 – Dublin Road Pump Station (DRPS) – All piles Type B pressure grouted with typically developed pressures of 345 kPa • Highlight aspects of pile mechanics – Degradation of secant pile modulus – Nonuniform load distribution – Generation of micropile tip resistance and shaft resistance

  3. Case History No. 1-167 Johnson St • 40+ story residential high rise on mixed mat/spread footing foundations • Dense to v. dense sand and sand/gravel deposits • Excessive δ v beneath heavily loaded elevator core • Minimize δ v � incorporate δ v micropiles to create “piled raft” effect – Allow high δ and low F.S. • 2 strain gauge instrumented load tests – 14 gauges per pile Dense to v. dense m/c SAND (NYCBC 7-65)

  4. Ground Conditions and Pile Design DL=1112 kN, TL=2224 kN SR-1 SR-2 0 0 m LB-1 URBAN FILL SG-1 SG-1 384 mm LB-2 Isolation 3 LB-3 Casing LB-4 Depth below Ground Surface (m) LB-5 273 mm 6 LB-6 Casing LB-7 LB-8 6.1 m LB-9 SG-2 SG-2 9 SAND, SM TO TR GRAVEL (SP) EB Strain Gauge 12 9.1 m SG-3 SG-3 15 12.2 m SG-4 18 13.7 m SG-4 15.2 m SG-5 21 SW Strain Gauge 17.8 m 24 SG-5 0 25 50 75 100 125 150 Uncorrected SPT N-value (blows/0.3 m)

  5. Instrumentation • Spot-weldable gauges on bar (10 ea.) – Accuracy=15 µε , Sensitivity=0.4 µε • Embedment gauges in grout (4 ea.) – Accuracy=15 µε , Resolution=1.0 µε • Grout strength and unconfined modulus testing – E=13.5 to 14.5 GPa (Unconfined secant at ε =0.11% ) – f’ c =44.8 MPa (cylinders) to 62.1 MPa (cubes)

  6. Test Pile Installation Left - Installation of 273 mm test element (pile) Top – Installation of 194 mm diameter reaction anchor, 1334 kN capacity

  7. Test Pile Construction Left - Installation of 273 mm test element (pile) Top – Buried old foundation wall and obstructions

  8. Load Testing Data 0 2 SR-1 0 Depth below Ground Surface (m) 4 Tip Isolation Casing 6 Geometry Change 8 Max. Test Tip Pile Casing 10 Load= 2669 kN Geometry Change 10 Pile Butt Settlement (mm) 12 Net Permanent 14 Settlement=8 mm P=556 kN 20 P=1112 kN P=1669 kN 16 P=2224 kN Post Failure (1771 kN) Residual 18 0 200 400 600 800 1000 Net Permanent 30 Measured Strain ( µε ) Settlement=29 mm 0 SR-2 2 Plunging Failure Depth below Ground Surface (m) at 2224 kN 40 4 Tip Isolation Casing 6 Geometry Change SR-1 (6.1 m Bond) 8 SR-2 (9.1 m Bond) 50 10 Tip Pile Casing Geometry Change 0 1000 2000 3000 12 Applied Pile Top Load (kN) 14 P=556 kN P=1112 kN 16 P=1669 kN P=2224 kN P=2669 kN 18 0 400 800 1200 1600 2000 Measured Strain ( µε )

  9. Case History No. 2-DRPS • Ground loss, heave, PUMP WET WELL INLET CHAMBER CHAMBER and settlement (BUILT) (NOT BUILT) (NOT BUILT) around 3 pump station structures following excavation and pile driving SILT, SAND, AND CLAY • Complex ground FILL conditions – Excess head/high groundwater levels – Marine glauconitic SHEET PILES silty fine sand GLAUCONITIC F/M SAND deposits

  10. Ground Conditions and Pile Design DL=534 kN, TL=1067 kN 0 m 0 B-1 (pre-failure) SILTY SAND (SM) B-2 (pre-failure) Isolation B-3 3 B-4 SAND, SILT, AND CLAY Casing Depth below Ground Surface (m) B-5 B-6 6 194mm OD Zone of Ground (SM, ML, CL) Casing SW Strain Loss/Disturbance 9 Gauges 1.5 m 12 13.6 m GLAUCONITIC F/M SAND 15 16.8 m 18 20.3 m 21 24 0 10 20 30 40 50 60 Uncorrected SPT N-value (blows/0.3 m)

  11. Load Testing Data 0 13 Plunging Failure SG-1 Level at 933 kN 14 Depth below Ground Surface (m) 10 Pile Butt Settlement (mm) 15 16 20 SG-2 Level 17 Net Permanent 30 Settlement=26 mm 18 P=267 kN 19 P=534 kN 40 P=801 kN P=934 kN 20 Post Failure SG-3 Level Full Unload 21 50 0 200 400 600 800 1000 0 200 400 600 800 1000 Measured Strain ( µε ) Applied Pile Top Load (kN)

  12. Analysis and Interpretation • Nonlinear σ−ε behavior of composite pile section • Calculated load distribution along bond length • Deformation-based generation of micropile tip resistance and bond resistance

  13. Composite Micropile Behavior 28 Estimated Secant Modulus (GPa) • Interpretation of load DRPS-Bond Zone distribution 26 – P= ε A p E p 24 • Composite pile has E sec (MPa)= -0.0063 ε + 27.46 22 complex σ−ε behavior • Secant modulus of 20 0 200 400 600 800 1000 composite pile Measured Strain ( µε ) 70 Estimated Secant Modulus (GPa) degrades with SR-1 Cased Zone Secant Modulus Approx. Secant Modulus (Field Data) 60 increasing strain Bond Zone Secant Modulus 50 – Linear degradation 40 model invoked E sec (GPa)= -0.0081 ε + 42.89 (Cased) 30 • Calculate E sec as f( ε ) 20 E sec (GPa)= -0.0104 ε + 26.32 (Bond) 10 0 200 400 600 800 1000 1200 Measured Strain ( µε )

  14. Load Distribution 0 0 13 2 2 14 Depth below Ground Surface (m) Depth below Ground Surface (m) Depth below Ground Surface (m) 4 4 15 6 6 16 8 8 17 10 10 18 SR-1 SR-2 DRPS 12 12 P=556 kN 19 P=267 kN 14 14 P=1112 kN P=556 kN P=534 kN P=1669 kN P=1112 kN P=801 kN P=2224 kN 20 P=1669 kN 16 16 P=934 kN Post Failure P=2224 kN (1771 kN) Post Failure P=2669 kN Full Unload Residual 18 18 21 0 400 800 1200 1600 2000 2400 0 500 1000 1500 2000 2500 3000 0 200 400 600 800 1000 Interpreted Load (kN) Interpreted Load (kN) Interpreted Load (kN) • Non-constant mobilized bond stress for piles with short bond length (SR-1 and DRPS) – Approaches constant value near failure – 16-23 kN/m for SR-1, 25-28.5 kN/m for SR-2, 8.5-12.1 kN/m for DRPS • Significant ultimate tip resistance for SR-1 and DRPS – 19-25% of total ultimate capacity (300-700 kN)

  15. Generation of Tip Resistance • Total pile deformation 800 Mobilized Tip Load (kN) δ = δ + δ + δ 600 c b t ∫ + = ( δ δ ) ε dz c b 400 L • Tip resistance mobilizes nonlinearly for piles with 200 SR-1 SR-2 short bond length DRPS 0 – Initial yield at settlement ratio 0 10 20 30 40 of 0.01 to 0.02 Calc. Pile Tip Settlement (mm) – Limiting values at settlement 1.2 ratio of 0.08 to 0.10 Normalized Tip Load Q t /Q tmax 1 • Small tip resistance 0.8 developed for SR-2 0.6 – No failure condition – Denser soils at pile tip 0.4 SR-1 • Trends similar to larger 0.2 SR-2 DRPS deep foundations 0 0 0.02 0.04 0.06 0.08 0.1 0.12 Normalized Tip Settlement δ t /D b

  16. Generation of Bond Resistance 300 Average Bond Shear Stress (kPa) 200 100 SR-1 SR-2 DRPS 0 0 10 20 30 40 Calc. Shaft Compression and Tip Settlement (mm) • Develops with compression of bond zone and tip displacement ( δ b + δ t ) • 6 to 8 mm of deformation required to initiate failure for short bond length piles ( ≈ 0.1% L b ) • Ultimate τ reached between 10 and 20 mm ( ≈ 0.2% L b ) • No failure for SR-2 with long bond length

  17. Summary and Conclusions • Strain gauges can point out changes in pile geometry • Composite, nonlinear nature of micropiles complicates stress-strain response • Resistance distribution is nonuniform along bond length • Significant micropile tip resistance may be mobilized for shorter bond length piles • Instrument for better understanding!!

  18. Summary and Conclusions • Implications for analysis and design – Structural assessment of micropile response should account for real σ−ε behavior (i.e. nonlinear material behavior) – For controllable design scenarios micropile tip resistance could be considered – Short bond lengths for micropiles should be used cautiously due to the relatively small bond movement/compression required to reach ultimate capacity

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend