town of norwich
play

TOWN OF NORWICH Norwich Pool Dam and Recreation Area PRESENTATION - PowerPoint PPT Presentation

TOWN OF NORWICH Norwich Pool Dam and Recreation Area PRESENTATION by Shawn Patenaude, P .E. August 20, 2012 1 2 Existing Conditions Impact from Tropical Storm Irene Amount of rainfall Overtopping Erosion of right embankment


  1. TOWN OF NORWICH Norwich Pool Dam and Recreation Area PRESENTATION by Shawn Patenaude, P .E. August 20, 2012 1

  2. 2

  3. Existing Conditions Impact from Tropical Storm Irene • Amount of rainfall • Overtopping • Erosion of right embankment Conclusions from Visual Inspection and Desktop Analysis • Vintage concrete (1949) - Minimal reinforcement and cracks • Antiquated fmashboard design - Nonfunctional 1

  4. Project Approach Address Deficiencies Through Design • Inadequate hydraulic spillway - Overtopping in 1979 and 2011 caused right embankment erosion. • Deteriorated spillway concrete has led to structural instability • Inoperable fmashboard system - Flashboards are braced reducing hydraulic capacity during fmood fmows. • Manual stoplog section is often utilized during inclement conditions. • Unprotected abutments - If the left embankment hadn’t eroded, overtopping would have been widespread and additional damages would have occurred. Conform to Regulatory Requirements • Adequate Hydraulic capacity (1% storm frequency) - 6" of rain in one 24-hour period • Address sediment transport - Operable low-level gates - Sediment management plan • Fish passage element - Constructed natural fjsh bypass - Fish ladder - Flow management 2

  5. Alternative 1 - Rehabilitate Existing Structure Address Deficiencies • New concrete training walls • Raise right abutment • Denil fjsh ladder • Articulated concrete blocks on left embankment • New fmashboard system • Concrete overfmow section • Rising stem sluice gate 3

  6. Alternative 1 - Rehabilitate Existing Structure Alt 1 pdf 4

  7. Denil Fish Ladder Alt 1 pdf 5

  8. Articulated Concrete Blocks 6

  9. Flash Board System Alt 1 pdf 7

  10. Concrete Overfmow Section Alt 1 pdf 8

  11. Alternative 1 - Rehabilitate Existing Structure Address Deficiencies • New concrete training walls • Raise right abutment • Denil fjsh ladder • Articulated concrete blocks on left embankment • New fmashboard system • Concrete overfmow section • Rising stem sluice gate Conclusion of Alternative 1 • Hydraulic capacity - water level during storm • Structural integrity • Fish bypass • Sediment 9

  12. 10 Alternative 2 - Ogee Spillway Design Address Deficiencies • Remove and replace entire dam • Raise right abutment • 50-foot-span ogee spillway • Constructed natural fjsh bypass • Articulated concrete blocks on left embankment • Rising stem sluice gate 10

  13. Alternative 2 - Ogee Spillway Design Alt 1 pdf 11

  14. Ogee Spillway 12

  15. Constructed Natural Fish Bypass 13

  16. 14 Alternative 2 - Ogee Spillway Design Address Deficiencies • Remove and replace entire dam • Raise right abutment • 50-foot-span ogee spillway • Constructed natural fjsh bypass • Articulated concrete blocks on left embankment • Rising stem sluice gate Conclusion of Alternative 2 • Hydraulic capacity - water level during storm • Structural integrity • Fish bypass • Sediment 14

  17. Alternative 3 - Labyrinth Weir Spillway Address Deficiencies • Remove and replace entire structure • Raise right abutment • 40-foot, 3-cycle labyrinth weir • Denil fjsh ladder • Articulated concrete blocks on left embankment • Rising stem sluice gate 15

  18. Alternative 3 - Labyrinth Weir Spillway Alt 1 pdf 16

  19. Labyrinth Weir Spillway 17

  20. Alternative 3 - Labyrinth Weir Spillway Address Deficiencies • Remove and replace entire structure • Raise right abutment • 40-foot, 3-cycle labyrinth weir • Denil fjsh ladder • Articulated concrete blocks on left embankment • Rising stem sluice gate Conclusion of Alternative 3 • Hydraulic capacity - water level during storm • Structural integrity • Fish bypass • Sediment 18

  21. Project Costs Alternative 1 Alternative 2 Alternative 3 Cost Elements Rehabilitate Existing Dam New Ogee Spillway New Labyrinth Weir Dam Construction Costs $324,000 $456,000 $375,000 (without fish passage) Fish Passage Construction $100,000 $50,000 $100,000 Engineering Costs $50,880 $60,720 $57,000 TOTAL $474,880 $566,720 $532,000 19

  22. Questions and Discussion 20

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend