town of norwich
play

TOWN OF NORWICH Norwich Pool Dam and Recreation Area PRESENTATION - PowerPoint PPT Presentation

TOWN OF NORWICH Norwich Pool Dam and Recreation Area PRESENTATION by Shawn Patenaude, P .E. August 20, 2012 1 2 Existing Conditions Impact from Tropical Storm Irene Amount of rainfall Overtopping Erosion of right embankment


  1. TOWN OF NORWICH Norwich Pool Dam and Recreation Area PRESENTATION by Shawn Patenaude, P .E. August 20, 2012 1

  2. 2

  3. Existing Conditions Impact from Tropical Storm Irene • Amount of rainfall • Overtopping • Erosion of right embankment Conclusions from Visual Inspection and Desktop Analysis • Vintage concrete (1949) - Minimal reinforcement and cracks • Antiquated fmashboard design - Nonfunctional 1

  4. Project Approach Address Deficiencies Through Design • Inadequate hydraulic spillway - Overtopping in 1979 and 2011 caused right embankment erosion. • Deteriorated spillway concrete has led to structural instability • Inoperable fmashboard system - Flashboards are braced reducing hydraulic capacity during fmood fmows. • Manual stoplog section is often utilized during inclement conditions. • Unprotected abutments - If the left embankment hadn’t eroded, overtopping would have been widespread and additional damages would have occurred. Conform to Regulatory Requirements • Adequate Hydraulic capacity (1% storm frequency) - 6" of rain in one 24-hour period • Address sediment transport - Operable low-level gates - Sediment management plan • Fish passage element - Constructed natural fjsh bypass - Fish ladder - Flow management 2

  5. Alternative 1 - Rehabilitate Existing Structure Address Deficiencies • New concrete training walls • Raise right abutment • Denil fjsh ladder • Articulated concrete blocks on left embankment • New fmashboard system • Concrete overfmow section • Rising stem sluice gate 3

  6. Alternative 1 - Rehabilitate Existing Structure Alt 1 pdf 4

  7. Denil Fish Ladder Alt 1 pdf 5

  8. Articulated Concrete Blocks 6

  9. Flash Board System Alt 1 pdf 7

  10. Concrete Overfmow Section Alt 1 pdf 8

  11. Alternative 1 - Rehabilitate Existing Structure Address Deficiencies • New concrete training walls • Raise right abutment • Denil fjsh ladder • Articulated concrete blocks on left embankment • New fmashboard system • Concrete overfmow section • Rising stem sluice gate Conclusion of Alternative 1 • Hydraulic capacity - water level during storm • Structural integrity • Fish bypass • Sediment 9

  12. 10 Alternative 2 - Ogee Spillway Design Address Deficiencies • Remove and replace entire dam • Raise right abutment • 50-foot-span ogee spillway • Constructed natural fjsh bypass • Articulated concrete blocks on left embankment • Rising stem sluice gate 10

  13. Alternative 2 - Ogee Spillway Design Alt 1 pdf 11

  14. Ogee Spillway 12

  15. Constructed Natural Fish Bypass 13

  16. 14 Alternative 2 - Ogee Spillway Design Address Deficiencies • Remove and replace entire dam • Raise right abutment • 50-foot-span ogee spillway • Constructed natural fjsh bypass • Articulated concrete blocks on left embankment • Rising stem sluice gate Conclusion of Alternative 2 • Hydraulic capacity - water level during storm • Structural integrity • Fish bypass • Sediment 14

  17. Alternative 3 - Labyrinth Weir Spillway Address Deficiencies • Remove and replace entire structure • Raise right abutment • 40-foot, 3-cycle labyrinth weir • Denil fjsh ladder • Articulated concrete blocks on left embankment • Rising stem sluice gate 15

  18. Alternative 3 - Labyrinth Weir Spillway Alt 1 pdf 16

  19. Labyrinth Weir Spillway 17

  20. Alternative 3 - Labyrinth Weir Spillway Address Deficiencies • Remove and replace entire structure • Raise right abutment • 40-foot, 3-cycle labyrinth weir • Denil fjsh ladder • Articulated concrete blocks on left embankment • Rising stem sluice gate Conclusion of Alternative 3 • Hydraulic capacity - water level during storm • Structural integrity • Fish bypass • Sediment 18

  21. Project Costs Alternative 1 Alternative 2 Alternative 3 Cost Elements Rehabilitate Existing Dam New Ogee Spillway New Labyrinth Weir Dam Construction Costs $324,000 $456,000 $375,000 (without fish passage) Fish Passage Construction $100,000 $50,000 $100,000 Engineering Costs $50,880 $60,720 $57,000 TOTAL $474,880 $566,720 $532,000 19

  22. Questions and Discussion 20

Recommend


More recommend