TOWN OF NORWICH

Norwich Pool Dam and Recreation Area

PRESENTATION by Shawn Patenaude, P .E.

August 20, 2012

slide-2
SLIDE 2

2

slide-3
SLIDE 3

1

Existing Conditions

Impact from Tropical Storm Irene

  • Amount of rainfall
  • Overtopping
  • Erosion of right embankment

Conclusions from Visual Inspection and Desktop Analysis

  • Vintage concrete (1949)
  • Minimal reinforcement and cracks
  • Antiquated fmashboard design
  • Nonfunctional
slide-4
SLIDE 4

2

Project Approach

Address Deficiencies Through Design

  • Inadequate hydraulic spillway
  • Overtopping in 1979 and 2011 caused right embankment erosion.
  • Deteriorated spillway concrete has led to structural instability
  • Inoperable fmashboard system
  • Flashboards are braced reducing hydraulic capacity during fmood fmows.
  • Manual stoplog section is often utilized during inclement conditions.
  • Unprotected abutments
  • If the left embankment hadn’t eroded, overtopping would have been

widespread and additional damages would have occurred.

Conform to Regulatory Requirements

  • Adequate Hydraulic capacity (1% storm frequency)
  • 6" of rain in one 24-hour period
  • Address sediment transport
  • Operable low-level gates
  • Sediment management plan
  • Fish passage element
  • Constructed natural fjsh bypass
  • Fish ladder
  • Flow management
slide-5
SLIDE 5

3

Alternative 1 - Rehabilitate Existing Structure

Address Deficiencies

  • New concrete training walls
  • Raise right abutment
  • Denil fjsh ladder
  • Articulated concrete blocks on left embankment
  • New fmashboard system
  • Concrete overfmow section
  • Rising stem sluice gate
slide-6
SLIDE 6

4

Alt 1 pdf Alternative 1 - Rehabilitate Existing Structure

slide-7
SLIDE 7

5

Alt 1 pdf Denil Fish Ladder

slide-8
SLIDE 8

6

Articulated Concrete Blocks

slide-9
SLIDE 9

7

Alt 1 pdf Flash Board System

slide-10
SLIDE 10

8

Alt 1 pdf Concrete Overfmow Section

slide-11
SLIDE 11

9

Alternative 1 - Rehabilitate Existing Structure

Address Deficiencies

  • New concrete training walls
  • Raise right abutment
  • Denil fjsh ladder
  • Articulated concrete blocks on left embankment
  • New fmashboard system
  • Concrete overfmow section
  • Rising stem sluice gate

Conclusion of Alternative 1

  • Hydraulic capacity - water level during storm
  • Structural integrity
  • Fish bypass
  • Sediment
slide-12
SLIDE 12

10 10

Alternative 2 - Ogee Spillway Design

Address Deficiencies

  • Remove and replace entire dam
  • Raise right abutment
  • 50-foot-span ogee spillway
  • Constructed natural fjsh bypass
  • Articulated concrete blocks on left embankment
  • Rising stem sluice gate
slide-13
SLIDE 13

11

Alt 1 pdf Alternative 2 - Ogee Spillway Design

slide-14
SLIDE 14

12

Ogee Spillway

slide-15
SLIDE 15

13

Constructed Natural Fish Bypass

slide-16
SLIDE 16

14 14

Alternative 2 - Ogee Spillway Design

Address Deficiencies

  • Remove and replace entire dam
  • Raise right abutment
  • 50-foot-span ogee spillway
  • Constructed natural fjsh bypass
  • Articulated concrete blocks on left embankment
  • Rising stem sluice gate

Conclusion of Alternative 2

  • Hydraulic capacity - water level during storm
  • Structural integrity
  • Fish bypass
  • Sediment
slide-17
SLIDE 17

15

Alternative 3 - Labyrinth Weir Spillway

Address Deficiencies

  • Remove and replace entire structure
  • Raise right abutment
  • 40-foot, 3-cycle labyrinth weir
  • Denil fjsh ladder
  • Articulated concrete blocks on left embankment
  • Rising stem sluice gate
slide-18
SLIDE 18

16

Alt 1 pdf Alternative 3 - Labyrinth Weir Spillway

slide-19
SLIDE 19

17

Labyrinth Weir Spillway

slide-20
SLIDE 20

18

Alternative 3 - Labyrinth Weir Spillway

Address Deficiencies

  • Remove and replace entire structure
  • Raise right abutment
  • 40-foot, 3-cycle labyrinth weir
  • Denil fjsh ladder
  • Articulated concrete blocks on left embankment
  • Rising stem sluice gate

Conclusion of Alternative 3

  • Hydraulic capacity - water level during storm
  • Structural integrity
  • Fish bypass
  • Sediment
slide-21
SLIDE 21

19

Project Costs

Cost Elements Alternative 1 Rehabilitate Existing Dam Alternative 2 New Ogee Spillway Alternative 3 New Labyrinth Weir Dam Construction Costs (without fish passage) $324,000 $456,000 $375,000 Fish Passage Construction $100,000 $50,000 $100,000 Engineering Costs $50,880 $60,720 $57,000 TOTAL $474,880 $566,720 $532,000

slide-22
SLIDE 22

20

Questions and Discussion