Obrajes bridge tO Market
Design T
eam:
Thomas BurklanD maria giBBs russell glorioso Thomas haDzor
Duke universiTy PraTT school of engineering DeParTmenT of civil anD environmenTal engineering civil engineering 142 sPring 2009
Construction Scheduling BOLIVIAN BRIDGE DESIGN CE 142 S pring 2009 Q - - PowerPoint PPT Presentation
O brajes b ridge tO M arket D uke u niversiTy P raTT s chool of e ngineering D eParTmenT of c ivil anD e nvironmenTal e ngineering c ivil e ngineering 142 s Pring 2009 D esign T eam : T homas B urklanD m aria g iBBs r ussell g lorioso T homas h
eam:
Thomas BurklanD maria giBBs russell glorioso Thomas haDzor
Duke universiTy PraTT school of engineering DeParTmenT of civil anD environmenTal engineering civil engineering 142 sPring 2009
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
Project Site
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
Floating Bridge
Utilizing the bouyant force of water, this bridge would respond to a fmooded river by simply rising on
potentially recycling oil drums, this bridge would be simple to maintain, if not to cross. Major concerns about durability, safety, and reliability shelved this untested concept.
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
Culvert Bridge
The culvert bridge is a standard rural design. It is durable, easily crossed, and relatively simple to construct. Large round pipes
through, leaving the bridge nearly untouched. Major drawbacks are the uncertainty
availability
appropriate culverts,
the manpower needed to construct such a bridge.
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
Hardened Roadway
The simplest option by far, the hardened roadway is little more than a slab on grade. It is easy to build and maintain and potentially extremely
this solution becomes impassable. In the times of high water that make this bridge project necessary, this
become passable faster than mud could dry, the signifjcant problem of fmooding makes this option less than
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
We utilized a spreadsheet of values, scoring each bridge out
Our results indicated that the culvert design was the best
with a design for a culvert bridge.
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
1 2 3 4 A B C D E F 10 x 20 10 x 20 10 x 20 10 x 20 10 x 20 10 x 20 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 14 x 25 12' - 0" 12' - 0" 12' - 0" 12' - 0" 1 2 3 4 A B C D E F 2' - 9" 1' - 8" 1' - 0" 5' - 0" 5' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 20' - 0" 4' - 0" 4' - 0" 4' - 0" 1 2 3 4 A B C D E F 12' - 0" 1/4" = 1'-0" 1 03 - DECK 1/4" = 1'-0" 2 01 - FOUNDATION 1/4" = 1'-0" 3 02 - BANKSBOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
1 2 3 4
02 - BANKS 0' - 0" 03 - DECK 1' - 6" 01 - FOUNDATION1 2 3 4
02 - BANKS 0' - 0" 03 - DECK 1' - 6" 01 - FOUNDATIONA B C D E F
THIS AREA TO BE FILLED IN WITH SOIL THIS AREA TO BE FILLED IN WITH SOIL 02 - BANKS 0' - 0" 03 - DECK 1' - 6" 01 - FOUNDATIONA B C D E F
THIS AREA TO BE FILLED IN WITH SOIL THIS AREA TO BE FILLED IN WITH SOIL 1/4" = 1'-0" 1 EAST ELEVATION 1/4" = 1'-0" 2 WEST ELEVATION 1/4" = 1'-0" 3 NORTH ELEVATION 1/4" = 1'-0" 4 SOUTH ELEVATIONBOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
A
0' - 3" 2' - 9" 1' - 8" 7' - 0" 1' - 0" 1' - 0" 2 #8 BARS 2 #8 BARS 3" = 1'-0" 1 04 - PRIMARY AND SECONDARY BEAMS 3/4" = 1'-0" 2 05 - RETAINING WALLBOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
courTesy of WooDy kloesel, Pe Optimal water/cement ratio ≤ 0.55 Reinforcing steel: Fy = 40 ksi Concrete: fc’ = 2500 psi (EWB recommended for site-mixed) Allowable soil bearing pressure: 2000 psf Suggested Rho value: ρ= 0.0045
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
0.6C24 Deck 2.5” Deep WWF= 6x6 W2.1 x W2.1 (As=0.042)
10 x 20 with 2-#8 bars Tops each of the four sets of columns and the retaining wall.
14 x 25 with 4-#8 bars Runs with the fmow of traffjc, @ 4’ O.C.
10 x 12 reinforced concrete 4 #8 bars with #3 ties @ 1’-0” O.C.
60 x 60 x 8 5 #4 bars @ 1’-2” O.C. in each direction Major materials used
Concrete: 1846 ft3 Metal Decking: 1200 ft2 WWF: 12 csf #3 bars: 140 ft #4 bars: 400 ft #8 bars: 2259 ft
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
Goals: water/cement ratio ≤ 0.55 concrete fc’ ≥ 2500 psi Concrete Mix: Water: 0.5 lb/ft3 Cement: 25.38 lb/ft3 Coarse Aggregate: 73.89 lb/ft3 Fine Aggregate: 48.9 lb/ft3
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
NOTE: Each design is for one of the objects it specifjes
Footing: 4 - 1” x 8” timbers; two cut at 5’-2”, two cut at 5’-0” Column: 4 - 1” x 12” timbers; cut at 6’-5” Primary Beam: 5 - 1/2” plywood; one cut to 12’-0” x 11”, two cut to 11’-11” x 20”, two cut to 11” x 20” Secondary Beam: 5 - 1/2” plywood; one cut to 12’-0” x 15”, two cut to 1’-3” x 2’-1”, two cut to 19’-11” x 2’-1” Ramp: 4 - 1” x 4” timbers; two cut to 12’-0”, two cut to 12’-2” Retaining Wall Slab: 4 - 1” x 12” timbers; two cut to 5’-5”; two cut to 12’-2” Retaining Wall: 4 - 1/2” plywood; two cut to 6’-5” x 1’-2”, two cut to 6’-5” x 12’-0”
BOLIVIAN BRIDGE DESIGN CE 142 S
PRING 2009
Materials List 1 U.S. dollar = 7.02000702 Bolivian bolivianos Item Amount per Element Units Multiply by 1.25 Convert to m# of 12m bars # of Elements Cost(BOB) Units Cost (USD) Cost Spread Footing 8 concrete 16.7 cf rebar (8 #4 bars)12.7mm 400 ft 500 152.4 13 135.71 per 12 m bar $19.34 Column 8 concrete rebar (6 #3 bars)9.525mm 140 ft 173.6 52.91328 5 85.26 per 12m bar $12.15 Primary Beam 6 concrete rebar (2 #8 bars) 2259 ft 2823.75 860.679 72 604.55 per 12m bar $86.14 Secondary Beam 20 concrete rebar (4 #8 bars)28.65mm 0 ft 604.55 per 12m bar $86.14 Retaining Wall 2 concrete rebar (2 #8 bars) 1 ft 1.25 0.381 1 604.55 per 12m bar $86.14 $172.28 Welded Wire Fabric 12 csf Deck concrete metal decking 1200 sf 1 15.94 sf $2.27 anchor bolts Form Work plywood $1,000 lumber (i.e. 2 x 4) $1,000 nails (clavos) 1000 18/kg(.35/nail) $0.05 $50.00 Total # 8 re-bar 2259 ft 2823.75 860.679 72 604.55 per 12m bar $86.14 $6,202.08 #4 re-bar 400 ft 500 152.4 13 135.71 per 12m bar $19.34 $251.42 # 3 re-bar 140 ft 175 53.34 5 8.26 per 12m bar $12.15 $60.75 Concrete 1846 ft $8,452 Metal Decking 1200 sf 15.94 sf $2.27 $2,724.00 Welded Wire Fabric 12 csf 15.16 csf $2.16 $25.92 Concrete 1846 cf Portland Cement 23.33 lb/cf Coarse Aggregate(Gravel) 73.89 lb/cf Fine Aggregate (Sand) 48.9 lb/cf Water Welded Wire Mesh 347.49/cfs $49.50
Trowels(paleta, badilejo) 5 18 $2.56 $12.80 Shovels(pala) 10 85 $12.11 $121.10 Wheelbarrows 5 600 $85.49 $427.45 Concrete Mixer 2 $1,000 $1,000 Stakes 200 1.75 $0.25 $50.00 Tape Measures 5 28 $4.00 $20.00 Levels (nivel) 5 17 $2.42 $12.10 Spray Paint 20 35 $5 $100 Surveying Equipment *brought from Duke $0 $0 Helmets(cascos) 20 30 $0.27 $5.40 Gloves(guantes de cuero) 20 20 $2.85 $57.00 Breathing Masks 10 10 $1.42 $14.20 Safety Glasses(gafas) 10 15 $2.14 $21.40 Wood Saws 10 40 $5.70 $57.00 Hammars (martillo) 10 45 $6.41 $64.10 Total Cost $21,728.72 English Spanish rebar Acero Corrugado
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009
BOLIVIAN BRIDGE DESIGN CE 142 Spring 2009