Measurement for land slide slope stability using High Capacity - - PDF document

measurement for land slide slope stability using high
SMART_READER_LITE
LIVE PREVIEW

Measurement for land slide slope stability using High Capacity - - PDF document

Measurement for land slide slope stability using High Capacity Micropiles Masao SAGARA Masao SAGARA (Fujita Corporation) (Fujita Corporation) Prof. Masaru HOSHIYA Prof. Masaru HOSHIYA (Musashi Institute of Technology) (Musashi Institute of


slide-1
SLIDE 1

Measurement for land slide slope stability using High Capacity Micropiles

Masao SAGARA Masao SAGARA

(Fujita Corporation) (Fujita Corporation)

  • Prof. Masaru HOSHIYA
  • Prof. Masaru HOSHIYA

(Musashi Institute of Technology) (Musashi Institute of Technology)

Good evening! (Good, afternoon!) My name is MASAO SAGARA. We applied HMP on the slope in exit of the tunnel. We executed the field measurement. I will present result of it. I introduce the result of field measurement.

slide-2
SLIDE 2

We applied HMP on the slope in the exit of the tunnel. We executed the field measurement.

HMP in the Retaining Wall

Good evening! (Good, afternoon!) My name is MASAO SAGARA. We applied HMP on the slope in exit of the tunnel. We executed the field measurement. I will present result of it. I introduce the result of field measurement.

slide-3
SLIDE 3

Contents Contents 1.Background & Outline of the 1.Background & Outline of the Construction Construction 2.Purpose of Field measurement 2.Purpose of Field measurement 3.Field measurement result of 3.Field measurement result of High Capacity Micropiles High Capacity Micropiles 4.Conclusion 4.Conclusion

I would like to speak four contents. 1.Background & Outline of the Construction 2.Purpose of Field measurement 3.Field measurement result of High Capacity Micropiles 4.Conclusion

slide-4
SLIDE 4

Background(Site location) Background(Site location)

TOKYO

This is the site location from Google Earth. It is a site of the tunnel construction. The name is called BESHO tunnel.

This is the site location from Google Earth. It is a site of the tunnel construction. The name is called BESHO tunnel.

slide-5
SLIDE 5

BESHO Tunnel

L=948m

NEW Expressway L=100km ISE Bay

TOUMEI Expressway TOKAI Belt Line CHUOH Expressway MEISHIN Expressway

SURUGA Bay NAGOYA City

Background(Site location) Background(Site location)

TOKYO

In Japan, there are two expressways where Tokyo is connected with Nagoya. Tokyo is located besides the right of the screen. One is a CHUOH expressway, and another is a TOUMEI expressway. These two expressways are connecting by the new

  • expressway. It is constructing, now.

One of tunnels on this expressways is BESHO tunnel. The length is 948m. Here, HMP was constructed.

In Japan, there are two expressways where Tokyo is connected with Nagoya. Tokyo is located besides the right of the screen. One is a CHUOH expressway, and another is a TOUMEI expressway. These two expressways are connecting by the new expressway. It is constructing, now. One of tunnels on this expressways is BESHO tunnel. The length is 948m. Here, HMP was constructed.

slide-6
SLIDE 6

E x i t The Forestry Road Private House Serpentinite Crystalline schist Epidote - Amphibolite Shallow overburden(18m) Subsurface layers

Outline of the Construction Outline of the Construction

Exit of tunnel terminal side Exit of tunnel terminal side ( (longitudinal longitudinal vertical section) vertical section)

Crystalline schist

Tunnel

There is a private house and the forestry road up soon about the tunnel. If the tunnel is dug without the reinforcement construction method, the house will be leaning to one side. And, the slope will be failure, too.

This figure is a longitudinal vertical section of the tunnel. There is a private house and the forestry road up soon about the tunnel. If the tunnel is dug without the reinforcement construction method, the house will be leaning to one side. And, the slope will be failure, too.

slide-7
SLIDE 7

All Ground Fasten Method (AGF)

For Tunnelling For Slope Stability

The three countermeasures were applied for the slope stability.

  • Extension of entrance of

tunnel(8m)

  • Rock Bolt
  • High Capacity Micropile

with Ground Anchor

Countermeasure Against Landslide Countermeasure Against Landslide and Tunneling and Tunneling

However, the exit of the tunnel has been extended. As a result, the amount of cut has been reduced. In the first plan, the exit of the tunnel was here. And, it was scheduled to be cut.

All Ground Fasten Method was applied to the tunneling. Like this, a small slope failure and a large- scale slope failure were forecast. The lock bolt was constructed to a small slope failure. HMP with the ground anchor were constructed to a large- scale slope failure.

This figure shows countermeasure against landslide and tunneling. All Ground Fasten Method was applied to the tunneling. And, three countermeasures were applied for the slope stability. In the first plan, the exit of the tunnel was here. And, it was scheduled to be cut. However, the exit of the tunnel has been extended. As a result, the cut amount has been reduced. Like this, a small slope failure and a large-scale slope failure were forecast. The lock bolt was constructed to a small slope failure. HMP with the ground anchor were constructed to a large-scale slope failure.

slide-8
SLIDE 8

C Construction

  • nstruction position

position in ground plan

Private House

林道

Construction position of High Capacity Micropiles

The Forestry Road

Tunneling

  • HMP was constructed

near the tunnel.

  • 11 piles
  • L=13.0-17.5m@1.5m
  • Total Length 149m

This figure shows the construction position of HMP. HMP was constructed near the tunnel. 11 piles were constructed. The length is from 13 to 17m. The total length is 149m.

slide-9
SLIDE 9

Construction position Construction position

Panorama of Site

HMP Construction Position

slide-10
SLIDE 10

Drilling situation Drilling situation

slide-11
SLIDE 11

Drilling completion Drilling completion

slide-12
SLIDE 12

Connection of Pile head Connection of Pile head

slide-13
SLIDE 13

HMP seen from mountain side HMP seen from mountain side

slide-14
SLIDE 14

The process for Retaining Wall

High capacity Micro-Piles

Φ178@11pieces L=13.0~17.5m@1.5m

Cradle

Retaining Wall strip(H150 beam)

slide-15
SLIDE 15

The process for Retaining Wall The process for Retaining Wall

(Placing of reinforcement) (Placing of reinforcement)

slide-16
SLIDE 16

The process for Retaining Wall The process for Retaining Wall

(Concrete placement)

slide-17
SLIDE 17

Purpose of field measurement Purpose of field measurement

We aim to confirm the effect of HMP

control works on the slope.

The strain gauges ware put on HMP,

and the bending moment was measured

  • n the site.
slide-18
SLIDE 18

Measurement Piles Measurement Piles

  • The vinyl chloride pipe with

The vinyl chloride pipe with the strain gauges was set the strain gauges was set up in the steel pipe. up in the steel pipe.

  • The strain gauges of

The strain gauges of installation sections ware installation sections ware six places. six places. The vinyl chloride pipe

8 7 6 5 4 3 2 1 7 6 5 4 3 2 1 12000 Steel Casing

2000

1000 Bearing Stratum Soft Stratum 13000 Total HMP length Drill bit Steel Casing Pipe Steel Casing Joint Deformed Bar 1000

1000

9000 Cased Upper HMP Length 2000 1000 1000 ⑥ 1000 ⑤ 1000 ④ 1000 ③

500

② 8000 Vinyl Chloride Pipe 5600 ①

Slip surface

Strain Gauge H beam

500

Baseine

Pressure Grouted HMP Bond Length Non-steel Casing

This is an outline of the measurement piles. In this case, the vinyl chloride pipe with the strain gauges was set up in the steel pipe. The strain gauges of installation sections are six places. 計測杭の概念図です。 高耐力マイクロパイルの場合、鋼管を削孔ケーシングとして用いますので、鋼管へ ひずみゲージを貼付することは不可能です。 そこで、塩ビ管にひずみゲージを貼付し、鋼管内に設置して計測しました。 ひずみゲージは、想定すべり面(5.6m)および最大曲げモーメントが発生すると予 想される深度(2~3m)を考慮して6箇所に設置しました。

slide-19
SLIDE 19

Measurement position Measurement position in section in section

High Capacity Micropiles L=13.0-17.5m@1.5m

H beam Measurement Piles Measurement Piles

予備のスライドです。 使用しません。 非表示に設定しています。 計測杭の設置位置の断面図です。

slide-20
SLIDE 20

Measurement position Measurement position in ground plan

House of Inhabitant

林道 Construction position of High Capacity Micropiles

The Forestry Ro

Measurement Piles No.6 No.9

Tunneling

The field measurement was done by two places. They are the No.6 and No.9. In the following, the result of No.9 is introduced.

This figure shows the position of the measurement piles. The field measurement was done by two places. They are the No.6 and No.9. In the following, the result of No.9 is introduced.

slide-21
SLIDE 21

Bending Moment & Date (No.9)

  • 50
  • 40
  • 30
  • 20
  • 10

10 20 30 40 50 2/20 2/27 3/6 3/13 3/20 3/27 4/3 4/10 4/17 4/24 5/1 5/8 5/15 5/22 5/29 6/5 6/12 Date

Bending Moment(kN・m)

9-① 9-② 9-③ 9-④ 9-⑤ 9-⑥

Date & Bending Moment Date & Bending Moment

Valley side Mountain side

It was March 21 that the tunnel penetrated. The bending moment has increased in those days. The bending moment changed on March 27. After that, it indicates a constant value.

This figure shows the distribution of the date and the bending moment. It was March 21 that the tunnel penetrated. The bending moment has increased in those days. The bending moment changed on March 27. After that, it indicates a constant value.

slide-22
SLIDE 22
  • When we had the

When we had the tunneling, the tunneling, the bending moment bending moment was an increasing was an increasing tendency. tendency.

  • After the tunnel had

After the tunnel had penetrated (3/21), penetrated (3/21), the bending moment the bending moment indicated a value indicated a value about half of the about half of the design. design.

No.9 Bending Moment Diagram 2 4 6 8 10 12

  • 80
  • 60
  • 40
  • 20

20 40 60 80 Bending Moment (kN・m) Depth(m)

2/21 3/20 3/27 4/6 4/26 5/6 Design Value Slip Surface

Bending Moment Diagram Bending Moment Diagram

Valley side Mountain side

This figure shows depth and the bending moment. When we had the tunneling, the bending moment was an increasing tendency. After the tunnel had penetrated (3/21), the bending moment indicated a value about half of the design.

slide-23
SLIDE 23

No.9 Axis force Diagram

2 4 6 8 10 12

  • 800 -600 -400 -200

200 400 600 800 Axis force(kN) Depth(m) 2/21 3/20 3/27 4/6 4/26 5/6 Slip Surface

Axis Force Diagram Axis Force Diagram

  • The change in the axial

The change in the axial force is seen in the force is seen in the sliding surface. sliding surface.

  • It might be an influence

It might be an influence

  • f the tunneling.
  • f the tunneling.
  • However, clear

However, clear consideration is not consideration is not

  • btained. We will
  • btained. We will

examine it in the future. examine it in the future.

Tension Compression

This figure shows depth and the axial force. The change in the axial force is seen in the sliding surface. It might be an influence of the tunneling. However, clear consideration is not obtained. We will examine it in the future.

slide-24
SLIDE 24

Conclusion Conclusion

  • The bending moment has increased

The bending moment has increased while digging the tunnel. while digging the tunnel.

  • After the tunnel had penetrated, the

After the tunnel had penetrated, the bending moment indicated half the bending moment indicated half the value of the design. value of the design.

  • It is thought that High Capacity

It is thought that High Capacity Micropiles Micropiles are working as the control are working as the control piles. piles.

The bending moment has increased while digging the tunnel. After the tunnel had penetrated, the bending moment indicated half the value of the design. It is thought that HMP functions as a control works. トンネルを掘削中の時は、曲げモーメントが増加した。 トンネル貫通後は、曲げモーメントは設計値の半分の値を示した。 HMPは抑止杭として機能していると考えられる。

slide-25
SLIDE 25

THE END THE END

Thank you for your attention!! Thank you for your attention!!

Thank you. Thank you for your attention!!