Talbert P-Well Vault and Pipeline Decommissioning Contract TAL-2020-2 Pre-bid Meeting March 17, 2020 Bid Info & Schedule Activity Date Bid Advertisement March 5 Non-Mandatory Pre-Bid Meeting March 17 Bid Opening March 31, 2 p.m.


slide-1
SLIDE 1

Talbert P-Well Vault and Pipeline Decommissioning

Contract TAL-2020-2

Pre-bid Meeting March 17, 2020

slide-2
SLIDE 2

Bid Info & Schedule

Activity Date

Bid Advertisement March 5 Non-Mandatory Pre-Bid Meeting March 17 Bid Opening March 31, 2 p.m. OCWD Committee April 8 OCWD Board April 15 Notice to Proceed ~May 1

Class A Contractor’s License Contract documents available at www.ocwdplanroom.com Questions directed to Ben Smith in writing, bsmith@ocwd.com, 10+ days prior to bid

slide-3
SLIDE 3

Bid Info

  • DIR Registration & Labor Compliance
  • Prevailing Wage
  • EMR / X-Mod
  • Safety Worksheets in “P” pages
slide-4
SLIDE 4

Project

  • Wells abandoned by others
  • 7 Vault Removal/Abandonments

– 2 in Street – 4 in Sidewalk – 1 in Flood Channel Road – Ignore OCWD-P10 Site

  • Filling of 24-inch pipeline with sand-cement

–Contractor select locations and prepare traffic control plans –Remove air-vacs and valve

  • Cutting & capping pipelines

–Some asbestos cement

  • Sidewalk, curb, tree, asphalt restoration
slide-5
SLIDE 5

Project Permits

Agency Type of Document Status

CEQA Final Initial Study / Mitigated Negative Declaration Complete City of Huntington Beach Encroachment Permit with Traffic Control Preliminary approved

  • btained. To be obtained by

Contractor County of Orange Encroachment Permit (FE20- 0029) for OCWD-P6 Site In project, To be obtained by CONTRACTOR South Coast Air Quality Management District Asbestos Pipe Work To be obtained by Contractor

OCWD will pay permit fees directly to Agencies. Contractor to provide application, traffic control, and supporting documents.