Lisbon Channel Access Project Non-Mandatory Pre-Bid
1
Please Sign In 1 Lisbon Channel Access Project Non-Mandatory - - PowerPoint PPT Presentation
Lisbon Channel Access Project Non-Mandatory Pre-Bid Please Sign In 1 Lisbon Channel Access Project Non-Mandatory Pre-Bid Conference February 21, 2018 NMDOT CN A301870 2 Lisbon Channel Access Project Introductions: SSCAFCA Staff
1
Non-Mandatory Pre-Bid Conference February 21, 2018 NMDOT CN A301870
2
– SSCAFCA Staff
– Wilson and Company
– NMDOT
3
– SSCAFCA Bond Funds – FHWA Federal Funds
– Buy America certifications – Use of LCPTracker and B2GNOW software platforms – And more….
4
5
6
– The bid includes:
base course access path (with asphalt additive alt)
width is available for the access path
the access
drainage
7
– The successful bidder shall develop and implement the plan. – The successful bidder will need to file a Notice of Intent (NOI) for the project with EPA. SSCAFCA will also file an NOI as the Owner. – No work on the project shall commence until the mandatory waiting period after filing the NOI is complete – Successful bidder must file Notice of Termination (NOT) with EPA once project is complete and site is stabilized.
8
9
– Last day to submit written questions is February 27 by 5:00 PM
question
Question”
– SSCAFCA will post responses to written questions on web page (http://sscafca.org) by March 5, 5:00 PM – Any Addenda will be issued by SSCAFCA by March 5, 5:00 PM. Addenda will be posted to the website. Aside from posting on website, no notification will occur. – Bids are due to SSCAFCA by 3:00 PM on March 8. Public bid
– SSCAFCA, in consultation with NMDOT hopes to determine the lowest responsive bidder by March 13. – SSCAFCA hopes to request SSCAFCA Board of Directors approval to contract with lowest responsive bidder on March 16. – SSCAFCA will continue to work with NMDOT and the lowest responsive bidder to finalize contract.
10
– Mandatory bid attachments
Nondiscrimination
– Make sure prime AND all subcontractors (not suppliers) are currently registered with the Department of Workforce Solutions – Make sure to acknowledge any Addenda on your Bid Form – Make sure you are prequalified with NMDOT seven days before the bid date!
11