Lisbon Channel Access Project Non-Mandatory Pre-Bid

1

Please Sign In

slide-2
SLIDE 2

Lisbon Channel Access Project

Non-Mandatory Pre-Bid Conference February 21, 2018 NMDOT CN A301870

2

slide-3
SLIDE 3

Lisbon Channel Access Project

  • Introductions:

– SSCAFCA Staff

  • Charles Thomas, P.E., Executive Engineer
  • Jim Service, Field Services Director
  • Andres Sanchez, P.E., Drainage Engineer
  • Dave Gatterman, P.E., Project Manager
  • Debbie Casaus, Procurement Manager

– Wilson and Company

  • Tyler Ashton, P.E. (design engineer)
  • Chris Perea, P.E.

– NMDOT

  • Luke Smith, P.E.
  • Mary Lovato, P.E.

3

slide-4
SLIDE 4

Lisbon Channel Access Project

  • Funding

– SSCAFCA Bond Funds – FHWA Federal Funds

  • Federal Funds mandate federal requirements

– Buy America certifications – Use of LCPTracker and B2GNOW software platforms – And more….

4

slide-5
SLIDE 5

Lisbon Channel Access Project

  • Where exactly is the project?

5

slide-6
SLIDE 6

Lisbon Channel Access Project

  • Current site conditions

6

slide-7
SLIDE 7

Lisbon Channel Access Project

  • Bid Highlights

– The bid includes:

  • Grubbing and installation of approximately 4,500 LF of

base course access path (with asphalt additive alt)

  • Installation of retaining wall in areas where side-slopes
  • f arroyo are close to property lines and insufficient

width is available for the access path

  • Installation of metal railing along majority of length of

the access

  • Three culvert crossings to accommodate off site

drainage

7

slide-8
SLIDE 8

Lisbon Channel Access Project

  • Stormwater Pollution Prevention Plan (SWPPP)

– The successful bidder shall develop and implement the plan. – The successful bidder will need to file a Notice of Intent (NOI) for the project with EPA. SSCAFCA will also file an NOI as the Owner. – No work on the project shall commence until the mandatory waiting period after filing the NOI is complete – Successful bidder must file Notice of Termination (NOT) with EPA once project is complete and site is stabilized.

8

slide-9
SLIDE 9

Lisbon Channel Access Project

9

  • Bid Schedule

– Last day to submit written questions is February 27 by 5:00 PM

  • Submit all questions via e-mail to dcasaus@sscafca.com
  • Ms. Casaus will email you back letting you know we received the

question

  • Remember to change subject line to “Lisbon Channel Access Project

Question”

– SSCAFCA will post responses to written questions on web page (http://sscafca.org) by March 5, 5:00 PM – Any Addenda will be issued by SSCAFCA by March 5, 5:00 PM. Addenda will be posted to the website. Aside from posting on website, no notification will occur. – Bids are due to SSCAFCA by 3:00 PM on March 8. Public bid

  • pening shortly after 3:00 PM.
slide-10
SLIDE 10

Lisbon Channel Access Project

  • Project Schedule (post bid):

– SSCAFCA, in consultation with NMDOT hopes to determine the lowest responsive bidder by March 13. – SSCAFCA hopes to request SSCAFCA Board of Directors approval to contract with lowest responsive bidder on March 16. – SSCAFCA will continue to work with NMDOT and the lowest responsive bidder to finalize contract.

10

slide-11
SLIDE 11

Lisbon Channel Access Project

  • Remember:

– Mandatory bid attachments

  • Bid Form
  • Bid Security with Agent’s Affidavit
  • List of proposed subcontractors
  • Certification of Bidder Regarding Affirmative Action/Equal Employment Opportunity and

Nondiscrimination

  • Non-Debarment Certification
  • New Mexico Pay Equity Reporting Acknowledgment
  • SSCAFCA Campaign Contribution Disclosure Form
  • Non-Collusion affidavit
  • Federal Disclosure of Lobbying Activities
  • NOTE: There is no DBE goal with this project

– Make sure prime AND all subcontractors (not suppliers) are currently registered with the Department of Workforce Solutions – Make sure to acknowledge any Addenda on your Bid Form – Make sure you are prequalified with NMDOT seven days before the bid date!

  • Subs too!

11

slide-12
SLIDE 12

Lisbon Channel Access Project

  • Questions?