“The road is going to be closed for how long?” How to reduce the impact of road closures during an emergency culvert repair
Marc Horstman, PE, PH, CFM, Project Manager –WK Dickson Wayne Miles, PE, Stormwater Program Manager –City of Raleigh
The road is going to be closed for how long? How to reduce the - - PowerPoint PPT Presentation
The road is going to be closed for how long? How to reduce the impact of road closures during an emergency culvert repair Marc Horstman, PE, PH, CFM, Project Manager WK Dickson Wayne Miles, PE, Stormwater Program Manager City of
“The road is going to be closed for how long?” How to reduce the impact of road closures during an emergency culvert repair
Marc Horstman, PE, PH, CFM, Project Manager –WK Dickson Wayne Miles, PE, Stormwater Program Manager –City of Raleigh
The Problem
Key Success Factors
Emergency Procurement Process
Stakeholder Communication
Internal “Team” Communication
Emergency Procurement Procedures
Cameron Village Broughton High School Local Residents
State Farmers Market Maywood Businesses
Clark Avenue Emergency Culvert Repair
RO AD O PENS
AUG UST O C T O BER SEPT EMBER NO VEMBER
2 ND FIEL D MT G . 70% PL ANS C O MPL ET E H&H MO DEL ING AND FINAL REPO RT MT G . WIT H C IT Y AND C O NT RAC T O R 1 ST FIEL D MT G . 100% PL ANS C O MPL ET E, C O NST RUC T IO N BEG INS 3 WEEKS 6½ WEEKS 4 WEEKS
Lake Wheeler Emergency Culvert Repair
RO AD O PENS
DEC EMBER FEBRUARY JANUARY MAY
70% PL ANS C O MPL ET E H&H MO DEL ING AND FINAL REPO RT MT G . WIT H C IT Y AND C O NT RAC T O R 1 ST FIEL D MT G . 100% PL ANS C O MPL ET E, C O NST RUC T IO N BEG INS 3 WEEKS 3 MO NT HS
Marc Horstman, PE, PH, CFM WK Dickson mhorstman@wkdickson.com 919.256.5642 Wayne Miles, PE City of Raleigh wayne.miles@raleighnc.gov 919.996.3964