Results of Light Rail Review City Council Presentation Tuesday, - - PowerPoint PPT Presentation

results of light rail review
SMART_READER_LITE
LIVE PREVIEW

Results of Light Rail Review City Council Presentation Tuesday, - - PowerPoint PPT Presentation

Results of Light Rail Review City Council Presentation Tuesday, September 13, 2016 Lyndon S. Remias, City Auditor Chris Ford, Deputy City Auditor Virginia Beach Transit Extension Project Background Project expenditures to date related to


slide-1
SLIDE 1

City Council Presentation Tuesday, September 13, 2016 Lyndon S. Remias, City Auditor Chris Ford, Deputy City Auditor

Results of Light Rail Review

slide-2
SLIDE 2

Virginia Beach Transit Extension Project

Background

  • Project expenditures to date related to the

following three phases:

1. Acquisition of former Norfolk Southern Right-of-Way 2. PPEA unsolicited proposal process – Terminated in May 2014 3. Light rail project feasibility analysis for delivering transit extension as City and State capital project from May 2014 – present Note: Audit captures expenditures through June 30, 2016

2

slide-3
SLIDE 3

Virginia Beach Transit Extension Project

Background (continued)

  • Public Private Education Facility and Infrastructure Act (PPEA) of 2002 -

legislative framework that encourages the private sector to propose alternative project delivery methods for qualifying projects that may deliver the project in a more timely or cost-effective manner.

  • On April 2, 2013, the City received an unsolicited PPEA proposal from a

corporate group to extend the Tide Light Rail into Virginia Beach. In June of 2013, the City Council, by resolution, directed the City Manager to accept the unsolicited proposal.

  • Under the Act, proposals may be invited through solicitation or they may be

considered when delivered by a private entity on an unsolicited basis. The City received one other light rail proposal and one maglev proposal.

  • PPEA process terminated by the City in May 2014 in part due to the

Commonwealth of Virginia recommending a more competitive procurement process for its $155M project funding.

3

slide-4
SLIDE 4

Objective #1 Identify the various CIP projects and general fund budget units where Light Rail related expenditures have been recorded since the commencement of the project through June 30, 2016 and where future light rail expenditures will be recorded should the decision be made to continue with the construction phase of the project.

Virginia Beach Transit Extension Project

4

slide-5
SLIDE 5

Virginia Beach Transit Extension Project

Results

The following are where expenditures are being captured:

  • 1. Purchase of the Norfolk Southern railroad line from

Newtown Road to Birdneck Road in Virginia Beach in September of 2009:

  • CIP Project #2301 - provides for acquisition of the former

Norfolk Southern Right-of-Way

  • CIP Project #2186 - provides for the physical survey of the

Norfolk Southern Right-of-Way acquisition

  • 2. Transit Corridor Feasibility Analysis:
  • CIP Project #9011 - provides for a light rail project feasibility

analysis for delivering The Tide extension as a City and State capital project in Virginia Beach

5

slide-6
SLIDE 6

Virginia Beach Transit Extension Project

  • 3. Consultant Costs to Review and Analyze the three (3) PPEA Proposals

received to extend Light Rail.

– City Council adopted two ordinances; the first on November 12, 2013, the second on April 8, 2014 as a continuation to retain three (3) consultants, one each for engineering, legal, and financial assistance in reviewing the three (3) PPEA proposals received to extend light rail.

The following General Fund accounts for the consultant costs:

  • 002.10510.603109 - Provides for the engineering consultant, Kimley-Horn

and Associates, to assist in the review of the three (3) PPEA proposals.

  • 002.03010.603102 - Provides for the legal consultant, Nossaman LLP, to

assist in the review of the three (3) PPEA proposals.

  • 002.04030.603120 - Provides for the financial consultant, Public

Resources Advisory Group (PRAG), to assist in the review of the three (3) PPEA proposals.

6

slide-7
SLIDE 7

Virginia Beach Transit Extension Project

4. Main Light Rail Project and the two (2) related projects providing for the design/build and completion of the project should it be approved:

  • CIP Project #2092 - This is the main CIP project, which will provide

for the costs of the design/build project to extend light rail from its terminus at Newtown Station/Norfolk – Virginia Beach City line, east to the Town Center/Constitution Drive area.

  • CIP Project #2093 - A companion project to 2092, this project funds

12 transit buses to support enhanced public transportation throughout the City in addition to feeding the Tide light rail system.

  • CIP Project #2108 - This project will fund the design, construction,

right-of-way acquisition (if needed) and site furnishings required to create a shared-use pathway within/along the former Norfolk Southern right-of-way in conjunction with the light rail extension project to provide additional modes of transportation.

7

slide-8
SLIDE 8

Virginia Beach Transit Extension Project

Objective #2 Identify the amounts and purpose of the light rail expenditures paid through June 30, 2016 by tracing expenditures to supporting documentation ex. Invoices, purchase orders, work orders, closing statements, and contracts.

8

slide-9
SLIDE 9

Virginia Beach Transit Extension Project

Results The following charts identify the amounts and purpose of the light rail expenditures paid through June 30, 2016.

  • We were able to trace expenditures to

supporting documentation (i.e. invoices, purchase orders, work orders, closing statements, and contracts).

9

slide-10
SLIDE 10

10

$15,462,564 $201,536 $463,837 $88,115 $115,927 $0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000 $16,000,000

Land Acquisition Feasibility Analysis PPEA Prosposal Consultants Analysis Light Rail Office Expenses Preliminary A & E

Allocation of Local Light Rail Expenditures Grand Total $16,331,979

slide-11
SLIDE 11

11

$417,393 $15,045,171 $0 $2,000,000 $4,000,000 $6,000,000 $8,000,000 $10,000,000 $12,000,000 $14,000,000 $16,000,000 Norfolk Southern Land Survey NFK Southern Land Acquisition

Land Acquisition Expenditures $15,462,564

slide-12
SLIDE 12

12

$98,940 $12,795 $40,000 $49,295 $507 $0 $10,000 $20,000 $30,000 $40,000 $50,000 $60,000 $70,000 $80,000 $90,000 $100,000

Pembroke Station Extension Study Virginia Transportation Infrastructure Bank Application Standard Poors Indicative Bond Rating/Consultation US Dept Transportation Smart Cities Challenge Submission Other

Feasibility Analysis Expenditures $201,537

slide-13
SLIDE 13

13

$406,301 $50,608 $6,175 $753 $0 $50,000 $100,000 $150,000 $200,000 $250,000 $300,000 $350,000 $400,000 $450,000

Public Works Consultant Fees City Attorney Consultant Fees Finance Consulting Fees PPEA Solicitation

PPEA Proposal Evaluation Expenditures $463,837

slide-14
SLIDE 14

14

$8,576 $31,956 $47,583 $0 $10,000 $20,000 $30,000 $40,000 $50,000

Light Rail Office Lease (4801 Columbus) Furniture & Fixtures for Office Technology Costs for Light Rail Office

Light Rail Office Expenditures $88,115

slide-15
SLIDE 15

15

$51,177 $14,633 $1,649 $48,468 $0 $10,000 $20,000 $30,000 $40,000 $50,000 $60,000

Architectural and Engineering Legal Expenses Other (Letter of Interest and Misc) General Engineering and Consulting

Preliminary A&E Expenditures $115,927

slide-16
SLIDE 16

Virginia Beach Transit Extension Project

Objective #3

Identify/develop a reporting mechanism whereby City Council, City Management, and interested outside parties can be informed on the financial progress of Light Rail project should the decision be made to pursue construction.

Results

  • Department of Finance has developed, through the

report writing tool Discoverer, a report titled “Light Rail Expenditures” that queries and reports all light rail expenditures by CIP project and expenditure type.

  • Besides some minor items all expenditures were properly

captured by Finance.

16

slide-17
SLIDE 17

Virginia Beach Transit Extension Project

Conclusion

Based upon the results of our procedures we determined:

  • Expenditures are being fully captured.
  • Supporting documentation exist to support

expenditures.

– invoices, purchase orders, work orders, closing statements, and contracts

  • Finance has effective reporting tools in place to readily

capture and report expenditures to provide accountability and transparency to the project.

17

slide-18
SLIDE 18

Questions?

For further information please contact: Lyndon S. Remias, City Auditor Office of the City Auditor 757-385-5870 lremias@vbgov.com Visit our website at www.vbgov.com/cityauditor

18