Rail Update LEP SIB May 2017 Val Male Principal Rail Officer Rail - - PowerPoint PPT Presentation

rail update
SMART_READER_LITE
LIVE PREVIEW

Rail Update LEP SIB May 2017 Val Male Principal Rail Officer Rail - - PowerPoint PPT Presentation

Rail Update LEP SIB May 2017 Val Male Principal Rail Officer Rail Strategy & Liaison, HCC Whats Happening in Rail? Growth in Service Investment and Improvements Demand Infrastructure Station Usage Watford Junction is


slide-1
SLIDE 1

Rail Update

LEP SIB May 2017 Val Male Principal Rail Officer – Rail Strategy & Liaison, HCC

slide-2
SLIDE 2

What’s Happening in Rail?

Growth in Demand Investment and Infrastructure Service Improvements

slide-3
SLIDE 3

Station Usage

slide-4
SLIDE 4

Watford Junction is Hertfordshire’s busiest station with over 8 million passengers (1)

(1) 8,189,586 entries and exits (2015/16)= 22,437 per day [Source: Office of Rail and Road]

24 stations have over 1 million passengers

slide-5
SLIDE 5

Passenger Growth

5000 10000 15000 20000 25000 06/07 07/08 08/09 09/10 10/11 11/12 12/13 13/14 14/15 15/16 +28% in last 5 years

Passengers at Hertfordshire’s four busiest stations

‘000s

slide-6
SLIDE 6

Public Transport Journeys

62 34 38 66 10 20 30 40 50 60 70 GB Herts Bus Rail Train Bus Train Bus

slide-7
SLIDE 7

Challenges

  • Capacity on trains – Overcrowding on

commuter routes

  • Capacity on the rail network
  • Capacity at Stations – Overcrowding causing

safety concerns

  • Capacity on the road network around stations
slide-8
SLIDE 8

Investment

slide-9
SLIDE 9

2020 2018 2018 2016 - 2018 2018 - 2019

New Trains

slide-10
SLIDE 10

Franchise Commitments

  • Improvements to St Albans, Broxbourne and

Cheshunt Stations

  • Station Travel Plans – GTR and Greater Anglia

leading to small scale improvements e.g. RTPI bus information and increased cycle storage

slide-11
SLIDE 11

Major Schemes

2018 2020 2022 2024 2026 2028 2030 2032 2034 2036 Thameslink Crossrail MLX HS2 Phase 1 Crossrail 2 HS2 Phase 2 EWR

slide-12
SLIDE 12

Service Improvements

Increasing Capacity

slide-13
SLIDE 13

New Thameslink Timetable

slide-14
SLIDE 14

St Albans

London Bridge Brighton

St Pancras Blackfriars Farringdon 15 trains per hour

2018

24 trains per hour Stevenage

slide-15
SLIDE 15

Thameslink / Crossrail Connections

Crossrail Thameslink Farringdon Heathrow 31 mins Canary Wharf 8 mins St Albans 26 mins Stevenage 32 mins

Journey times from Farringdon

slide-16
SLIDE 16

Crossrail 2

  • 20 - 22 tph Broxbourne – Central London

(o/w 10 -12 Crossrail 2)

  • Faster journeys / greater reliability for existing

services

  • Station improvements
  • Better access to stations
  • Level crossing closures
  • Land take for new sidings
  • Assumption of increased housing development
slide-17
SLIDE 17

Crossrail 2 – Current Status

  • Working group
  • Consultation – ? 2017
  • Hybrid Bill – 2019 – 2021
  • Construction starts – 2023
slide-18
SLIDE 18

Connections to WAML services – Bishop’s Stortford / Hertford East Connection to ECML services – WGC / Stevenage Connection to Hertford Loop

slide-19
SLIDE 19

HS2 – Impact on West Coast Main Line

  • Phase 1 opens 2026
  • Opportunity to improve local services
  • Opportunity to increase InterCity services at

Watford Junction

  • Potential competing aspirations from other

authorities

slide-20
SLIDE 20

East West Rail

Bishop’s Stortford Oxford Milton Keynes Bedford St Albans Watford Stevenage Sandy Cambridge 17 mins 16 mins 7 mins Alignment Stopping pattern

slide-21
SLIDE 21

Opportunities to Influence

slide-22
SLIDE 22

Franchise Timetable

2017 2018 2019 2020 2021 West Midlands S East Midlands I S InterCity West Coast S Thameslink S Chilterns S InterCity East Coast East Anglia

Mar 2023 Oct 2025

slide-23
SLIDE 23

Forthcoming Consultations

  • East Midlands Franchise
  • East Coast Route Study
  • Crossrail 2
  • GTR 2018 Timetable Phase 2
slide-24
SLIDE 24

Rail Groups

Local Authority Rail Groups WCR250 ECMA EWR Consortium Stansted Transport Forum Rail Group Rail User Groups Railfutures Local rail groups Hertfordshire Groups HIPP Local Transport Body Rail Industry TOC stakeholder forums Network Rail forums Community Rail Abbey Line CRP Steering Group

slide-25
SLIDE 25

Questions?