project schedule
play

Project Schedule Design Schedule: Field Field Office Construction - PowerPoint PPT Presentation

Project Schedule Design Schedule: Field Field Office Construction Concept of Advertise Inspection Review (Final Complete Operations Review Engineering) July 2014 July 1, 2015 August/ (Preliminary April/May 2014


  1. Project Schedule Design Schedule: Field Field Office Construction Concept of Advertise Inspection Review (Final Complete Operations Review Engineering) • July 2014 • July 1, 2015 • August/ (Preliminary • April/May 2014 September Engineering 2013 • November/ December 2013 NEPA Schedule: Assess impacts, Data Prepare Clearance Construction determine Collection/ Technical Complete • June 2014 mitigation, Agency and Reports • July 1, 2015 finalize Cat Ex, public scoping • November/ obtain permits December 2013 • August/ • April/May 2014 September 2013

  2. Draft Purpose and Need Based on six recent studies:  Efficient Use of Highway Capacity, November 2010  I-70 Reversible Lane Phase 1 Feasibility Study , August 2010  I-70 Hard Shoulder Running Report , July 2011  I-70 Mountain Corridor Mobility and Operational Assessment , August 2011  I-70 Reversible Lane Phase II Feasibility Study , March 2012  I-70 Peak Period Shoulder Lane Feasibility Study , March 2013

  3. Draft Purpose The purpose of the PPSL project is to:  Provide short-term eastbound operational improvements.  Relieve traffic congestion during peak periods.  Be implemented within a short time frame.  Avoid substantial construction outside of the existing I-70 highway footprint.  Be implemented in advance of longer-term major improvements to the I-70 Mountain Corridor.

  4. Draft Need Statement TRAVEL TIME RELIABILITY  Severely compromised  Affects tourism  Affects economic development  Affects transportation-dependent commerce

  5. Draft Purpose and Need MOTORISTS DIVERT TO ALTERNATE ROUTES  Causes congestion on the frontage road.  Causes reduced safety on the frontage road.  Frontage road provides access to numerous adjacent properties and has a lower speed.  Frontage road is not suitable as an alternate route for I-70 traffic.

  6. Draft Need Statement CONGESTION-RELATED CRASHES  Far more crashes occur in the eastbound direction than in the westbound direction.  For rear-end crashes, 69% of total crashes for eastbound and westbound occurred in the eastbound direction.  For sideswipe crashes, 70% of total crashes for eastbound and westbound occurred in the eastbound direction.

  7. Draft Need Statement EMERGENCY SERVICE PROVIDERS ARE DELAYED AND COMPROMISED.  Emergency vehicles have no other way to get to an incident on I-70 than to try to maneuver around traffic that is stopped because of congestion.  The resulting delay in effective incident management compromises safety, substantially inconveniences other travelers, and results in economic and environmental impacts.

  8. Break

  9. ENVIRONMENTAL ISSUES For Analysis and Documentation BRIEF indicates that the resource is not present or is present but will not be impacted. SOME indicates that the resource is present and may be impacted; further investigation and coordination will be required. FULL indicates that the resource will be impacted and may require mitigation; further investigation and coordination will be required.

  10. Full Assessment FULL indicates that the resource will be impacted and may require mitigation; further investigation and coordination will be required. Wetlands and other Public Involvement Storm/Water Quality Transportation Visual/Aesthetics Waters of the US • Will utilize the I-70 • Will do a full analysis • Will evaluate VMT • Will be focused on • Will conduct wetland Mountain Corridor including and VHT changes, visual impacts of delineations in areas CSS process plus development of changes in travel additional signage that may be additional public measures consistent time and congestion, for the PPSL. physically impacted. involvement as with the Clear Creek effects to safety and Will analyze appropriate County SCAP and any mitigation practicable involvement of the needed to assure alternatives to SWEEP committee. planned operation is minimize or avoid safe. impact. Will coordinate with the SWEEP Issues Task Force and the USACE.

  11. Some Assessment SOME indicates that the resource is present and may be impacted; further investigation and coordination will be required. Air Quality Environmental Justice Floodplains • Will evaluate changes in VMT and • Will assess Census data to • Likely minimal impacts except at VHT. Will conduct climate change determine the low income and bridge replacement locations or analysis plus mobile source air minority populations. If the PPSL is retaining wall locations. Will toxics analysis. Area is not in a tolled, the accessibility of this to involve SWEEP Issues Task Forces non-attainment or maintenance low income and minority in discussions of analysis findings. area so no CO hot spot analysis is populations will be analyzed. needed. Will need to determine if Since the physical improvements a conformity analysis is needed are so minimal and there will be since the period of operation is so mobility benefits during peak minimal. hours, it is unlikely there will be disproportionately high and adverse effects to low income and minority populations.

  12. Some Assessment SOME indicates that the resource is present and may be impacted; further investigation and coordination will be required. Hazardous/Solid Wastes Noise Recreation • Will conduct testing to • Will take existing noise • Will evaluate impacts to rafting determine presence of any measurements and anticipate and fishing, USFS access hazardous or solid waste into a NEPA level analysis looking points. Since physical impacts historic mine waste. Since at locations where travel lanes will be so minimal, level of physical impacts are minimal, may move closer to residential concern is low. it is likely the anticipated level or other sensitive receptors. of concern is low. CDOT has already determined the project is not a Type 1 project so no analysis is needed in compliance with the 2011 guidance.

  13. Some Assessment SOME indicates that the resource is present and may be impacted; further investigation and coordination will be required. Threatened and Endangered Section 4(f) Socioeconomics Wildlife/Fisheries Species (T&E) • Will determine what • Will analyze effects to safety • Will coordinate with CPW, • Anticipate no T&E species recreational Section 4(f) and emergency services, but anticipate minimal are impacted—except for properties there are based economic effects of impacts because the physical South Platte River species. on ownership, public access lessening of congestion impacts are so minimal. Will and inclusion in an adopted during eastbound peak coordinate with ALIVE Issues plan. Will coordinate with period, improvements in Task Force. Section 106 task to mobility. incorporate any historic properties. Will analyze for de minimis impact. Since no new ROW is needed, anticipate something less that a full Section 4(f) evaluation.

  14. Brief Assessment BRIEF indicates that the resource is not present or is present but will not be impacted. Paleontology Right-of-Way Section 6(f) Vegetation • Similar to • Minimal to • Will • Since the Twin no additional coordinate minimal Tunnels EA right-of-way with Clear physical is anticipated Creek impacts will to be County, but occur. needed. anticipate no resources.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend