PROJECT TIMELINE Design-Build Project Procurement Timeline Activity - - PowerPoint PPT Presentation

project timeline design build project procurement timeline
SMART_READER_LITE
LIVE PREVIEW

PROJECT TIMELINE Design-Build Project Procurement Timeline Activity - - PowerPoint PPT Presentation

C HESAPEAKE B AY B RIDGE -T UNNEL Parallel Thimble Shoal Tunnel Project Proposed Parallel Tunnel Existing Tunnel Parallel Thimble Shoal Tunnel Project PROJECT TIMELINE Design-Build Project Procurement Timeline Activity Schedule Project


slide-1
SLIDE 1

CHESAPEAKE BAY BRIDGE-TUNNEL

Parallel Thimble Shoal Tunnel Project

Proposed Parallel Tunnel Existing Tunnel

slide-2
SLIDE 2

Parallel Thimble Shoal Tunnel Project

PROJECT TIMELINE

slide-3
SLIDE 3

Design-Build Project Procurement Timeline

Activity Schedule Project Showcase November 2014 Issue DB Request for Qualifications May 2015 Request for Qualifications Due July 2015 Shortlist DB Teams August 2015 Issue Final RFP February 2016 Technical Proposals due March 2016 Final Pricing due April 29, 2016 Revised Technical Proposals due July 12, 2016 Revised Proposal Pricing due July 15, 2016

slide-4
SLIDE 4

Parallel Thimble Shoal Tunnel Project

RESULTS OF DB PROCUREMENT

Design‐Build Teams Tunnel Method Qualification Proposed Tunnel Construction Method April 29 Proposal Price July 15 Proposal Price Archer Western – Vinci Construction TunnelBuilders (AWVC) ITT and Bored Bored $1,071,683,000 $785,883,000 Bouygues TP/Traylor/Manson (BTM JV) ITT and Bored Bored $1,016,046,800 $848,452,987 Dragados Team: Dragados USA and Schiavone Construction Company, LLC Bored Bored $1,092,000,000 $755,987,318 SKW Tunnel Builders ITT ‐‐‐ No Proposal ‐‐‐

slide-5
SLIDE 5

Island #1 Expansion

to include Full Public Access with Restaurant/Gift Shop

April 29, 2016 Phase I Procurement Rendering

Restaurant, Gift Shop, Visitor Center – 15,000 square feet New Tunnel Existing Ventilation Building New Ventilation Building

  • Required Island Expansion of
  • approx. 3.25 acres
  • 338 Parking Spaces
slide-6
SLIDE 6

Island #1 - No Restaurant

July 12, 2016 Revised Rendering

No Island Expansion

New Vent Building

New Tunnel Existing Ventilation Building

slide-7
SLIDE 7

The Dragados Team:

Dragados USA and Schiavone Construction Co. LLC

slide-8
SLIDE 8

Tunnel Boring Machine

Rotating cutter head The machine is operated from the control room Pressure is maintained in the cutting chamber Rotating arm adds pre‐cast concrete Tunnel segments to form a ring Pre‐cast concrete segments delivered to rotating arm Excavated earth removed by conveyor belt Hydraulic rams push against newly‐placed concrete segments to drive machine forward Approximate TBM diameter is 42’

slide-9
SLIDE 9

Parallel Thimble Shoal Tunnel Project

PROJECT FUNDING

No operating subsidies from the Federal Government, State or Localities

slide-10
SLIDE 10

Design-Build Technical Timeline

Activity Schedule Limited Notice to Proceed (LNTP) August 2016 – December 2016 Notice to Proceed 1 (NTP1) January 2017 – September 2017 Notice to Proceed 2 (NTP2) Construction Begins – October 1, 2017