LIU-ABT systems: PSB BI.DIS10 controls

  • Agenda: https://indico.cern.ch/event/525232/
  • Timing system (Christophe Chanavat)
  • Fast interlocks studies (Felipe Cordobes Dominguez)
  • IGBT’s R&D program (Tobias Stadlbauer & Luc Sermeus)
  • General controls (Roger Andrew Barlow)

prepared by R.A.Barlow 12/05/2016

1

CERN

TE-ABT-EC

slide-2
SLIDE 2

2

BI.DIS10

Generator prototype, Jura 6 Status of technical progress

  • Prototype

BI.DIS10 controls completed with TECHNIX 10kV-1A power supply integration

  • Improved IGBT protection and triggering
  • Pulsed power system near completion (PFN &

Magnet)....but issues with inductors...

  • Thermal studies & reliability runs have started (April

2016) up to 8kV...to go further...worst case not studied yet

  • Fast interlock system (early tests planned for April

2016)...?

  • Review of logical connection to BIS ongoing (1

channel Vs. 4 channels) …still to be discussed by MPE group.

  • Looking at current technology issues concerning

PFN signal conditioning, to be determined trough tests !!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!!

slide-3
SLIDE 3

BI.DIS10

Generator controls and production PLC controls production

  • 95% PLC modules ordered, arrived !

FSU jobs created for the following:

  • ABTECMAINT-48 Installation components BI.DIS10 in BCER (Linac4/LS2)
  • ABTECPROD-18 Cablage des 6 PFN pour le BI.DIS10 (Naked shells ready)
  • ABTECPROD-20 JURA6 BI.DIS10 patch traversant prototype (Change-over proto)
  • ABTECPROD-21 Pre-production series for PLC crates BI.DIS10 (Master, OP, GPC, EDS)

FSU jobs created for the following:

  • ABTECPROD-22 Production of series PLC crates for BI.DIS10 (Outside ?)
  • ABTECPROD-25 Patch panel de series pour BI.DIS10 au BCER (Outside ?)
  • ABTECPROD-19 Cablage des unites casette IGBT pour le BI.DIS10 (Outside ?)

Chassis drawings and cabling drawings started, aim to have all this ready by end of MAY-2016. PDC production envisage for September...

slide-4
SLIDE 4

BI.DIS10

Budget

  • 1.) Materials to be ordered for end 2016 delivery:
  • Major order placed for PLC components: 25kCHF – DONE-> (23kCHF)
  • FIS system: 90 kCHF
  • Timing KiT’s: 10 kCHF
  • PDC: 10kCHF
  • Other (AUE. Flashers, Scope, etc..): 10kCHF
  • TOTAL: 145kCHF
  • 2.) FSU taskforce expenditure:
  • Pre-production crates: 3 man.week
  • Pre-production specialised cables: 1 man.week
  • Final specialised control cables + patches 6 generators: 5 man.week
  • PFN internal cabling (6 of): 6 man.week
  • IGBT cassette cabling (6 of): 4 man.week
  • TOTAL: 19 man.week / 30kCHF
  • 3.) Equipment to be built by external companies:
  • PLC chassis: 40kCHF
slide-5
SLIDE 5

BI.DIS10

Documentation PBU-MSMIA-ES-0001 - Functional Specification BI.DIS10 Controls (EDMS 1339372) Released PSB-MSMIA-ES-0008 - Engineering Specification BI.DIS10 controls (EDMS 1574218) Under approval PSB-MSMIA-ES-0006 - Engineering Specification, Beam Interlock Specification For Booster BI.DIS10 with linac4 (EDMS 1571034) In work PSB-MSMIA-ES-0004 - Functional Specification, BI.DIS10 Fast interlocks (EDMS 1537992) Engineering check PSB-MSMIA-ES-0005 - Engineering Specification, BI.DIS10 Fast interlocks (EDMS 1538154) In work and recently added ! PSB-MSMIA-ES-0007 - BI.DIS10 GENERATOR SPARE CONNECTION TO MAGNET PROCEDURE (EDMS 1571059) Under approval