fy15 prop opos osed capi pit al i m pr provem ent budge
play

FY15 Prop opos osed Capi pit al I m pr provem ent Budge dget - PowerPoint PPT Presentation

Massachusetts Water Resources Authority Presentation to Board of Directors FY15 Prop opos osed Capi pit al I m pr provem ent Budge dget Rachel C. Madden Director, Administration and Finance December 18, 2013 FY15 Proposed CI P Debt


  1. Massachusetts Water Resources Authority Presentation to Board of Directors FY15 Prop opos osed Capi pit al I m pr provem ent Budge dget Rachel C. Madden Director, Administration and Finance December 18, 2013

  2. FY15 Proposed CI P – Debt burden reduced; – Paying more principal than interest; and – Meets all Cap requirements. 2

  3. Projected Debt Burden Decreases MWRA's Outstanding Debt Total Outstanding Total Outstanding $6,500,000,000 Debt will decrease Debt Increased by $258 million by $264 million $6,000,000,000 Total Outstanding Debt Increased by $619 million $5,500,000,000 $5,000,000,000 $4,500,000,000 $4,000,000,000 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 FY04-08: $1.135 billion FY14-18: $791.7 million FY09-13: $1.144 billion 3

  4. Paying More Principal than I nterest MWRA Principal and Interest Payment History and Projections $600 $500 $400 Millions $300 $200 $100 $0 FY90 FY92 FY94 FY96 FY98 FY00 FY02 FY04 FY06 FY08 FY10 FY12 FY14 FY16 FY18 FY20 FY22 FY24 FY26 FY28 FY30 FY32 FY34 FY36 FY38 FY40 FY42 FY44 Interest Principal 4

  5. FY14-18 Base-Line Cap as Compared with FY15 Proposed Total FY14-18 Base-Line FY14 FY15 FY16 FY17 FY18 FY14-18 Projected Expenditures $142.5 $147.6 $149.3 $141.8 $136.8 $718.0 Cap Contingency 7.6 9.5 10.1 9.8 9.3 46.1 Inflation on Unawarded Construction 0.8 4.2 8.4 11.1 13.5 37.9 Less: Chicopee Valley Aqueduct Projects (5.0) (2.2) (1.4) (1.3) (0.4) (10.3) FY14-18 Base-Line Cap $145.8 $159.1 $166.4 $161.3 $159.1 $791.7 Total FY14 FY15 FY16 FY17 FY18 FY15 Proposed FY14-18 Projected Expenditures $117.0 $124.6 $145.9 $170.3 $161.0 $718.8 Contingency 5.9 7.5 9.9 11.8 11.0 46.2 Inflation on Unawarded Construction 0.0 1.0 4.8 9.9 12.7 28.3 Less: Chicopee Valley Aqueduct Projects (4.7) (1.0) (0.2) (0.2) (0.2) (6.2) FY15 Proposed FY14-18 Cap $118.2 $132.2 $160.4 $191.8 $184.5 $787.1 FY15 Proposed vs FY14- Total FY14 FY15 FY16 FY17 FY18 18 Base-Line Cap FY14-18 Projected Expenditures ($25.5) ($22.9) ($3.4) $28.5 $24.2 $0.9 Contingency (1.6) (2.0) (0.1) 2.1 1.8 0.1 Inflation on Unawarded Construction (0.8) (3.2) (3.6) (1.2) (0.8) (9.6) Less: Chicopee Valley Aqueduct Projects 0.3 1.2 1.2 1.1 0.2 4.1 Proposed FY15 Final FY14-18 Cap ($27.5) ($26.9) ($5.9) $30.4 $25.4 ($4.6) FY14-18 Cap (% Change) -18.9% -16.9% -3.6% 18.9% 16.0% -0.6% 5

  6. FY15 Community Assistance Program – I nflow & I nfiltration • No additional I/I funding; • Advisory Board Operations Committee recently voted on two additional phases; • FY15 Final CIP will likely include additional funding; • Will have Cap implications; and • Will consider exempting the Community Financial Assistance Programs from the Cap. 6

  7. FY14-18 Proposed CI P Expenditures by Major Programs Business Operations & Support $39.5 5% Wastewater (excluding CSO) Waterworks $334.5 $289.9 47% 40% CSO $54.9 8% 7

  8. FY15 Proposed CI P Expenditures by Major Programs Business and Operations Support $9.6 8% Wastewater Waterworks (excluding CSOs) $54.0 $42.0 43% 34% CSO $19.1 15% 8

  9. FY15 Big Spenders FY15 Planned Spending DI Treatment Plant Asset Protection $ 39.5 Long-Term Redundancy 14.8 Facility Asset Protection 12.7 Cambridge Sewer Separation 11.9 Spot Pond Storage Facility 8.3 Carroll Water Treatment Plant 8.1 Weston Aqueduct Supply Mains 3.9 Dorchester Bay Sewer Separation (Commercial Point) 3.8 Equipment Purchase 2.7 Applications Improvement Program 2.3 Top 10 Spending in FY15 $ 108.0 FY15 Spending $ 124.4 The top ten projects account for 86.9% of FY15 planned spending. 9

  10. On-Going Capital Projects 10

  11. Deer I sland Asset Protection Total Budget $651.7M Spending Through FY13 $147.5M Remaining Spending: $504.1M FY14-18 Spending: $195.5M FY15 Spending: $ 39.5M 11

  12. Deer I sland: Scum Skimmer Replacement NTP: October 2013 SC : October 2016 Total Contract: $20.2M FY14-18 Spending: $20.2M FY15 Spending: $ 6.7M 12

  13. Deer I sland: North Main Pump Station Motors/ VFDs NTP: December 2011 SC : March 2016 Total Contract: $24.3M FY14-18 Spending: $17.7M FY15 Spending: $ 3.2M 13

  14. North Main Pump Station and Winthrop Terminal Facility Butterfly Valve Replacements NTP: May 2014 SC : May 2016 Total Contract: $14.6M FY14-18 Spending: $14.6M FY15 Spending: $ 4.9M 14

  15. Deer I sland Electrical Upgrades - Construction 4 NTP: May 2013 SC : May 2016 Total Contract: $10.9M FY14-18 Spending: $10.9M FY15 Spending: $ 3.9M 15

  16. Carroll Water Treatment Plant UV NTP: May 2011 SC : March 2014 Total Contract: $32.0M Spending thru FY13: $29.2M FY14-18 Spending: $ 2.8M FY15 Spending: $ 0.1M 16

  17. Quabbin Ultraviolet Disinfection Project NTP: January 2013 SC : August 2014 Total Contract: $5.7M FY14-18 Spending: $4.0M FY15 Spending: $0.0M 17

  18. Spot Pond Covered Storage Facility and Pump Station NTP: November 2011 SC : November 2014 Total Contract: $50.0M FY14-18 Spending: $32.4M FY15 Spending: $ 7.2M 18

  19. Spot Pond Covered Storage Facility and Pump Station 19

  20. Cambridge Sewer Separation - Construction Total Contract: $61.7M FY14-18 Spending: $32.5M FY15 Spending: $ 8.9M NTP: July 1998 SC : December 2015 20

  21. Cambridge Sewer Separation - Construction Drain Vault # 1 Vassal Lane Track removal along Concord Ave 21

  22. Alewife Brook Pump Station Rehabilitation NTP: January 2015 SC : May 2017 Total Contract: $9.3M Fy14-18 Spending: $9.3M FY15 Spending: $2.1M 22

  23. Upcoming Capital Projects 23

  24. Chelsea Headworks Rehabilitation Design NTP: July 2010 SC : December 2019 Total Contract: $7.9M FY14-18 Spending: $4.2M FY15 Spending: $0.1M Construction NTP: July 2015 SC : December 2018 Total Contract: $53.7M FY14-18 Spending: $42.2M FY15 Spending: $ 0.0M 24

  25. Wachusett Aqueduct Pump Station NTP: August 2014 SC : January 2017 Total Contract: $47.0M FY14-18 Spending: $47.0M FY15 Spending: $12.5M 25

  26. Southern Extra High Redundancy – Section 111 NTP: August 2016 SC : June 2020 Total Contract: $29.2M FY14-18 Spending: $16.7M FY15 Spending: $ 0.0M 26

  27. Clinton Treatment Plant Phosphorous Removal Design & Construction NTP: December 2013 SC : August 2017 Total Contract: $6.9M FY14-18 Spending: $6.9M FY15 Spending: $0.3M 27

  28. Future Risks • Residual Processing/Asset Management; • Sudbury Aqueduct – tunnel vs. surface pipeline; • North Metropolitan Trunk Sewer Rehabilitation; • Chelsea Creek Headworks Rehabilitation; and • New regulatory mandates. 28

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend