Shaft 5A Pipe Break May 6, 2010 2 SYSTEM OVERVI EW 3 Normal Flow - - PowerPoint PPT Presentation

shaft 5a pipe break
SMART_READER_LITE
LIVE PREVIEW

Shaft 5A Pipe Break May 6, 2010 2 SYSTEM OVERVI EW 3 Normal Flow - - PowerPoint PPT Presentation

Massachusetts Water Resources Authority Presentation to the MWRA Board of Directors Shaft 5A Pipe Break May 6, 2010 2 SYSTEM OVERVI EW 3 Normal Flow 4 Normal Flow 5 Diverted Flow After Leak 6 Shaft 5 Break Site 7 I NCI DENT OVERVI EW


slide-1
SLIDE 1

Massachusetts Water Resources Authority

Presentation to the

MWRA Board of Directors

Shaft 5A Pipe Break

May 6, 2010

slide-2
SLIDE 2

2

SYSTEM OVERVI EW

slide-3
SLIDE 3

3

Normal Flow

slide-4
SLIDE 4

4

Normal Flow

slide-5
SLIDE 5

5

Diverted Flow After Leak

slide-6
SLIDE 6

6

Shaft 5 Break Site

slide-7
SLIDE 7

7

I NCI DENT OVERVI EW

slide-8
SLIDE 8

8

Surveillance Camera Captures Leak

slide-9
SLIDE 9

9

Changes in Flow

slide-10
SLIDE 10

10

Charles River Flow Impacts

slide-11
SLIDE 11

11

Immediate Response

  • 10:01 AM - Loss of communication alarm from Shaft 5 received at

Carroll Water Treatment Plant (CWTP)

  • 10:05 AM - Chelsea Security calls CWTP to report that water

discharge was observed on the camera at Shaft 5

  • 10:05 & following initial notifications to and mobilization of MWRA

management, operations, engineering, construction and support

  • staff. Flow at Shaft 5 reported to have immediately gone from 200

mgd to 450 mgd

slide-12
SLIDE 12

12

Communications

  • These parties were quickly provided by phone or e-mail with a

preliminary assessment of the incident and the potential impacts: – MWRA Staff – Board of Directors – Governors Office – Department of Public Health – Department of Environmental Protection – Fire Marshalls – MEMA – Service Area Communities

slide-13
SLIDE 13

13

Immediate Operational Response

  • Increase plant flows (match flow to demand) to mitigate loss of

storage in the Norumbega Reservoir

  • Shut down Cosgrove Turbine to avoid potential impacts
  • Metropolitan system operation stable and decision to continue

flow through the break site

  • Contact partial user communities and request use of local sources

(Bedford, Woburn, Wakefield, Wellesley, Needham, Peabody, Wilmington, Stoughton)

  • Coordinate/control tank fillings to regulate flow (Blue Hills, Loring

Road, etc.)

slide-14
SLIDE 14

14

Sudbury System/Chestnut Hill Emergency Pump Station

  • Hydraulic grade lines below targets – fire protection
  • Fear of catastrophic failure at break site
  • Fear of loss of backpressure necessary to start Chestnut Hill

Pumps Station and air intrusion in system

  • Imminent loss of power at Shaft 5 resulting in significant delay if

shut down

slide-15
SLIDE 15

15

Sudbury System/Chestnut Hill Emergency Pump Station

  • May 1

– Operated for 7 hours

  • May 2

– Operated for 8 hours

  • Sudbury Aqueduct

– Activated May 1, shut down May 4, 9:30 AM – Transferred approximately 90 million gallons

slide-16
SLIDE 16

16

Sudbury System

slide-17
SLIDE 17

17

Chestnut Hill

slide-18
SLIDE 18

18

Spot Pond

  • Staffed, all valving reset and chlorine delivered May 1
  • Could have provided another 30-40 million gallons per day
slide-19
SLIDE 19

19

Emergency Operations Center Received 4,162 Calls

slide-20
SLIDE 20

20

PI PE BREAK AND REPAI R

slide-21
SLIDE 21

21

Coupling

slide-22
SLIDE 22

22

Pipe Repair Timeline

EVENT DATE/TIME Leak Detected on Security Cameras May 1/10:00 am Total Line Shut Down May 1/6:40 pm Dewatering of Flooded Area Complete May 1/10:00 pm Pipe and Repair Collar Preparation for welding begins May 1/10:00 pm Pipe and Collar Preparation Completed May 2/9:15 am Welding of Collar on Bottom Half of Pipe Begins May 2/10:00 am Welding of Collar on Bottom Half of Pipe Complete May 2/10:00 pm Chlorine Addition Complete May 2/11:00 pm Welding of Collar on Top Half of Pipe Begins May 2/11:00 pm Concrete Cradle Pour Begins May 2/Midnight Concrete Cradle Pour Complete May 3/12:45 am Welding of Collar on Top Half of Pipe Complete May 3/ 4:00 am Filling of Pipe Begins May 3/ 4:00 am Filling of Pipe Complete May 3/ 4:30 am Pipe Pressure Test Begins May 3/ 4:30 am Pipe Placed into Service May 3/ 5:30 am Flow Fully Restored May 3/ 6:15 am

slide-23
SLIDE 23

23

Dewatering

slide-24
SLIDE 24

24

Top of Pipe

slide-25
SLIDE 25

25

Rubber Gasket

slide-26
SLIDE 26

26

Pipe Joint

slide-27
SLIDE 27

27

Probing

slide-28
SLIDE 28

28

Installing New Strap

slide-29
SLIDE 29

29

Welding Strap in Place

slide-30
SLIDE 30

30

Welding Strap in Place

slide-31
SLIDE 31

31

New Strap Installation Completed

slide-32
SLIDE 32

32

Concrete Cradle Poured

slide-33
SLIDE 33

33

WATER QUALI TY

slide-34
SLIDE 34

34

Activation of Chestnut Hill Pump Station – Water Quality

  • Prior to activation, tested raw water at gatehouse for E. coli, VOC, SOC,

metals

  • Results available 24 hours later – all within health standards
  • Chlorine tank truck delivered to site and treatment system prepared
  • Hourly monitoring of chlorine residual near first meter/first customer
slide-35
SLIDE 35

35

Next Steps

  • Worked with DEP to determine criteria for lifting the boil order

– Agreed to conducting two rounds of coliform sampling each Sunday and Monday (continuing as needed) – About 400 samples per round - Each round represents a normal week

  • f sampling
  • Test results include total coliform, E. coli, and chlorine residual
  • Agreed with DEP that two rounds of samples about 8 hours apart would

allow boil order to be lifted

  • Communities contacted Sunday morning to collect two rounds of samples
slide-36
SLIDE 36

36

Sample Collections Averaged 8 hours Between First and Second Rounds

slide-37
SLIDE 37

37

Boil Order Lifted

  • Last of Sunday sample results were available at approximately 1 am

Tuesday

  • DEP set up emergency operations at the Chelsea facility to monitor results
  • Two remaining community results (from Monday first round) available at

2:37 am and 6:30 am

  • Boil order lifted at approximately 3 am Tuesday for 29 communities
  • Boil order for all 30 communities lifted at about 7 am Tuesday
slide-38
SLIDE 38

38

Sampling Locations

slide-39
SLIDE 39

39

EMERGENCY RESPONSE PREPARATI ON

slide-40
SLIDE 40

40

Emergency Planning

  • The MWRA has developed and maintains contingency or emergency plans for a

wide range of events, including:

  • 140 Individual Emergency Action Plans for each of the MWRA’s facilities and

events

  • Emergency Service Unit plans for responding to water contamination
  • Specific plans for reactivating backup facilities
  • Continuity of Operations Plan
  • Emergency Plans for all MWRA Dams
  • Integrated Contingency Plans for Deer Island and the Carroll Water Treatment

Plant

  • Spill Control Plans
slide-41
SLIDE 41

41

Training and Drills

  • MWRA staff regularly participate in drills

and training exercises

  • These have included a 2006 exercise that

specifically involved damage to Shaft 5 and the resulting need to activate the Sudbury Aqueduct

  • Other training and exercises include:

– Major yearly exercises – Monthly Emergency Service Unit drills – Boom Deployment drills using boats and other equipment – Mobile Disinfection Unit drills and deployments – Notification Drills

slide-42
SLIDE 42

42

Emergency Equipment

slide-43
SLIDE 43

43

PRELI MI NARY I NVESTI GATI ON

slide-44
SLIDE 44

44

Forensics to Date and On Going

  • As soon as the site (hole) was dewatered, MWRA Staff and Consultants

and Contractor started: – Visual Inspection – Excavation below Pipe

  • People under pipe doing inspection
  • Vactor removal of loose material under pipe
  • Probing into soil under pipe by geotechnical consultant

– State Police divers in Charles River looking for old collar – Ground penetrating radar and electromagnetic detectors to try locate

  • ld collar

– Soil removal from River, with stockpiling on adjacent land to inspect for old collar or other information – Magnetic Metal Detectors – Metallurgical tests on any metal found

slide-45
SLIDE 45

Massachusetts Water Resources Authority

slide-46
SLIDE 46

46

slide-47
SLIDE 47

47

slide-48
SLIDE 48

48

slide-49
SLIDE 49

49

slide-50
SLIDE 50

50

slide-51
SLIDE 51

51

slide-52
SLIDE 52

52

slide-53
SLIDE 53

53

slide-54
SLIDE 54

54

Consultants and Sub-Consultants

  • DESIGN CONSULTANT, MWRA Contract No. 5044
  • Prime consultant:

– Sverdrup Corporation/Sverdrup Civil, Inc.

  • Sub-consultants:

– Boston Affiliates – Delon Hampton & Associates – Fay, Spofford & Thorndike, Inc – Goldberg Zoino & Associates – Jacobs Engineering – Lenz Engineering – Judith Nitsch Engineering, Inc – GPR (sub-sub to Goldberg Zoino) – Offset Prep – GZA Geo Environmental, Inc.

slide-55
SLIDE 55

55

Consultants and Sub-Consultants

  • CONSTRUCTION MANAGEMENT & RESIDENT ENGINEERING

CONSULTANT, MWRA Contract No. 5284

  • Prime consultant:

– Stone & Webster Civil and Transportation Services, Inc. (assigned to Stone & Webster Massachusetts, Inc. and The Shaw Group)

  • Sub-consultants:

– Stone & Webster Construction Company, Inc. – Parsons Brinckerhoff Construction Services, Inc. – DMC Engineering, Inc. – H2O Engineering Consulting Associates, Inc. – Judith Nitsch Engineering, Inc. – Regina Villa Associates, Inc. – Toxikon – Hager GeoScience – Revet Laboratories

slide-56
SLIDE 56

56

Contractors and Sub-Contractors

  • CONSTRUCTION CONTRACTOR, MWRA Contract No. 6374
  • Prime Contractor:

– Shea-Traylor-Healy, Joint Venture

  • Sub-contractors:

– Barletta Engineering/Daniel O’Connell’s Sons – Harding & Smith – E.J. Smith Construction Corporation – E.T. & L. Construction Corporation – Determining if others

slide-57
SLIDE 57

57

Reviewing Other Projects

  • Reviewed 28 Projects to date including other MetroWest Water Supply projects.

The failed coupling is the only coupling of its type on the entire MWWST project and the ongoing Hultman Aqueduct Interconnections project

  • 8 Projects used similar couplings under varying conditions

– Many existing locations have been retrofitted or included internal joint seals – Many of the projects included low pressure lines – Projects where couplings have been used will be evaluated for risk of failure depending on the findings related to the recent event

  • Staff will continue to review additional projects since Depend-O-Lok couplings

became available

slide-58
SLIDE 58

58

HULTMAN REHABI LI TATI ON

slide-59
SLIDE 59

59

Hultman Aqueduct Rehabilitation and I nterconnections

  • Two construction contracts

– CP-6A Lower Hultman – under construction

  • Phase 1: Shaft 4 to Norumbega Covered Storage (9/2009-

9/2011)

  • Phase 2: Norumbega Covered Storage to Shafts 5/5A and W

(10/2011-9/2014)

– CP-6B Upper Hultman – to be designed

  • Rehab Hultman from Shaft C to Shaft 4
  • Rehab Shaft 4 Top of Shaft Structure
  • (5/2012-5/2014)
slide-60
SLIDE 60

60

CP-6A Hultman Aqueduct Rehabilitation and I nterconnections with MetroWest Tunnel

slide-61
SLIDE 61

61

CP-6A Project Scope and Schedule

  • Inspect and rehabilitate 13.5 miles of Hultman Aqueduct and

appurtenances

  • 4 new interconnections between the Hultman Aqueduct and the

MWWST

  • 6 new valves on Hultman Branch at River Road in Weston
  • Current Project Schedule: September 2009 – September 2014
slide-62
SLIDE 62

62

CP-6B Project Scope and Schedule

  • Rehabilitate Hultman Aqueduct and appurtenances from Shaft C

to Shaft 4

  • Rehabilitate Shaft 4 Top of Shaft Structure
  • Current Project Schedule: May 2012 – May 2014

CP-6A Project Scope and Schedule

slide-63
SLIDE 63

63

CP-6A Current Sequence of Work

  • Designed to minimize number of sections that are unavailable at

any given time.

  • Maintain uninterrupted service to customers during normal
  • peration.

– Valves need to be added at the interconnection between the Hultman 84-in Branch and WASM 3 at River Road in Weston prior to working on Hultman east of Norumbega. – Valve work at River Road in Weston must be completed during low demand winter months – Improvements must be made to the Waltham water distribution system to allow WASM 3 to be shut down during the River Road valve work

slide-64
SLIDE 64

64

Reassessment of Project Schedules for CP-6A & CP-6B

  • A comprehensive reassessment of the sequence of work for CP-

6A and CP-6B has begun with contractor, designer and MWRA

  • staff. Factors being analyzed:

– Valve manufacturing lead time – Working additional shifts on weekends – Contractor resources – Reevaluating seasonal flow constraints – Coordination with other ongoing MWRA projects – Acceleration of CP-6B contract award – Risk of additional sections out of service for rehabilitation

slide-65
SLIDE 65

65

REDUNDANCY I NI TI ATI VES

slide-66
SLIDE 66

66

Water Redundancy Spending

Water Redundancy Spending thru FY09 and Projected to FY20 and Beyond ($ in Millions)

$1.7 $1.9 $1.0 $5.5 $4.4 $4.0 $11.4 $68.7 $104.6 $159.7 $128.9 $114.9 $104.8 $87.3 $40.2 $31.1 $20.1 $25.1 $38.3 $47.7 $97.8 $85.7 $53.0 $34.9 $43.2 $91.7 $36.1 $34.3 $33.7 $42.8 $39.0 $27.9 $0.0 $20.0 $40.0 $60.0 $80.0 $100.0 $120.0 $140.0 $160.0 $180.0 F Y 9 F Y 9 1 F Y 9 2 F Y 9 3 F Y 9 4 F Y 9 5 F Y 9 6 F Y 9 7 F Y 9 8 F Y 9 9 F Y F Y 1 F Y 2 F Y 3 F Y 4 F Y 5 F Y 6 F Y 7 F Y 8 F Y 9 F Y 1 F Y 1 1 F Y 1 2 F Y 1 3 F Y 1 4 F Y 1 5 F Y 1 6 F Y 1 7 F Y 1 8 F Y 1 9 F Y 2 B e y

  • n

d F Y 2

Average Annual Spending from FY97 through FY10 is $70.7 Million