Massachusetts Water Resources Authority
Presentation to the
Shaft 5A Pipe Break May 6, 2010 2 SYSTEM OVERVI EW 3 Normal Flow - - PowerPoint PPT Presentation
Massachusetts Water Resources Authority Presentation to the MWRA Board of Directors Shaft 5A Pipe Break May 6, 2010 2 SYSTEM OVERVI EW 3 Normal Flow 4 Normal Flow 5 Diverted Flow After Leak 6 Shaft 5 Break Site 7 I NCI DENT OVERVI EW
Presentation to the
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
EVENT DATE/TIME Leak Detected on Security Cameras May 1/10:00 am Total Line Shut Down May 1/6:40 pm Dewatering of Flooded Area Complete May 1/10:00 pm Pipe and Repair Collar Preparation for welding begins May 1/10:00 pm Pipe and Collar Preparation Completed May 2/9:15 am Welding of Collar on Bottom Half of Pipe Begins May 2/10:00 am Welding of Collar on Bottom Half of Pipe Complete May 2/10:00 pm Chlorine Addition Complete May 2/11:00 pm Welding of Collar on Top Half of Pipe Begins May 2/11:00 pm Concrete Cradle Pour Begins May 2/Midnight Concrete Cradle Pour Complete May 3/12:45 am Welding of Collar on Top Half of Pipe Complete May 3/ 4:00 am Filling of Pipe Begins May 3/ 4:00 am Filling of Pipe Complete May 3/ 4:30 am Pipe Pressure Test Begins May 3/ 4:30 am Pipe Placed into Service May 3/ 5:30 am Flow Fully Restored May 3/ 6:15 am
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
wide range of events, including:
events
Plant
41
and training exercises
specifically involved damage to Shaft 5 and the resulting need to activate the Sudbury Aqueduct
– Major yearly exercises – Monthly Emergency Service Unit drills – Boom Deployment drills using boats and other equipment – Mobile Disinfection Unit drills and deployments – Notification Drills
42
43
44
46
47
48
49
50
51
52
53
54
55
56
57
The failed coupling is the only coupling of its type on the entire MWWST project and the ongoing Hultman Aqueduct Interconnections project
– Many existing locations have been retrofitted or included internal joint seals – Many of the projects included low pressure lines – Projects where couplings have been used will be evaluated for risk of failure depending on the findings related to the recent event
became available
58
59
60
61
62
63
– Valves need to be added at the interconnection between the Hultman 84-in Branch and WASM 3 at River Road in Weston prior to working on Hultman east of Norumbega. – Valve work at River Road in Weston must be completed during low demand winter months – Improvements must be made to the Waltham water distribution system to allow WASM 3 to be shut down during the River Road valve work
64
– Valve manufacturing lead time – Working additional shifts on weekends – Contractor resources – Reevaluating seasonal flow constraints – Coordination with other ongoing MWRA projects – Acceleration of CP-6B contract award – Risk of additional sections out of service for rehabilitation
65
66
Water Redundancy Spending thru FY09 and Projected to FY20 and Beyond ($ in Millions)
$1.7 $1.9 $1.0 $5.5 $4.4 $4.0 $11.4 $68.7 $104.6 $159.7 $128.9 $114.9 $104.8 $87.3 $40.2 $31.1 $20.1 $25.1 $38.3 $47.7 $97.8 $85.7 $53.0 $34.9 $43.2 $91.7 $36.1 $34.3 $33.7 $42.8 $39.0 $27.9 $0.0 $20.0 $40.0 $60.0 $80.0 $100.0 $120.0 $140.0 $160.0 $180.0 F Y 9 F Y 9 1 F Y 9 2 F Y 9 3 F Y 9 4 F Y 9 5 F Y 9 6 F Y 9 7 F Y 9 8 F Y 9 9 F Y F Y 1 F Y 2 F Y 3 F Y 4 F Y 5 F Y 6 F Y 7 F Y 8 F Y 9 F Y 1 F Y 1 1 F Y 1 2 F Y 1 3 F Y 1 4 F Y 1 5 F Y 1 6 F Y 1 7 F Y 1 8 F Y 1 9 F Y 2 B e y
d F Y 2
Average Annual Spending from FY97 through FY10 is $70.7 Million