Tideway Community Liaison Working Group Heathwall Pumping Station - - PowerPoint PPT Presentation

tideway community liaison working group
SMART_READER_LITE
LIVE PREVIEW

Tideway Community Liaison Working Group Heathwall Pumping Station - - PowerPoint PPT Presentation

Tideway Community Liaison Working Group Heathwall Pumping Station Kirtling Street Tunnels 1 Agenda Tideway Central Project Overview if required Heathwall Site Progress and Programme Kirtling Street Site Progress and Programme


slide-1
SLIDE 1

1

Tideway Community Liaison Working Group

Heathwall Pumping Station Kirtling Street Tunnels

slide-2
SLIDE 2

2

Agenda

  • Tideway Central Project Overview – if required
  • Heathwall Site Progress and Programme
  • Kirtling Street Site Progress and Programme
  • Site Air Quality and Noise Data – shortened
  • Community Relations
  • Other items / Actions from Last Meeting
  • Notifications
  • Greenwall
  • Settlement
slide-3
SLIDE 3

3

Tideway Central – Project Overview

Justin in Feltham ham – Environment ironmental al Ad Adviser iser

slide-4
SLIDE 4

4

Bazalgette’s interceptor sewers

slide-5
SLIDE 5

5

slide-6
SLIDE 6

6

Project Overview

  • Heathwall Pumping Station
  • Existing Combined Sewer Outfall into Thames.
  • Diversion of existing CSO to allow it to operate while we work.
  • Construction of cofferdam and placement of infill material to construct

interception chamber and shaft.

  • Construction of CSO Shaft to connect new Tunnel.
  • Kirtling Street
  • Drive site for construction of tunnel
  • Services and materials for TBM.
  • Removal of excavated material from TBM.
slide-7
SLIDE 7

7

HEATHWALL PUMPING STATION UPDATE

Nick k Rowlan wland d – Marine ine Works ks Sub Agent ent Landside Works and Marine Works

slide-8
SLIDE 8

8

Heathwall Pumping Station Works

Main Tunnel Existing Pumping Station PS Shaft PS Chamber CSO Shaft Air-Treatment Chamber SWSR Chamber

slide-9
SLIDE 9

9

  • Diversion of existing Pumping Station Outfall to new location to allow

us to construct our cofferdam.

  • Construction of UKPN Substation for HEAPS operation.
  • Installation of ground water wells and pump test.

Works to date

slide-10
SLIDE 10

10

  • Ongoing – clearance of

marine pile locations

Marine Works

slide-11
SLIDE 11

11

Marine Works – High Water Looking West

slide-12
SLIDE 12

12

Marine Works – High Water Looking East

slide-13
SLIDE 13

13

Marine Works – Low Water Looking West

slide-14
SLIDE 14

14

Marine Works – Low Water Looking East

slide-15
SLIDE 15

15

Marine Works

  • Piles delivered by river – next week
  • Vibro piling undertaken during core working hours 08:00 – 18:00
  • Impact Piling 5 hours per day – 20 hours per Week
  • Noise Monitoring ongoing
slide-16
SLIDE 16

16

Marine Works – Interception Shaft Excavation

slide-17
SLIDE 17

17

Heathwall Final Layout

slide-18
SLIDE 18

18

Heathwall Street Programme

  • From Mid to Late June
  • Complete pile line clearance, pump station outfall demolition activity
  • Begin installation of cofferdam.
  • July & August
  • Continuation of cofferdam installation
  • Piling for landside CSO Shaft and chambers
slide-19
SLIDE 19

19

KIRTLING STREET RECENT WORKS

Al Alber erto to Gonzal nzalez ez – Civi vils ls Work rks s Site Agent nt Drive Shaft and Tunnel Boring Machine Launch Adits

slide-20
SLIDE 20

20

We have a shaft

slide-21
SLIDE 21

21

Launch Adit Construction

slide-22
SLIDE 22

22

Launch Adit Construction

slide-23
SLIDE 23

23

Breaking Out D-Wall

slide-24
SLIDE 24

24

Ground-borne Vibration

slide-25
SLIDE 25

25

Building an adit

slide-26
SLIDE 26

26

Building an adit

slide-27
SLIDE 27

27

Building an adit

slide-28
SLIDE 28

28

KIRTLING STREET RECENT WORKS

Russell ssell Brown wn – Tunnel nnel Senior nior Projec

  • ject

t Manager ager Tunnel Boring Machine, Gantries and Conveyor

slide-29
SLIDE 29

29

Tunnel Boring Machine (TBM) Delivery

slide-30
SLIDE 30

30

Tunnel Boring Machine (TBM) Delivery

slide-31
SLIDE 31

31

TBM Assembly

slide-32
SLIDE 32

32

TBM into the Shed

slide-33
SLIDE 33

33

TBM into the Shed

slide-34
SLIDE 34

34

TBM lowered into the launch adit

slide-35
SLIDE 35

35

TBM lowered into the launch adit

slide-36
SLIDE 36

36

TBM lowered into the launch adit

slide-37
SLIDE 37

37

TBM Gantries

slide-38
SLIDE 38

38

Conveyor System Install

slide-39
SLIDE 39

39

Conveyor System Install

slide-40
SLIDE 40

40

Kirtli tling Street eet prog

  • gram

ramme me

slide-41
SLIDE 41

41

Kirtli tling Street eet prog

  • gram

ramme me

slide-42
SLIDE 42

42

Kirtling Street Programme

  • From Mid June
  • Complete shaft to depth.
  • Install conveyor.
  • July
  • Complete conveyor.
  • Construct shaft base.
  • Install Segment gantry crane.
  • August
  • Construct shaft bottom ring beam.
  • Assemble Water Treatment Plant
  • Assemble Grout Plant
  • September
  • Begin tunnelling
slide-43
SLIDE 43

43

AIR QUALITY

REPORTING

slide-44
SLIDE 44

44

Air Quality Monitor Exceedances

  • Heathwall Monitor Locations
slide-45
SLIDE 45

45

Air Quality Monitor Exceedances

  • Kirtling Monitor Locations
slide-46
SLIDE 46

46

Air Quality Monitor Exceedances - Kirtling

  • 23/02/18 & 14/04/18
  • Caused by number of large items of plant on site restricting access for our
  • Roadsweeper. Damping down is also carried out.
  • 21/04/18
  • Exceedance caused by timber works underneath dust monitor to provide

formwork/shuttering for a concrete slab pour.

Air Quality Monitor Exceedances - Heathwall

  • None
slide-47
SLIDE 47

47

NOISE

REPORTING

slide-48
SLIDE 48

48

Noise Monitor Exceedances

  • Heathwall Monitor Locations
slide-49
SLIDE 49

49

Noise Monitoring Exceedances

  • Monitor Locations
slide-50
SLIDE 50

50

Noise Monitoring Exceedances - Heathwall

  • None

Noise Monitoring Exceedances - Kirtling

  • 02/06/2018 @ 19:00 & 07/02/2018 @ 19:45
  • Movement of the SPMTs (Self Propelled Mobile Transports) carrying
  • TBMs. On both occasions the SPMTs have been required to remain

active in the area in front of the noise monitor

slide-51
SLIDE 51

51

COMMUNITY ENGAGEMENT

CAROLINE BRENNAN

slide-52
SLIDE 52

52

Issues

Complaints & Enquiries register February - June 2018

Noise 12 Light 13 Other 4

slide-53
SLIDE 53

53

Community Survey

  • 0.5% surveys were returned
  • 64% of respondents felt we were performing better or as expected

than their expectations. 24% who felt it was worse than expected.

  • 40% felt that the site and contractors had been considerate, whilst

28% felt that we had not been considerate with 24% being undecided

  • 44% of respondents either agreed or strongly agreed that they

thought we were being considerate neighbours during the construction process, with 24% disagreeing

  • 93% of respondents who had received information about our site and

activities found it either ‘very useful’ or ‘fairly useful’

slide-54
SLIDE 54

54

Community Survey

Doing well

Communication Keeping noise to a minimum Communication and tidiness Things are better now, less traffic coming down Kirtling Street so thank you for improving that Minimising disruption Updates Communication is excellent. Site traffic is managed well

slide-55
SLIDE 55

55

Community Survey

Room for improvement Changes made

Digging earth at 3am in the morning. It keeps me awake. I thought there was a 10pm cut off time Several changes made to the barge loading operation (as discussed) Noise, especially during the night Night noise due to barge loading operations considerably reduced following mitigation measures Bus stop cleanliness Dedicated road sweepers clean every day Stop the noise at night after 11pm Changes made, as above Not enough information to put forward a view Proposal to change survey to capture distance from site. Info Sheets hand delivered to wider radius The construction level of noise across the water is unacceptable. Concerns from north of the river due to barge loading

  • perations, mitigated as discussed

The roads around the site are dusty and feel unsafe with the amount of HGVs, but I realise these are also from other sites nearby. Would like more communications. Strict logistics procedure limiting delivery times, numbers, no idling, vehicle routes etc Struggle in to cope with upwards light pollution. Security lighting needs to be downwards only and we have been promised hoods for the strip lights and trialled various blackout blinds but don’t solve the issue Security continue to implement blackout blinds on evening shifts and angle lights downward Working to a tighter, definite schedule Follow schedule as tightly as possible more communications with upcoming works and progress

  • Parking. Workers who are waiting to be picked up and leave a lot of

rubbish around where they are waiting Site workers know not to wait or idle. Travel survey undertaken, share results next session The main thing is the noise from the rubble landing as it drops from the conveyor belt on to the barge Potentially work from another site OR barge loading operation which was mitigated

slide-56
SLIDE 56

56

Community Investment

  • Series of foreshore clean-ups in Battersea

with Thames21

  • Community Open Day at Kirtling Street with
  • ver 700 visitors
  • Ongoing school workshops trialling the

Virtual Reality TBM

  • Supporting the Royal Wedding celebrations

at the ROSE Clubroom with refreshments, tumblers and picnic bench donation

  • Funding and decorating for new Family

Room at Falconbrook Primary School

slide-57
SLIDE 57

57

UPCOMING ACTIVITIES

  • Full summer of work experience placements June – August
  • Further litter clean-ups taking place in June at St Mary’s Foreshore
  • Proposed donation of plants from a gardening show to World’s End,

ROSE Centre and Falconbrook Primary School

  • Graduation and Celebration Event with Sprial and Students from Brixton

UTC

  • Invitation for event to mark International Women in Engineering day for

Wandsworth students

  • Careers workshop with Drive Forward Foundation (young care leavers)
  • BIG BANK Fair South (Sutton)
slide-58
SLIDE 58

COMMUNITY INVESTMENT 2018

5

1932 1932

687 687 40 40

slide-59
SLIDE 59

59

Other Items

Justin Feltham – Environmental Advisor

slide-60
SLIDE 60

60

Notifications

  • 02/02 – Working Hours at KRTST (crane assembly)
  • 07/02 – Crane Testing at KRTST
  • 22/02 – Unloading at Brooks Court
  • 09/03 – Barge Loading at KRTST
  • 15/03 – Nine Elms Lane crossing for HEAPS
  • 09/04 – Tideway and Thames21 Event
  • 10/04 – Postponement of April CLWG
  • 19/04 – Installation of Telestacker at KRTST
  • 20/04 – Marine Works at HEAPS
  • 01/05 – Tideway Open Day at KRTST
  • 18/05 – TBM Lowering Prep at KRTST
  • 25/05 – Invite to June CLWG for KRTST and HEAPS
  • 30/05 – Update on barge Loading at KRTST
slide-61
SLIDE 61

61

Greenwall

  • Greenwall
  • 3 Iterations of the Greenwall plan
  • Developed a plan to meet all objectives
  • Trees for Cities
  • Ivy screen set in oak planters.
  • Screens and planters will be reused in Schools under ‘Edible Schools

Programme’

  • We hope to begin installation for Clean Air Day 21/06/18.
slide-62
SLIDE 62

62

Greenwall

slide-63
SLIDE 63

63

Settlement

  • Settlement assessment carried. Concludes no impact to Nine Elms

Pier structure from settlement caused by tunnelling.

  • Install and monitor InM equipment (appropriate notice).
  • Monitoring per day.
  • If monitoring picks up settlement outside of predicted range it will be

investigated.

slide-64
SLIDE 64

64

QUESTIONS?