tideway community liaison working group
play

Tideway Community Liaison Working Group Heathwall Pumping Station - PowerPoint PPT Presentation

Tideway Community Liaison Working Group Heathwall Pumping Station Kirtling Street Tunnels 1 Agenda Tideway Central Project Overview if required Heathwall Site Progress and Programme Kirtling Street Site Progress and Programme


  1. Tideway Community Liaison Working Group Heathwall Pumping Station Kirtling Street Tunnels 1

  2. Agenda • Tideway Central Project Overview – if required • Heathwall Site Progress and Programme • Kirtling Street Site Progress and Programme • Site Air Quality and Noise Data – shortened • Community Relations • Other items / Actions from Last Meeting - Notifications - Greenwall - Settlement 2

  3. Tideway Central – Project Overview Justin in Feltham ham – Environment ironmental al Ad Adviser iser 3

  4. Bazalgette’s interceptor sewers 4

  5. 5

  6. Project Overview • Heathwall Pumping Station - Existing Combined Sewer Outfall into Thames. - Diversion of existing CSO to allow it to operate while we work. - Construction of cofferdam and placement of infill material to construct interception chamber and shaft. - Construction of CSO Shaft to connect new Tunnel. • Kirtling Street - Drive site for construction of tunnel - Services and materials for TBM. - Removal of excavated material from TBM. 6

  7. HEATHWALL PUMPING STATION UPDATE Nick k Rowlan wland d – Marine ine Works ks Sub Agent ent Landside Works and Marine Works 7

  8. Heathwall Pumping Station Works SWSR Existing Air-Treatment Chamber CSO Shaft Pumping Chamber Station Main Tunnel PS Chamber PS Shaft 8

  9. Works to date • Diversion of existing Pumping Station Outfall to new location to allow us to construct our cofferdam. • Construction of UKPN Substation for HEAPS operation. • Installation of ground water wells and pump test. 9

  10. Marine Works • Ongoing – clearance of marine pile locations 10

  11. Marine Works – High Water Looking West 11

  12. Marine Works – High Water Looking East 12

  13. Marine Works – Low Water Looking West 13

  14. Marine Works – Low Water Looking East 14

  15. Marine Works • Piles delivered by river – next week • Vibro piling undertaken during core working hours 08:00 – 18:00 • Impact Piling 5 hours per day – 20 hours per Week • Noise Monitoring ongoing 15

  16. Marine Works – Interception Shaft Excavation 16

  17. Heathwall Final Layout 17

  18. Heathwall Street Programme • From Mid to Late June - Complete pile line clearance, pump station outfall demolition activity - Begin installation of cofferdam. • July & August - Continuation of cofferdam installation - Piling for landside CSO Shaft and chambers 18

  19. KIRTLING STREET RECENT WORKS Al Alber erto to Gonzal nzalez ez – Civi vils ls Work rks s Site Agent nt Drive Shaft and Tunnel Boring Machine Launch Adits 19

  20. We have a shaft 20

  21. Launch Adit Construction 21

  22. Launch Adit Construction 22

  23. Breaking Out D-Wall 23

  24. Ground-borne Vibration 24

  25. Building an adit 25

  26. Building an adit 26

  27. Building an adit 27

  28. KIRTLING STREET RECENT WORKS Russell ssell Brown wn – Tunnel nnel Senior nior Projec oject t Manager ager Tunnel Boring Machine, Gantries and Conveyor 28

  29. Tunnel Boring Machine (TBM) Delivery 29

  30. Tunnel Boring Machine (TBM) Delivery 30

  31. TBM Assembly 31

  32. TBM into the Shed 32

  33. TBM into the Shed 33

  34. TBM lowered into the launch adit 34

  35. TBM lowered into the launch adit 35

  36. TBM lowered into the launch adit 36

  37. TBM Gantries 37

  38. Conveyor System Install 38

  39. Conveyor System Install 39

  40. Kirtli tling Street eet prog ogram ramme me 40

  41. Kirtli tling Street eet prog ogram ramme me 41

  42. Kirtling Street Programme • From Mid June - Complete shaft to depth. - Install conveyor. • July - Complete conveyor. - Construct shaft base. - Install Segment gantry crane. • August - Construct shaft bottom ring beam. - Assemble Water Treatment Plant - Assemble Grout Plant • September - Begin tunnelling 42

  43. AIR QUALITY REPORTING 43

  44. Air Quality Monitor Exceedances • Heathwall Monitor Locations 44

  45. Air Quality Monitor Exceedances • Kirtling Monitor Locations 45

  46. Air Quality Monitor Exceedances - Heathwall • None Air Quality Monitor Exceedances - Kirtling • 23/02/18 & 14/04/18 - Caused by number of large items of plant on site restricting access for our Roadsweeper. Damping down is also carried out. • 21/04/18 - Exceedance caused by timber works underneath dust monitor to provide formwork/shuttering for a concrete slab pour. 46

  47. NOISE REPORTING 47

  48. Noise Monitor Exceedances • Heathwall Monitor Locations 48

  49. Noise Monitoring Exceedances • Monitor Locations 49

  50. Noise Monitoring Exceedances - Heathwall • None Noise Monitoring Exceedances - Kirtling • 02/06/2018 @ 19:00 & 07/02/2018 @ 19:45 - Movement of the SPMTs (Self Propelled Mobile Transports) carrying TBMs. On both occasions the SPMTs have been required to remain active in the area in front of the noise monitor 50

  51. COMMUNITY ENGAGEMENT CAROLINE BRENNAN 51

  52. Issues Complaints & Enquiries register February - June 2018 Noise 12 Light 13 Other 4 52

  53. Community Survey • 0.5% surveys were returned • 64% of respondents felt we were performing better or as expected than their expectations. 24% who felt it was worse than expected. • 40% felt that the site and contractors had been considerate, whilst 28% felt that we had not been considerate with 24% being undecided • 44% of respondents either agreed or strongly agreed that they thought we were being considerate neighbours during the construction process, with 24% disagreeing • 93% of respondents who had received information about our site and activities found it either ‘very useful’ or ‘fairly useful’ 53

  54. Community Survey Doing well Communication Keeping noise to a minimum Communication and tidiness Things are better now, less traffic coming down Kirtling Street so thank you for improving that Minimising disruption Updates Communication is excellent. Site traffic is managed well 54

  55. Community Survey Room for improvement Changes made Digging earth at 3am in the morning. It keeps me awake. I thought Several changes made to the barge loading operation (as there was a 10pm cut off time discussed) Noise, especially during the night Night noise due to barge loading operations considerably reduced following mitigation measures Bus stop cleanliness Dedicated road sweepers clean every day Stop the noise at night after 11pm Changes made, as above Not enough information to put forward a view Proposal to change survey to capture distance from site. Info Sheets hand delivered to wider radius The construction level of noise across the water is unacceptable. Concerns from north of the river due to barge loading operations, mitigated as discussed The roads around the site are dusty and feel unsafe with the amount of Strict logistics procedure limiting delivery times, numbers, no HGVs, but I realise these are also from other sites nearby. Would like idling, vehicle routes etc more communications. Struggle in to cope with upwards light pollution. Security lighting needs Security continue to implement blackout blinds on evening to be downwards only and we have been promised hoods for the strip shifts and angle lights downward lights and trialled various blackout blinds but don’t solve the issue Working to a tighter, definite schedule Follow schedule as tightly as possible more communications with upcoming works and progress Parking. Workers who are waiting to be picked up and leave a lot of Site workers know not to wait or idle. Travel survey rubbish around where they are waiting undertaken, share results next session The main thing is the noise from the rubble landing as it drops from the Potentially work from another site OR barge loading operation conveyor belt on to the barge which was mitigated 55

  56. Community Investment • Series of foreshore clean-ups in Battersea with Thames21 • Community Open Day at Kirtling Street with over 700 visitors • Ongoing school workshops trialling the Virtual Reality TBM • Supporting the Royal Wedding celebrations at the ROSE Clubroom with refreshments, tumblers and picnic bench donation • Funding and decorating for new Family Room at Falconbrook Primary School 56

  57. UPCOMING ACTIVITIES • Full summer of work experience placements June – August • Further litter clean- ups taking place in June at St Mary’s Foreshore • Proposed donation of plants from a gardening show to World’s End, ROSE Centre and Falconbrook Primary School • Graduation and Celebration Event with Sprial and Students from Brixton UTC • Invitation for event to mark International Women in Engineering day for Wandsworth students • Careers workshop with Drive Forward Foundation (young care leavers) • BIG BANK Fair South (Sutton) 57

  58. COMMUNITY INVESTMENT 2018 1932 1932 5 687 687 40 40

  59. Other Items Justin Feltham – Environmental Advisor 59

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend