1
Tideway Community Liaison Working Group Heathwall Pumping Station - - PowerPoint PPT Presentation
Tideway Community Liaison Working Group Heathwall Pumping Station - - PowerPoint PPT Presentation
Tideway Community Liaison Working Group Heathwall Pumping Station Kirtling Street Tunnels 1 Agenda Tideway Central Project Overview if required Heathwall Site Progress and Programme Kirtling Street Site Progress and Programme
2
Agenda
- Tideway Central Project Overview – if required
- Heathwall Site Progress and Programme
- Kirtling Street Site Progress and Programme
- Site Air Quality and Noise Data – shortened
- Community Relations
- Other items / Actions from Last Meeting
- Notifications
- Greenwall
- Settlement
3
Tideway Central – Project Overview
Justin in Feltham ham – Environment ironmental al Ad Adviser iser
4
Bazalgette’s interceptor sewers
5
6
Project Overview
- Heathwall Pumping Station
- Existing Combined Sewer Outfall into Thames.
- Diversion of existing CSO to allow it to operate while we work.
- Construction of cofferdam and placement of infill material to construct
interception chamber and shaft.
- Construction of CSO Shaft to connect new Tunnel.
- Kirtling Street
- Drive site for construction of tunnel
- Services and materials for TBM.
- Removal of excavated material from TBM.
7
HEATHWALL PUMPING STATION UPDATE
Nick k Rowlan wland d – Marine ine Works ks Sub Agent ent Landside Works and Marine Works
8
Heathwall Pumping Station Works
Main Tunnel Existing Pumping Station PS Shaft PS Chamber CSO Shaft Air-Treatment Chamber SWSR Chamber
9
- Diversion of existing Pumping Station Outfall to new location to allow
us to construct our cofferdam.
- Construction of UKPN Substation for HEAPS operation.
- Installation of ground water wells and pump test.
Works to date
10
- Ongoing – clearance of
marine pile locations
Marine Works
11
Marine Works – High Water Looking West
12
Marine Works – High Water Looking East
13
Marine Works – Low Water Looking West
14
Marine Works – Low Water Looking East
15
Marine Works
- Piles delivered by river – next week
- Vibro piling undertaken during core working hours 08:00 – 18:00
- Impact Piling 5 hours per day – 20 hours per Week
- Noise Monitoring ongoing
16
Marine Works – Interception Shaft Excavation
17
Heathwall Final Layout
18
Heathwall Street Programme
- From Mid to Late June
- Complete pile line clearance, pump station outfall demolition activity
- Begin installation of cofferdam.
- July & August
- Continuation of cofferdam installation
- Piling for landside CSO Shaft and chambers
19
KIRTLING STREET RECENT WORKS
Al Alber erto to Gonzal nzalez ez – Civi vils ls Work rks s Site Agent nt Drive Shaft and Tunnel Boring Machine Launch Adits
20
We have a shaft
21
Launch Adit Construction
22
Launch Adit Construction
23
Breaking Out D-Wall
24
Ground-borne Vibration
25
Building an adit
26
Building an adit
27
Building an adit
28
KIRTLING STREET RECENT WORKS
Russell ssell Brown wn – Tunnel nnel Senior nior Projec
- ject
t Manager ager Tunnel Boring Machine, Gantries and Conveyor
29
Tunnel Boring Machine (TBM) Delivery
30
Tunnel Boring Machine (TBM) Delivery
31
TBM Assembly
32
TBM into the Shed
33
TBM into the Shed
34
TBM lowered into the launch adit
35
TBM lowered into the launch adit
36
TBM lowered into the launch adit
37
TBM Gantries
38
Conveyor System Install
39
Conveyor System Install
40
Kirtli tling Street eet prog
- gram
ramme me
41
Kirtli tling Street eet prog
- gram
ramme me
42
Kirtling Street Programme
- From Mid June
- Complete shaft to depth.
- Install conveyor.
- July
- Complete conveyor.
- Construct shaft base.
- Install Segment gantry crane.
- August
- Construct shaft bottom ring beam.
- Assemble Water Treatment Plant
- Assemble Grout Plant
- September
- Begin tunnelling
43
AIR QUALITY
REPORTING
44
Air Quality Monitor Exceedances
- Heathwall Monitor Locations
45
Air Quality Monitor Exceedances
- Kirtling Monitor Locations
46
Air Quality Monitor Exceedances - Kirtling
- 23/02/18 & 14/04/18
- Caused by number of large items of plant on site restricting access for our
- Roadsweeper. Damping down is also carried out.
- 21/04/18
- Exceedance caused by timber works underneath dust monitor to provide
formwork/shuttering for a concrete slab pour.
Air Quality Monitor Exceedances - Heathwall
- None
47
NOISE
REPORTING
48
Noise Monitor Exceedances
- Heathwall Monitor Locations
49
Noise Monitoring Exceedances
- Monitor Locations
50
Noise Monitoring Exceedances - Heathwall
- None
Noise Monitoring Exceedances - Kirtling
- 02/06/2018 @ 19:00 & 07/02/2018 @ 19:45
- Movement of the SPMTs (Self Propelled Mobile Transports) carrying
- TBMs. On both occasions the SPMTs have been required to remain
active in the area in front of the noise monitor
51
COMMUNITY ENGAGEMENT
CAROLINE BRENNAN
52
Issues
Complaints & Enquiries register February - June 2018
Noise 12 Light 13 Other 4
53
Community Survey
- 0.5% surveys were returned
- 64% of respondents felt we were performing better or as expected
than their expectations. 24% who felt it was worse than expected.
- 40% felt that the site and contractors had been considerate, whilst
28% felt that we had not been considerate with 24% being undecided
- 44% of respondents either agreed or strongly agreed that they
thought we were being considerate neighbours during the construction process, with 24% disagreeing
- 93% of respondents who had received information about our site and
activities found it either ‘very useful’ or ‘fairly useful’
54
Community Survey
Doing well
Communication Keeping noise to a minimum Communication and tidiness Things are better now, less traffic coming down Kirtling Street so thank you for improving that Minimising disruption Updates Communication is excellent. Site traffic is managed well
55
Community Survey
Room for improvement Changes made
Digging earth at 3am in the morning. It keeps me awake. I thought there was a 10pm cut off time Several changes made to the barge loading operation (as discussed) Noise, especially during the night Night noise due to barge loading operations considerably reduced following mitigation measures Bus stop cleanliness Dedicated road sweepers clean every day Stop the noise at night after 11pm Changes made, as above Not enough information to put forward a view Proposal to change survey to capture distance from site. Info Sheets hand delivered to wider radius The construction level of noise across the water is unacceptable. Concerns from north of the river due to barge loading
- perations, mitigated as discussed
The roads around the site are dusty and feel unsafe with the amount of HGVs, but I realise these are also from other sites nearby. Would like more communications. Strict logistics procedure limiting delivery times, numbers, no idling, vehicle routes etc Struggle in to cope with upwards light pollution. Security lighting needs to be downwards only and we have been promised hoods for the strip lights and trialled various blackout blinds but don’t solve the issue Security continue to implement blackout blinds on evening shifts and angle lights downward Working to a tighter, definite schedule Follow schedule as tightly as possible more communications with upcoming works and progress
- Parking. Workers who are waiting to be picked up and leave a lot of
rubbish around where they are waiting Site workers know not to wait or idle. Travel survey undertaken, share results next session The main thing is the noise from the rubble landing as it drops from the conveyor belt on to the barge Potentially work from another site OR barge loading operation which was mitigated
56
Community Investment
- Series of foreshore clean-ups in Battersea
with Thames21
- Community Open Day at Kirtling Street with
- ver 700 visitors
- Ongoing school workshops trialling the
Virtual Reality TBM
- Supporting the Royal Wedding celebrations
at the ROSE Clubroom with refreshments, tumblers and picnic bench donation
- Funding and decorating for new Family
Room at Falconbrook Primary School
57
UPCOMING ACTIVITIES
- Full summer of work experience placements June – August
- Further litter clean-ups taking place in June at St Mary’s Foreshore
- Proposed donation of plants from a gardening show to World’s End,
ROSE Centre and Falconbrook Primary School
- Graduation and Celebration Event with Sprial and Students from Brixton
UTC
- Invitation for event to mark International Women in Engineering day for
Wandsworth students
- Careers workshop with Drive Forward Foundation (young care leavers)
- BIG BANK Fair South (Sutton)
COMMUNITY INVESTMENT 2018
5
1932 1932
687 687 40 40
59
Other Items
Justin Feltham – Environmental Advisor
60
Notifications
- 02/02 – Working Hours at KRTST (crane assembly)
- 07/02 – Crane Testing at KRTST
- 22/02 – Unloading at Brooks Court
- 09/03 – Barge Loading at KRTST
- 15/03 – Nine Elms Lane crossing for HEAPS
- 09/04 – Tideway and Thames21 Event
- 10/04 – Postponement of April CLWG
- 19/04 – Installation of Telestacker at KRTST
- 20/04 – Marine Works at HEAPS
- 01/05 – Tideway Open Day at KRTST
- 18/05 – TBM Lowering Prep at KRTST
- 25/05 – Invite to June CLWG for KRTST and HEAPS
- 30/05 – Update on barge Loading at KRTST
61
Greenwall
- Greenwall
- 3 Iterations of the Greenwall plan
- Developed a plan to meet all objectives
- Trees for Cities
- Ivy screen set in oak planters.
- Screens and planters will be reused in Schools under ‘Edible Schools
Programme’
- We hope to begin installation for Clean Air Day 21/06/18.
62
Greenwall
63
Settlement
- Settlement assessment carried. Concludes no impact to Nine Elms
Pier structure from settlement caused by tunnelling.
- Install and monitor InM equipment (appropriate notice).
- Monitoring per day.
- If monitoring picks up settlement outside of predicted range it will be
investigated.
64