King Edward Memorial Park Foreshore Community Liaison Working Group 19 September 2018
King Edward Memorial Park Foreshore Community Liaison Working Group - - PowerPoint PPT Presentation
King Edward Memorial Park Foreshore Community Liaison Working Group - - PowerPoint PPT Presentation
King Edward Memorial Park Foreshore Community Liaison Working Group 19 September 2018 Staff present at the CLWG Tideway Jeff Alchin Tideway Mike Appleton Communications Manager CVB Charlie Lout Site Manager Dominic
2
Staff present at the CLWG Tideway
- Jeff Alchin
Tideway
- Mike Appleton
Communications Manager
CVB
- Charlie Louët
Site Manager
- Dominic
Lovelock Deputy Site Manager
- June Saunders
Community Relations Officer
- Breffni Quinlivan
Environmental Manager
3
CONTENTS
Environmental update (noise and air quality) Legacy and Community Progress report Upcoming works
4
Environmental
5
Noise & e & Ai Air Qu Quali lity
No exceedances - June, July, August 2018
KEMPF/AA/1
KEMPF/AA/2
Continuous air quality monitoring location Long-term unattended noise monitoring location
6
Legacy and Community Relations
7
Volunteering and Charity
Money raised from the event went towards Tideway’s three staff charities, as well as the Shadwell Basin Outdoor Activity Centre, which gets young people from some of the most disadvantaged communities in London onto the river every year
8
In June, as part of Women in Engineering Week 2018, Tower Hamlets Guides and Brownies visited Chambers Wharf, and we visited a Brownie Pack in Bow The girls learnt that women can make a positive impact in engineering and construction - as well as taking part in some fun tasks After a quick talk about engineering and the Tideway project, the girls got stuck into lots
- f activities, to get them thinking like
engineers. These included building spaghetti and marshmallow towers, balloon hovercrafts, lava lamps and making lemon fizz volcanoes And of course a challenge to ‘raise the bar’ which was this year’s theme
Women in Engineering 2018
#raisethebar
9
RIVE VER T TIMES – Summe mer E Editio ition
A digital copy of this publication can be found at https://www.tideway.london/media/4081/river-times_east_summer_18.pdf
10
Next Ge Gene neratio ion of
- f Eng
ngine neerin ing
- World of Work visit from students
taking part in the National Citizen Service summer programme ‘The Challenge’
- They were working on a project to
raise money for charity tackling domestic violence
- They practised their Dragon’s Den
style presentation with us.
Appren entic ices eships ips
- Three new civil engineering apprentices have
joined our team
- Two are from Newham, one recently finished
studying at the London Design Engineering UTC
- Two are studying degree level 6 qualifications
Work e exper erien ience
- Four work experience students with us over the
Summer.
- Two from the St Michael's College, one from
Walworth Academy and one from East Young Leaders Academy (EYLA) Here’s some of their feedback:
“Thanks to my work experience I have been able to develop a wide range of skills, including working as part of a team, listening and
- rganisation. It's also helped boost my confidence.”
“Getting a feel of engineering at Tideway has really encouraged me to go on and work in engineering.” “Engineering is now definitely an option for my future.”
11
Foresh shor
- re
e Cl Clean-up p King Edward M rd Memori
- rial F
Fore reshore
- re S
Site
- Tideway East volunteers headed down to the foreshore in July to clean up plastic
rubbish
- The team made a great effort and were able to collect many bags full of plastic
- This waste is taken away and properly disposed
Plastic is a hazardous material polluting our waterways It’s putting wildlife at risk, harming and in some cases mutating aquatic life
12
Foresh shor
- re c
e clean an-up o p on th the I e Isl sle e of D Dogs s
Staff volunteers, accompanied by the neighbouring Ecology Consultancy, based at Bermondsey Wall West, took to the Isle of Dogs foreshore to remove plastic waste embedded within its beach. Within the fifty bags of plastic rubbish collected they found a bag of Smiths salted peanuts with an expiry date of January 1984 - Which makes them 34 years old!
Newcastle Draw Dock - August 2018
13
More information can be found at: https://www.tideway.london/our-community/foreshore-festival/Shadwell-Activities
14
Tideway 20 2017/1 7/18 A 8 Annual al R Repo eport
Significant progress has been made on the project over the last 12 months and much of it is captured in Tideway’s 2017/18 Annual Report. In the year to 31 March 2018, we hit some key milestones, with all but one of our 21 construction sites up and running, the completion of the first shafts and the welcoming of three of our six TBMs. The report highlights Tideway’s commitment to use the river and cut the number of lorries needed for the project – with nearly 420,000 tonnes of material moved by barge to date and more than 20,000 lorry loads avoided.
Report can be found at: https://www.tideway.london/media/4029/tideway-annual_report_2017-18.pdf
15
Th Than ank y k you
- u
Any questions please contact the Tideway Helpdesk on: Telephone: 08000 3 00 308080 080 Email: Helpdesk@Tideway.London
16
Progress report
17
TIDEWAY TIME LAPSE FILM – JULY 2018
New d w diver ersion s sheet eet pi piles es n now co w compl plete
August 2018
Cofferd rdam s strengthe hening w works ks o
- ngoi
- ing
Rei einforce ced co concr crete pi piles es
August 2018
Pi Piles a are brok broken n do down re ready for for con concrete slab a b and c concre
- ncrete b
beams
August 2018
Pi Piles a are brok broken n do down re ready for for con concrete slab a b and c concre
- ncrete beam
eams
August 2018
Water er m main laid d throu rough p h park rk
August 2018
June 2 2018
June 2 2018
June 2 2018
26
Upcoming work
27
Upcomin ing w work rks
- Cofferdam strengthening works:
- Concrete piles in cofferdam to finish in October
- Concrete beams tying the piles together ongoing until November.
These works are tidally affected
- Concrete piles on landside in October. A concrete slab will be built
- n top to support silos being delivered in November for ground
improvement works to the main area of the cofferdam
- Concrete slab to be built within the North East Storm Relief Sewer
- diversion. These works are tidally affected and scheduled to start
in October
- Ground improvement works in November for approximately 4 to 6
- months. This will be deep soil mixing: a rig is used to auger down
into the ground and inject and mix grout to improve the ground characteristics
28
Upcoming works (plan view)
29
Install cofferdam Relieving platform Additional Sheet Piles Prepare cofferdam platform Diaphragm Walls Excavate shaft Build Shaft Hydraulic Structures Connect into Sewer Remove cofferdam Moving parts and tests Landscaping
2022
Q1 Q2 Q3
2018 2019 2020
Q2 Q3 Q4 Q1 Q2 Q3 Q4
2021
Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1
Progr gram amme
Building of slab is tidally affected Extended hours for long pours / Removal of spoil tidally affected Extended hours for long pours Removal tidally affected Removal of spoil tidally affected
Cofferdam platform preparation now includes a scope of ground improvement works
30
QUESTIONS?
31
THANK YOU
King Edward Memorial Park Foreshore Community Liaison Working Group 19 September 2018
34
Women in Engineering 2018
#raisethebar
In June, as part of Women in Engineering Week 2018, Tower Hamlets Guides and Brownies visited Chambers Wharf, and we visited a Brownie pack in Bow. The girls learnt that women can make a positive impact in Engineering and Construction - as well as taking part in some fun tasks. After a quick talk about engineering and the Tideway project, the girls got stuck into lots
- f activities, to get them thinking like
engineers. These included building spaghetti and marshmallow towers, balloon hovercrafts, lava lamps and lemon fizz volcanoes. And of course a challenge to ‘raise the bar’
35
Volunteering and Charity
Money raised from the event went towards Tideway’s three staff charities, as well as the Shadwell Basin Outdoor Activity Centre, which gets young people from some of the most disadvantaged communities in London onto the river every year.