Community Working Liaison Group Putney Embankment Foreshore & Barn Elms Thursday 1 12 M March Welcome 2 Putney Embankment Foreshore David Miles Tideway Project Manager Putney Embankment Foreshore The Putney Scheme overview Our
2
Welcome
Putney Embankment Foreshore
David Miles Tideway Project Manager – Putney Embankment Foreshore
The Putney Scheme overview
Our site setup
Current progress
Our recent milestones:
- Shaft excavation complete
- High level tunnel complete
- Low level tunnel commenced
- Bridge vaults works complete
What we’ve been up to…
What we’ve been up to…
Current progress
Current progress
Current progress
Putney Embankment Foreshore - Timeline
May ‘20 July ‘20 Dec ‘ 20 Winter ‘22 Spring ‘22 Late Spring ‘22 Early Spring ‘21 MEICA installation and landscaping
Long Term Short Term
April ‘20 June ‘20 2023/24
Putney’s legacy
Looking forward…
Occasional road closures
- Change to overall works
method, using larger barges, has resulted in fewer barge movements on the river
- Each barge movement
equates to approximately 50 HGV’s removed from the local road network
- Since October we have had
19 barges arrive at Putney Embankment Foreshore, keeping approximately 950 lorries off the road
Putney Embankment Foreshore
More by river
Boat Races
As we have every year since site establishment at Putney, Tideway lays down its tools to accommodate the boat races that utilise the Boat Race Stone. Those races for 2020 are:
- The Men’s Head of the River Race on
Saturday 21 March
- The University Boat Race on Sunday 29
March
Putney Embankment Foreshore Questions?
Barn Elms
Bhavini Vyas
Tideway Project Manager Barn Elms
Overview
Main Worksite Overview – Design, Planning & Construction
Main Worksite Overview – Design, Planning & Construction
Completion of Shaft
Completion of Thrust & Portal Walls
Tunnel Eye Breakthrough & Front Shunt
Pipe-Jacking set-up
Commenced Pipe-Jack Tunnel
Upcoming Works
- Continue & complete pipe-jack
connection tunnel (213m ‘short connection tunnel’ to main tunnel)
- Complete installation of flume for
CSO pipe
- Commence construction of
hydraulic structures
Future Works
- Complete secondary lining of connection tunnel and shaft
Barn Elms Questions?
30
Community Engagement
Katie Ashton
Community Engagement
Legacy since 2016 London Borough
- f Wandsworth
Putney & Barnes Elms Support Community Investment Hours 1,507 hours 821 hours STEM Hours 418 163 Work experience placement 5 placements 3 placements Summer placements 7 placements 5 placements Schools engaged 9 3 Apprentices 5 4
Helpdesk
Call: 08000 30 80 80 Email: helpdesk@tideway.london Write to: Freepost TIDEWAY Helpdesk have received 3 complaints enquiry linked to our schemes at Putney Embankment Foreshore and Barn Elms
How to make a claim if you are affected by Tideway’s work
Who do I go to for advice? Independent Advisory Service (IAS) Helpline for independent advice: 0800 917 8845 or info@tidewayias.co.uk Tideway’s Mitigation and Compensation Lead, Louise Walsh, for personal assistance and advice via Tideway’s Helpdesk 08000 30 80 80 or helpdesk@tideway.london or direct 07971 077165 or louise.walsh@tideway.london How do I submit my claim? Louise can submit your claim to the Independent Compensation Panel (ICP) on your behalf, or you can submit your claim direct to the ICP: admin@tidewayicp.london The IAS can send you a claim form, or you can download it from the Tideway website: www.tideway.london/help-advice/compensation- information/Independent-Compensation-Panel
34
Communication channels
Regular site visits Quarterly publication delivered to 14,000 neighbours Monthly update on the progress of the tunnelling for both our TBM’s Information events for community
35
Communication channels
Special event notifications Community presentations Community Information Centre at our Carnwath Road site Information events for community – Tideway Boat Tours
How to stay up to date @TidewayLondon
www.linkedin.com/company/tideway-london/ twitter.com/TidewayLondon www.instagram.com/tidewaylondon/ en-gb.facebook.com/TidewayLondon/
37
Project wide update
Andeep Gehlot – Tideway Communications Lead (West)
Where is Rachel?
The Tideway TBM tracker: www.tideway.london/tbm-tracker
40
Project update
Click here to watch our latest project update: https://vimeo.com/395756908/1cc39989b1
41