A160 Port of Immingham Improvement Scheme Feb 2017 Craig Snow - - PowerPoint PPT Presentation

a160 port of immingham improvement scheme
SMART_READER_LITE
LIVE PREVIEW

A160 Port of Immingham Improvement Scheme Feb 2017 Craig Snow - - PowerPoint PPT Presentation

A160 Port of Immingham Improvement Scheme Feb 2017 Craig Snow Costain Contract Lead Richard Pickup - Jacobs Engineering Manager Tiago Magalhaes Jacobs Geotech Site Representative Introduction to A160 Project Overview Health and


slide-1
SLIDE 1

A160 Port of Immingham Improvement Scheme Feb 2017

Craig Snow – Costain Contract Lead Richard Pickup - Jacobs Engineering Manager Tiago Magalhaes – Jacobs Geotech Site Representative

slide-2
SLIDE 2

Introduction to A160

  • Project Overview
  • Health and Safety
  • Project Delivery
  • Community and Society
  • BIM
  • Engineering Challenge
  • Geotechnical Challenges
  • Possession activities
slide-3
SLIDE 3

PROJECT OVERVIEW

slide-4
SLIDE 4

4

Project Overview

slide-5
SLIDE 5

HEALTH AND SAFETY

slide-6
SLIDE 6

1,200,000

Man-hours worked Full project to date without a reportable accident

SAFE WORKING

slide-7
SLIDE 7

Health and Safety

Environment Each other Empowerment

slide-8
SLIDE 8

PROJECT DELIVERY

slide-9
SLIDE 9

Statutory planning process

9
  • A160 Accelerated Delivery
  • Input
  • Prep Application
  • Legal Notices
  • Stats and Stakeholders
  • Represent at the Hearing

Planning Act 2008 Nationally Significant Infrastructure Project

slide-10
SLIDE 10

COMMUNITY AND SOCIETY IMPACT

slide-11
SLIDE 11

Community and Society

  • Deep water Estuary –Land

Development

  • STEM
slide-12
SLIDE 12

Community and Society

slide-13
SLIDE 13

BIM

slide-14
SLIDE 14

Technology – Early Adopter BIM

14

3D 6D 4D

slide-15
SLIDE 15
  • 3D/4D Sequencing and

Phasing Aerial Solutions – Digital Survey

Embrace Technology

slide-16
SLIDE 16

Technology – Early Adopter BIM

FME – Feature Manipulation Engine

slide-17
SLIDE 17

Interactive Stats Drawing

slide-18
SLIDE 18 18

4D Animation – Bridge Slide

slide-19
SLIDE 19

Longer Duration Planning

19
slide-20
SLIDE 20 20

4D Animation – Cofferdam Construction

slide-21
SLIDE 21

ENGINEERING CHALLENGE

BRIDGE SLIDE

slide-22
SLIDE 22

Bridge Slide

slide-23
SLIDE 23

Bridge Slide

slide-24
SLIDE 24

Bridge Slide

slide-25
SLIDE 25

25

Strand Jacks

slide-26
SLIDE 26

26

Catenary bridge

slide-27
SLIDE 27

27

Possession Planning

  • Temp Works
  • Staff planning
  • Works Package Plans
  • RAMS
  • ITP’s
  • Detail Planning
  • Logistics
  • QSRA
slide-28
SLIDE 28

28

Staff Planning

slide-29
SLIDE 29

29

Video 1 – Bridge Construction

slide-30
SLIDE 30

GEOTECHNICAL CHALLENGE

slide-31
SLIDE 31

31

Ground Conditions

  • Glacial Till
  • Potential for granular lenses
  • High groundwater level
slide-32
SLIDE 32

Ground Conditions Encountered – Soft Spots

  • Soft Spots – 5m x 4m and

10m x 3m

  • Groundwater at formation

level

  • Excavate and replace with

Class 6N Fill

slide-33
SLIDE 33

Ground Conditions Encountered – Instability of Excavation

  • Collapse of Excavation

Slopes

  • Bulk Fill – Telecomms Mast
  • Removal of loose material

and Class 6N backfill

slide-34
SLIDE 34

Ground Conditions Encountered - Mitigation

  • Monitoring Regime
  • 12No. Monitoring targets on bridge structure
  • 12No. Monitoring points on Backfill
slide-35
SLIDE 35

POSSESSION ACTIVITIES

slide-36
SLIDE 36

Lifting Rails

36
slide-37
SLIDE 37

Excavation

37
slide-38
SLIDE 38

Kingpost Wall Removal

38
slide-39
SLIDE 39

Kingpost Wall Removal

39
slide-40
SLIDE 40

Installation of Nosings & Final Trim

40
slide-41
SLIDE 41

Jacking Operation

41
slide-42
SLIDE 42

Strand Jacks

42
slide-43
SLIDE 43

Checking Alignment

43
slide-44
SLIDE 44

Backfill

44
slide-45
SLIDE 45

Backfill

45
slide-46
SLIDE 46

Track Replacement

46
slide-47
SLIDE 47

Tamping the Ballast

47
slide-48
SLIDE 48

Welding

48
slide-49
SLIDE 49

GO PRO

slide-50
SLIDE 50

THANK YOU