Tideway Central: Community Liaison Working Group 07/03/19 Heathwall - - PowerPoint PPT Presentation

tideway central community liaison working group 07 03 19
SMART_READER_LITE
LIVE PREVIEW

Tideway Central: Community Liaison Working Group 07/03/19 Heathwall - - PowerPoint PPT Presentation

Tideway Central: Community Liaison Working Group 07/03/19 Heathwall Pumping Station & Kirtling Street 1 Agenda Apologies Minutes of last meeting Heathwall site progress and programme Kirtling Street & Brooks Court site


slide-1
SLIDE 1

1

Tideway Central: Community Liaison Working Group 07/03/19

Heathwall Pumping Station & Kirtling Street

slide-2
SLIDE 2

2

Agenda

  • Apologies
  • Minutes of last meeting
  • Heathwall site progress and programme
  • Kirtling Street & Brooks Court site progress and programme
  • Environmental update
  • Community relations
  • AOB
slide-3
SLIDE 3

3

HEATHWALL PUMPING STATION UPDATE

Landside Works and Marine Works Ponciano ciano Perez ez Lu Lupi pi – Projec

  • ject

t Manager ager

slide-4
SLIDE 4

4

Heathwall Pumping Station overview

slide-5
SLIDE 5

5

Heathwall Pumping Station Progress

  • Marine:
  • New river wall construction complete
  • Tie-ins complete
  • Demolition of redundant sewer outfall complete
  • Backfill of cofferdam commenced
  • Landside:
  • Land piling works complete for future construction of SWSR interception

chamber

  • Upgrades to interface - signage
  • Removal of temporary working platform
  • Muck bay construction
  • Highways modifications commenced
slide-6
SLIDE 6

6

Heathwall Pumping Station Progress

slide-7
SLIDE 7

7

Heathwall lookahead

  • March:
  • Highways modification works to be finalised
  • Complete cofferdam backfilling
  • West entrance modification works
  • April:
  • Piling works for new river wall and pumping station interception chamber
  • Enabling works for combined sewer overflow shaft construction
  • May:
  • Piling works ongoing
  • Combined sewer overflow shaft sinking to commence
slide-8
SLIDE 8

8

KIRTLING STREET PROJECT UPDATE

Noel el Cooper per – Tunnel nnel Constru structi ction

  • n Ma

Manager ager

slide-9
SLIDE 9

9

Progress to date – March 2019

  • Site establishment for tunnelling operations – complete
  • ‘Umbilical’ launch of TBM B (westbound drive towards

Carnwath Road site) – complete

  • TBM Millicent has completed 500m on 04/03/19
  • Drive C ‘umbilical’ launch status (eastbound drive towards

Chambers Wharf site) Currently progressing with mechanical & electrical connections between TBM shield & gantries

  • Drive C (TBM Ursula) expected to commence tunnelling late

March

slide-10
SLIDE 10

10

TBM B (Millicent) Progress

slide-11
SLIDE 11

11

Shaft and inside acoustic shed

slide-12
SLIDE 12

12

View of segment pontoon & segment barge unloading

slide-13
SLIDE 13

13

View of Brooks Court muck-bay

slide-14
SLIDE 14

2018 2019 2020 2021 2022 2023

Complete shaft HEAPS Cofferdam structural elements complete Tunnel B excavation Tunnel C excavation Tunnel B secondary lining Tunnel C secondary lining Remove acoustic shed - site reinstatement Reinstate house boats Dynamic testing and opening

Tideway Central Programme

2024

slide-15
SLIDE 15

15

ENVIRONMENTAL UPDATE

Iram Mirza– Environmental Advisor

slide-16
SLIDE 16

16

Heathwall Pumping Station - Air Quality Monitor Exceedances

Dec 18 to 1 Mar 19 One FLo works exceedance

  • 1 Mar 19 – cutting tarmac

for West compound ramp (next to the monitor)

1 x exceedance No exceedances

reporting ceased Feb 19

No exceedances

slide-17
SLIDE 17

17

Heathwall Pumping Station - Noise Monitor Exceedances

No exceedances removed Nov 2018

26 Nov 18 to 17 Feb 19

  • No exceedances
slide-18
SLIDE 18

18

Kirtling Street - Air Quality Monitor Exceedances

Dec 18 to 1 Mar 19 None caused by FLo works Two non-FLo AQ exceedances

  • 18 Dec 18
  • 11 Jan 19

relocated No FLo exceedances No FLo exceedances

slide-19
SLIDE 19

19

Kirtling Street - Noise Monitor Exceedances

26 Nov 18 to 1 Mar 19 One related to FLo works

  • 4 Feb 19 -

Hydrocleanse Non-FLo noise exceedances

  • 9 Dec 18
  • 22 Dec 18
  • New Year celebrations
  • 7 Jan 19
  • 27 Jan 19

1 x FLo exceedance

slide-20
SLIDE 20

20

COMMUNITY ENGAGEMENT

Alick Whitfield – Community Relations Manager

slide-21
SLIDE 21

21

79% 11% 5% 5%

Kirtling Street Complaints Breakdown Noise Lighting Flooding Other

Complaints & Enquiries Summary December 2018 – February 2019 Kirtling Street and Heathwall Pumping Station

84% 5% 11%

Kirtling Street Complaints & Enquiries Complaints Invalid Complaints Enquiries

33% 67%

Heathwall Pumping Station Complaint & Enquiries Complaints Enquiries

100%

Heathwall Pumping Station Complaints Breakdown Noise

slide-22
SLIDE 22

22

Communications Update Emails and Information Sheets ➢Kirtling Street – Tunnelling 18/01/2019 ➢Heathwall Pumping Station – Change to road layout 03/01/2019 ➢Heathwall Weekly Piling Updates – reduced to weekly now that marine works have completed for the foreseeable future ➢Fortnightly Kirtling Street Updates

slide-23
SLIDE 23

23

Community Engagement

584

STEM hours

648

Contractor Community Investment Programme hours

352

Tideway Community Investment Programme hours

25

Schools

5534

Beneficiaries

Activities round up 2018 – February 2019

slide-24
SLIDE 24

24

Community Engagement 2019

  • Litter Survey and Clean-up in with Thames21 in Battersea
  • SPIRAL Education programme - careers
  • Bounce Back programme to get ex-offenders into work
  • Work Experience for students within the Tideway Central

boroughs

  • Reading Buddies with local Primary School
  • STEM Ambassador Training

If you have any suggestions for community investment, please contact us via the Tideway Helpdesk

slide-25
SLIDE 25

25

COMPENSATION

Louise Walsh – Mitigation and Compensation Lead

slide-26
SLIDE 26

26

Compensation

slide-27
SLIDE 27

27

AOB

slide-28
SLIDE 28

28

THANK YOU Contact details:

  • Helpdesk: 08000 30 80 80
  • helpdesk@tideway.london