1
Tideway Central: Community Liaison Working Group 07/03/19
Heathwall Pumping Station & Kirtling Street
Tideway Central: Community Liaison Working Group 07/03/19 Heathwall - - PowerPoint PPT Presentation
Tideway Central: Community Liaison Working Group 07/03/19 Heathwall Pumping Station & Kirtling Street 1 Agenda Apologies Minutes of last meeting Heathwall site progress and programme Kirtling Street & Brooks Court site
1
Heathwall Pumping Station & Kirtling Street
2
Agenda
3
Landside Works and Marine Works Ponciano ciano Perez ez Lu Lupi pi – Projec
t Manager ager
4
Heathwall Pumping Station overview
5
Heathwall Pumping Station Progress
chamber
6
Heathwall Pumping Station Progress
7
Heathwall lookahead
8
Noel el Cooper per – Tunnel nnel Constru structi ction
Manager ager
9
Progress to date – March 2019
Carnwath Road site) – complete
Chambers Wharf site) Currently progressing with mechanical & electrical connections between TBM shield & gantries
March
10
TBM B (Millicent) Progress
11
Shaft and inside acoustic shed
12
View of segment pontoon & segment barge unloading
13
View of Brooks Court muck-bay
2018 2019 2020 2021 2022 2023
Complete shaft HEAPS Cofferdam structural elements complete Tunnel B excavation Tunnel C excavation Tunnel B secondary lining Tunnel C secondary lining Remove acoustic shed - site reinstatement Reinstate house boats Dynamic testing and opening
Tideway Central Programme
2024
15
Iram Mirza– Environmental Advisor
16
Heathwall Pumping Station - Air Quality Monitor Exceedances
Dec 18 to 1 Mar 19 One FLo works exceedance
for West compound ramp (next to the monitor)
1 x exceedance No exceedances
reporting ceased Feb 19
No exceedances
17
Heathwall Pumping Station - Noise Monitor Exceedances
No exceedances removed Nov 2018
26 Nov 18 to 17 Feb 19
18
Kirtling Street - Air Quality Monitor Exceedances
Dec 18 to 1 Mar 19 None caused by FLo works Two non-FLo AQ exceedances
relocated No FLo exceedances No FLo exceedances
19
Kirtling Street - Noise Monitor Exceedances
26 Nov 18 to 1 Mar 19 One related to FLo works
Hydrocleanse Non-FLo noise exceedances
1 x FLo exceedance
20
Alick Whitfield – Community Relations Manager
21
79% 11% 5% 5%
Kirtling Street Complaints Breakdown Noise Lighting Flooding Other
Complaints & Enquiries Summary December 2018 – February 2019 Kirtling Street and Heathwall Pumping Station
84% 5% 11%
Kirtling Street Complaints & Enquiries Complaints Invalid Complaints Enquiries
33% 67%
Heathwall Pumping Station Complaint & Enquiries Complaints Enquiries
100%
Heathwall Pumping Station Complaints Breakdown Noise
22
Communications Update Emails and Information Sheets ➢Kirtling Street – Tunnelling 18/01/2019 ➢Heathwall Pumping Station – Change to road layout 03/01/2019 ➢Heathwall Weekly Piling Updates – reduced to weekly now that marine works have completed for the foreseeable future ➢Fortnightly Kirtling Street Updates
23
Community Engagement
STEM hours
Contractor Community Investment Programme hours
Tideway Community Investment Programme hours
Schools
Beneficiaries
Activities round up 2018 – February 2019
24
Community Engagement 2019
boroughs
If you have any suggestions for community investment, please contact us via the Tideway Helpdesk
25
Louise Walsh – Mitigation and Compensation Lead
26
Compensation
27
28