Cremorne Wharf Community Liaison Working Group Tuesday 10 th March - - PowerPoint PPT Presentation
Cremorne Wharf Community Liaison Working Group Tuesday 10 th March - - PowerPoint PPT Presentation
Cremorne Wharf Community Liaison Working Group Tuesday 10 th March 2020 1 Agenda Welcome Minutes of previous meeting Cremorne Wharf Site Update Tideway Tunnel Progression Environment Update Community Relations Any Other
2
Agenda
- Welcome
- Minutes of previous meeting
- Cremorne Wharf Site Update
- Tideway Tunnel Progression
- Environment Update
- Community Relations
- Any Other Business
3
Toma ma Schonk
- nker
eren en – Site Agent nt
CREMORNE WHARF SITE UPDATE
WORKS COMPLETED IN LAST PERIOD
Aeration Chamber Ventilation Pipe
- 40.50m length
- Drilled within 1800mm Diameter Bore
- High Density Polyethylene Pipe (HDPE)
- Weight 14 Tonnes
- Externally grouted & filled with sand & water for buoyancy
Piling Works Completed
- CSO Shaft
- 52 No. Secant Piles Installed
- Interception Chamber
- 56 No Secant Piles Installed
- Air Treatment Chamber & Aeration Chamber
- 27 No. Bearing Piles
CHELSEA WHARF MITIGATION WORKS COMPLETED
Chelsea Wharf Works Completed:
- Cintec Anchors Installed connecting Southern Flank
wall to the internal walls
- Helefix Resin Anchors installed across the major
structural cracks
- Pattress Plates installed to the upper floor connecting
the roof trusses to the Southern Flank Wall
- Installation of beams to the Internal Staircase D.
- Removal of redundant ventilation duct on external
façade Before Mitigation Works External Cracks After Completion Mitigation Works Internal Cracks
6
CSO SHAFT CAPPING BEAM WORKS COMPLETED
Secant Pile Excavation CSO Capping Beam Muck away by barge SCL Setup Works Combined Sewer Outfall
7
CREMORNE WHARF SITE PROGRESS SCL WORKS
Testing the material View from 1st Advance Lifting Operations Overhead view of CSO Sprayed Concrete Lining
Air Treatment Chamber Location
Air Treatment Unit
ATU CHAMBER WORKS
CREMORNE WHARF WORKS MAR 20– JUN 20
Upcoming Activities
Connection Tunnel Works CSO Base Slab Construction Interception Chamber Excavation Works
10
13
CREMORNE WHARF DEPOT ENVIRONMENTAL UPDATE
Katy-Leigh Smith – Environmental Lead
14
Cremorne Wharf Depot – Air Quality (December 2019 – February 2020)
Air Quality Monitor CREWD/AA/2 No Exceedances
15
Du Dust Miti itigation Meas asures
16
Crem emorne Wha harf Dep epot t – Noi
- ise (D
(December r 2019 – Feb ebruary 2020) )
Noise Monitor CREWD/NM/3 No Exceedances
17
Cremorne Wharf De Depot – No Nois ise Monit itoring Da Data De December 20 2019 19
18
Cremorne Wharf De Depot – No Nois ise Monit itoring Da Data Jan January 20 2020 20
19
Cremorne Wharf De Depot – No Nois ise Monit itoring Da Data February 20 2019 19
20
24 24/5 /5 workin ing nois
- ise le
levels ls (1 (1st
st – 8th th Mar
arch 20 2020 20)
Noisy works still allocated to during the day – noise levels drop off at night.
21
24 24/5 /5 workin ing nois
- ise le
levels ls (1 (1st
st – 8th th Mar
arch 20 2020 20)
Acoustic Blankets to shield noise emanating from generators.
22
What is is 80 80 dB?
23
Bar arge Movements – Jan January ry 202 2020 – Mar arch 20 2020 20
- Barge movements started 21st January 2020
- Excavated 2,379 tonnes
- Removed 264 movements from the road (based on an average 18 tonne load)
- Approx. 6 movements a day
24
COMMUNITY ENGAGEMENT
ALICK WHITFIELD – COMMUNITY RELATIONS MANAGER CAROLINE BRENNAN – COMMUNITY RELATIONS OFFICER
25
Complaints & Enquiries (January - March 2020)
82% 18%
Cremorne Wharf Depot Complaints & Enquiries January – March 2020
Complaints Enquiries
89% 11%
Cremorne Wharf Depot Complaints Breakdown
Trafffic Management General Site Management
Total - 11 Total - 9
Complaints & Enquiries:
- Lighting
- Vehicle Movements
- Muck Away Wagons
- Abnormal Load Deliveries
- Noise
- Idling Engines
26
Community Engagement - 2020
- Litter Surveys and Clean-up events in Collaboration
with Thames21
- Outreach to schools with local brokerages and through
the council
- EPIC Flashpoint Playcentre
- World’s End Hub
- SPIRAL education outreach programme
If If you have ve any suggestions for community in inve vestment, plea lease contact us via via th the e Tid ideway He Help lpdesk
27
AOB
28
THANK YOU Contact details:
- Information helpline: 08000 30 80 80
- helpdesk@tideway.london