Tideway Central: Community Liaison Working Group 23/10/18 Heathwall - - PowerPoint PPT Presentation

tideway central community liaison working group 23 10 18
SMART_READER_LITE
LIVE PREVIEW

Tideway Central: Community Liaison Working Group 23/10/18 Heathwall - - PowerPoint PPT Presentation

Tideway Central: Community Liaison Working Group 23/10/18 Heathwall Pumping Station & Kirtling Street 1 Agenda Heathwall Site Progress and Programme Kirtling Street Site Progress and Programme Site Air Quality and Noise Data


slide-1
SLIDE 1

1

Tideway Central: Community Liaison Working Group 23/10/18

Heathwall Pumping Station & Kirtling Street

slide-2
SLIDE 2

2

Agenda

  • Heathwall Site Progress and Programme
  • Kirtling Street Site Progress and Programme
  • Site Air Quality and Noise Data – shortened
  • Community Relations
  • Other items / Actions from Last Meeting
  • Notifications
  • Greenwall
  • Window Cleaning
slide-3
SLIDE 3

3

Tideway Central – Project Overview

Justin in Feltham ham – Environment ironmental al Ad Adviser iser

slide-4
SLIDE 4

4

Project Overview

  • Heathwall Pumping Station
  • Existing Combined Sewer Outfall into Thames.
  • Diversion of existing CSO to allow it to operate while we work.
  • Construction of cofferdam and placement of infill material to construct

interception chamber and shaft.

  • Construction of CSO Shaft to connect new Tunnel.
  • Kirtling Street
  • Drive site for construction of tunnel
  • Services and materials for TBM.
  • Removal of excavated material from TBM.
slide-5
SLIDE 5

5

slide-6
SLIDE 6

6

HEATHWALL PUMPING STATION UPDATE

Ponciano ciano Perez ez – Proje ject t Manager ager Landside Works and Marine Works

slide-7
SLIDE 7

7

Heathwall Pumping Station Works

Main Tunnel Existing Pumping Station PS Shaft PS Chamber CSO Shaft Air-Treatment Chamber SWSR Chamber

slide-8
SLIDE 8

8

  • Demolition of existing PS outfall
  • Installation of permanent river wall piles. 39 out of 41 piles installed to
  • date. Remainder to be complete this week
  • Construction of working platform to enable mobilisation of plant for

land piling and shaft construction operations

  • Completion of ventilation diversion
  • Commencement of land piling works for Air Treatment Chamber

bearing piles and SWSR interception chamber secant piles

  • East entrance modification works

Works Complete in previous 4 months

slide-9
SLIDE 9

9

Marine Works – Demolition of Existing PS Outfall

slide-10
SLIDE 10

10

Marine Works – River Wall Installation

slide-11
SLIDE 11

11

Marine Works – River Wall Installation

slide-12
SLIDE 12

12

Landside Works – Land Piling

slide-13
SLIDE 13

13

Heathwall Pumping Station Upcoming Works

  • Remainder of 2018;
  • East & West tie-in works for new river wall
  • Backfill of cofferdam
  • Completion of land piling works for SWSR interception chamber
  • Installation of dewatering structure
  • Early 2019;
  • Highway modification works for CLP3
  • Installation of mooring piles for Battersea barge & campshed
  • Relocation of Battersea barge and construction of campshed
  • Augering of new river walls for installation of reinforcement & concrete
  • Commencement of secant piling for PS interception chamber
  • Commencement of CSO shaft construction
slide-14
SLIDE 14

14

KIRTLING STREET RECENT WORKS

Justin in Feltham ham – Environment ironmental al Ad Adviser iser Noel el Cooper per – Tunnel nnel Senior nior Projec

  • ject

t Manager ager

slide-15
SLIDE 15

15

Kirtling Street Works

slide-16
SLIDE 16

16

Tunnel Boring Machine (TBM) Lowering

slide-17
SLIDE 17

17

Tunnel Boring Machine (TBM) Lowering

slide-18
SLIDE 18

18

TBM in to Adits

slide-19
SLIDE 19

19

TBM in to Adits

slide-20
SLIDE 20

20

TBM in to Adits

slide-21
SLIDE 21

21

TBM in to Adits

slide-22
SLIDE 22

22

Excavate for Shaft Base Slab

slide-23
SLIDE 23

23

Excavate for Shaft Base Slab

slide-24
SLIDE 24

24

Excavate for Shaft Base Slab

slide-25
SLIDE 25

25

Excavate for Shaft Base Slab

slide-26
SLIDE 26

26

Excavated Material Back into Barges

slide-27
SLIDE 27

27

Excavated Material Back into Barges

slide-28
SLIDE 28

28

Excavated Material Back into Barges

slide-29
SLIDE 29

29

Excavated Material Back into Barges Base Slab Excavation: 15,000t Total Excavated from Shaft: 127,000t

slide-30
SLIDE 30

30

Base Slab Pour

slide-31
SLIDE 31

31

Base Slab Pour

slide-32
SLIDE 32

32

Base Slab Pour

slide-33
SLIDE 33

33

Base Slab Pour

slide-34
SLIDE 34

34

Base Slab Pour

slide-35
SLIDE 35

35

Base Slab Pour

slide-36
SLIDE 36

36

Base Slab Pour

slide-37
SLIDE 37

37

Upstand Wall Construction

slide-38
SLIDE 38

38

Upstand Wall Construction

slide-39
SLIDE 39

39

Conveyor System in the Shaft

slide-40
SLIDE 40

40

Shaft Deck

slide-41
SLIDE 41

41

Shaft Deck

slide-42
SLIDE 42

42

Surface Conveyor System

slide-43
SLIDE 43

43

Surface: Water Treatment Plant, Grout Plant, Cooling Water System

slide-44
SLIDE 44

44

Segment Gantry Crane

slide-45
SLIDE 45

45

Burst Thames Water Main

slide-46
SLIDE 46

46

Burst Thames Water Main

slide-47
SLIDE 47

47

Kirtling Street Programme

slide-48
SLIDE 48

48

Kirtling Street Programme

  • October:
  • First segment delivery this week
  • November
  • Launch First TBM
  • February
  • Launch Second TBM
slide-49
SLIDE 49

49

AIR QUALITY

REPORTING

slide-50
SLIDE 50

50

Air Quality Monitor Exceedances

  • Heathwall Monitor Locations
slide-51
SLIDE 51

51

Air Quality Monitor Exceedances - Heathwall

  • June:
  • None
  • July:
  • None
  • August:
  • 09/08/2018 – a couple of exceedances - gritting operations to clear the surface before spraying

concrete; works necessary in stopping tidal water seeping into the site

  • 24/08/2018 and 28/08/2018 – a number of exceedances due to grouting directly underneath the

monitoring for the installation of the wells on the West compound.

  • September
  • 10/09/2018 – an exceedance caused by the proximity of the works to the air quality monitor
  • 20/09/2018 – three exceedances caused by grouting operations taking place directly below

the monitor

  • October
  • 2/10/2018 – an exceedance - our Road sweeper was sweeping up the muck on west

compound which had accumulated around WJ G’s rig

slide-52
SLIDE 52

52

Air Quality Monitor Exceedances

  • Kirtling Monitor Locations
slide-53
SLIDE 53

53

Air Quality Monitor Exceedances - Kirtling

  • June:
  • None
  • July:
  • 5 – attributed to work by Thames Water to repair bust

water main.

  • August:
  • None
  • September:
  • None
  • October:
  • None
slide-54
SLIDE 54

54

NOISE

REPORTING

slide-55
SLIDE 55

55

Noise Monitor Exceedances

  • Heathwall Monitor Locations

Temporary rehousing been

  • ffered

One exceedance No exceedances

slide-56
SLIDE 56

56

Noise Monitoring Exceedances - Heathwall

  • June:
  • None
  • July:
  • None
  • August:
  • None
  • September
  • 09/09/2018 - one exceedance - due to saw cutting in close proximity

underneath the monitor

  • October:
  • None
slide-57
SLIDE 57

57

Noise Monitoring Exceedances

  • Kirtling Monitor Locations
slide-58
SLIDE 58

58

Noise Monitoring Exceedances - Kirtling

  • June:
  • None
  • July:
  • 4 – due to works by Thames Water to repair bust water main.
  • August:
  • None
  • September
  • 08/09/18 – Concrete pour in close proximity to the meter, The pour did

not trigger the exceedance but the demobilisation continued after 13:00, into a period with a lower limit, and caused the alert.

  • October:
  • None
slide-59
SLIDE 59

59

COMMUNITY ENGAGEMENT

ALICK WHITFIELD – COMMUNITY RELATIONS MANAGER

slide-60
SLIDE 60

60

Issues

Complaints & Enquiries register July – October 2018 Kirtling Street

Complaints & Enquiries

Complaints Invalid Complaints Enquiries

slide-61
SLIDE 61

61

Issues

Complaints & Enquiries register July – October 2018 Heathwall Pumping Station

Complaint & Enquiries

Complaints Enquiries

slide-62
SLIDE 62

62

Update

Communications

  • Emails and Information Sheets:
  • Kirtling Street - Gantry Crane installation 18/10
  • Heathwall Pumping Station – Landside works 13/09
  • Heathwall Pumping Station – Marine works 03/08
  • Kirtling Street – Base Slab Pour 17/07
  • Kirtling Street – Telestacker 19/04
slide-63
SLIDE 63

63

Community Engagement

236

STEM hours

394

Contractor Community Investment Programme hours

160

Tideway Community Investment Programme hours

23

Schools

1343

Beneficiaries

Activities Round Up June – October 2018

slide-64
SLIDE 64

64

Community Engagement - Ongoing

  • Litter Survey and Clean-up in with Thames21 in

Battersea

  • SPIRAL Education programme - careers
  • Boat trip with students from 5 Wandsworth schools
  • R.O.S.E Clubroom ongoing discussions regarding

improvements and volunteering events

  • Bounce Back programme to get ex-offenders into work
  • On-going work placement candidate from PIP (Pursuing

Independent Paths), working with adults with learning difficulties

  • Work Experience for students within the Tideway Central

boroughs

slide-65
SLIDE 65

65

Community Investment

  • Series of foreshore clean-ups in Battersea

with Thames21

  • Donation of flowers and plants from

Hampton Court Flower Show to R.O.S.E Clubroom and Savona Estate; Falconbrook Primary School and World’s End Community Centre

  • Supporting 9/11 Memorial Day at R.O.S.E

Clubroom with volunteers and materials

  • Ongoing school workshops trialling the

Virtual Reality TBM

  • Supporting the Foreshore Festival with

Thames21 and London ZSL

  • Work experience and placements for local

students and unemployed candidates

slide-66
SLIDE 66

66

UPCOMING ACTIVITIES

  • October half-term work experience placements October
  • Boat Trip for 5 schools based in Wandsworth
  • Science Museum Lates event
  • Future Festival – Careers event in Lambeth school
  • If you have any suggestions for community investment, please contact

us via the Tideway Helpdesk

slide-67
SLIDE 67

67

Community Survey

  • 14,748 surveys sent out with summer issue of River Times
  • 1 response received
  • As a result we will be reviewing the need for future surveys and the

best way to obtain feedback from residents and stakeholders.

slide-68
SLIDE 68

68

Other Items

Justin Feltham – Environmental Advisor

slide-69
SLIDE 69

69

Greenwall

  • Greenwall
  • Start date 29/10/18
slide-70
SLIDE 70

70

COMPENSATION

LOUISE DAVIS

slide-71
SLIDE 71

71

QUESTIONS?

slide-72
SLIDE 72

72

THANK YOU Contact details:

  • Information helpline: 08000 30 80 80
  • helpdesk@tideway.london