terminal 5 modernization program briefing
play

Terminal 5 Modernization Program Briefing Presenter: Anne Porter - PowerPoint PPT Presentation

Item No.: 4A -supp Date of Meeting: February 5, 2019 Terminal 5 Modernization Program Briefing Presenter: Anne Porter Title: POS Capital Program Leader Terminal 5 Schedule and Phasing 2019 2020 2021 2022 2023 Begin North Begin Two


  1. Item No.: 4A -supp Date of Meeting: February 5, 2019 Terminal 5 Modernization Program Briefing Presenter: Anne Porter Title: POS Capital Program Leader

  2. Terminal 5 – Schedule and Phasing 2019 2020 2021 2022 2023 Begin North Begin Two Berth Operations Berth Operations Berth Modernization Project CONSTRUCTION CONSTRUCTION PRE- PROJECT TRANSITION PHASE 1 PHASE 2 COMPLETION CONSTRUCTION Uplands Improvement Project DESIGN/PERMIT PHASED CONSTRUCTION In-water work windows Schedule and phasing over next 4 years 3

  3. Terminal 5 – Current Status • Berth Modernization construction ready to advertise • Pre-solicitation complete • Environmental reviews and permit approvals complete • Construction schedule phased over next 4 years • Uplands Improvement Project • Design & permitting 2019 • Construction 2020-2023 • Estimated Program costs $340 million including • Management reserve $20 million • Stormwater reserve $30 million Status of program execution 4

  4. Terminal 5 – Permit Conditions • Air Quality • Implement Air Quality Management Plan • Monitor PM 2.5 to confirm operations meet modeled assumptions < 6 tons/year • Noise • Implement Operations Noise Management Plan • All mobile cargo handling equipment uses broadband safety alarms • Railroad Quiet zone • Traffic • Implement Gate Queue Management Plan • Avoid backups past intersection of SW Spokane St and access bridge • Roadway and signalization improvements • Stormwater • Treatment system design is informed by future use • Tenant holds ISGP (Industrial Stormwater General Permit) • Best management practices and benchmark sampling Key elements of permit conditions 5

  5. Next Steps Returning on 2/26 to request Managing Members of the Northwest Seaport Alliance (NWSA) authorization for program funding and construction authorization 6

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.