CAC Temporary Terminal Presentation Terminal Presentation July 13, - - PowerPoint PPT Presentation

cac temporary terminal presentation terminal presentation
SMART_READER_LITE
LIVE PREVIEW

CAC Temporary Terminal Presentation Terminal Presentation July 13, - - PowerPoint PPT Presentation

CAC Temporary Terminal Presentation Terminal Presentation July 13, 2010 July 13, 2010 Program Status Program Status Finalizing Temporary Terminal construction Striping and traffic changes in progress p g g p g SFMTA and


slide-1
SLIDE 1

CAC Temporary Terminal Presentation

July 13, 2010

Terminal Presentation

July 13, 2010

slide-2
SLIDE 2

Program Status Program Status

  • Finalizing Temporary Terminal construction
  • Striping and traffic changes in progress

p g g p g

  • SFMTA and other operators move to Temporary

Terminal on August 7th Terminal on August 7

  • Demolition of existing ramps and Terminal begin
  • n August 14th
  • n August 14th
  • Seven year schedule for construction of the new

T it C t Transit Center

slide-3
SLIDE 3

Temporary Terminal Access

slide-4
SLIDE 4

Temporary Terminal

slide-5
SLIDE 5

38 38L

41

38 38L

108

71

5

Phase 1 Temporary

71 71L 82X

Temporary Terminal Operation Operation August to August to November 2010

slide-6
SLIDE 6

Temporary Terminal

slide-7
SLIDE 7

Phase 2 Temporary Temporary Terminal Operation Operation

slide-8
SLIDE 8

Key Outreach Dates Key Outreach Dates

  • Install banners & re-launch website

July 1st y

  • Handouts available at Terminal

July 7th L h b d J l 20th

  • Launch ambassador program

July 20th

  • Commemoration Event

July 30th

  • Open House at Temporary Terminal

August 3rd

  • Begin Operations at Temporary Terminal

August 7th Begin Operations at Temporary Terminal August 7 T it C t G db ki E t A t 11th

  • Transit Center Groundbreaking Event

August 11th

slide-9
SLIDE 9

Outreach Signage

slide-10
SLIDE 10

Signage

slide-11
SLIDE 11

Wayfinding Signage Wayfinding Signage

slide-12
SLIDE 12

Signage

slide-13
SLIDE 13

Questions?