schedule presentation to the cac to the cac
play

Schedule Presentation to the CAC to the CAC July 13, 2010 July - PowerPoint PPT Presentation

Schedule Presentation to the CAC to the CAC July 13, 2010 July 13, 2010 Construction Duration Construction Duration Begin Operations Vacate in TTC Existing Terminal August 2017 August 2010 Construction Duration 7y Critical Demolition


  1. Schedule Presentation to the CAC to the CAC July 13, 2010 July 13, 2010

  2. Construction Duration Construction Duration Begin Operations Vacate in TTC Existing Terminal August 2017 August 2010 Construction Duration  7y Critical Demolition (thru Zone 4)  7mo Substantial Completion March 2011 - Start Shoring Wall August 2017 Final Completion November 2017

  3. Schedule Impacts Schedule Impacts ― Buttress Scope and Duration Buttress Scope and Duration

  4. Schedule Impacts Schedule Impacts ― Remove Existing Piles and Pile Caps Remove Existing Piles and Pile Caps

  5. Schedule Impacts Schedule Impacts ― Refined Construction Sequencing Refined Construction Sequencing

  6. Schedule Impacts Schedule Impacts ― Refined Construction Sequencing Refined Construction Sequencing

  7. Schedule Impacts Schedule Impacts ― Refined Construction Sequencing Refined Construction Sequencing

  8. Phase 1 Program Summary Schedule S mmar Sched le 2010 2011 2012 2013 2014 2015 2016 2017 Transit Center Final Design Temporary Terminal Construction - Phase 1 Begin Bus Operation in Temporary Terminal Temporary Terminal Construction - Phase 2 Bus Storage Facility - Design Bus Storage Facility - Construction Utility Relocation - Design Utility Relocation - Construction y Demolition of Existing Terminal Demolition of Existing Ramps Transit Center Foundation/Train Box Construction Transit Center Superstructure Construction T it C t S t t C t ti Transit Center Interior Construction Transit Center Exterior Enclosures Site Civil Construction Bus Ramps - Design Bus Ramps - Construction Begin Bus Operations in New Terminal

  9. Phase I Milestones Vacate Terminal/Begin Demolition Vacate Terminal/Begin Demolition August 2010 August 2010 Begin Shoring Wall Construction March 2011 Complete Excavation July 2013 Complete Below-Grade Construction p June 2014 Complete Construction of Bus Ramps October 2014 Complete Superstructure Construction C l t S t t C t ti A August 2015 t 2015 Complete Rooftop Park October 2016 Begin Bus Operations August 2017

  10. Phase 1 Program Critical Path g 2009 2010 2011 2012 2013 2014 2015 2016 2017 Early Utility Relocation - First, Natoma & Fremont St Shoring - Zone 1 g Shoring - Zone 2 Excavation - Zone 2 Below Grade Train Box - Zone 2 Below Grade Concourse - Zone 2 Above Grade Structure - Central Zone Above Grade Structure - East Zone Above Grade Structure East Zone Rough Interiors - Bus Deck Level, East Zone Exterior Enclosures - Bus Deck and Awning, East Site Civil Work Site Civil Work Commisioning and Project Weather Allowance

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend