Swansfield Elementary School Additions and Renovations Schematic Design Report Scott Washington Director, School Construction February 26, 2015 Project Overview A classroom addition that will Increase the capacity by 100 seats


slide-1
SLIDE 1

Swansfield Elementary School Additions and Renovations

Schematic Design Report

Scott Washington Director, School Construction February 26, 2015

slide-2
SLIDE 2

Project Overview

  • A classroom addition that will

– Increase the capacity by 100 seats – Eliminate 4 portable classrooms – House the related art areas and support

spaces

  • A complete systemic renovation of the existing

building, including new mechanical, electrical and IT systems

  • Grade cluster teaching stations reconfigured

into self-contained classrooms

slide-3
SLIDE 3

Project Overview (con’t)

  • Construction of additions for an administrative

area providing improved security and a COMAR compliant health suite

  • Interior spaces reconfigured to increase the

standard classroom size, given new finishes, and provide improved accessibility and circulation

  • Inclusion of a second pre-k classroom to

address the growing need and all day pre-k

  • Another LEED ‘Certified’ project
slide-4
SLIDE 4

S wansfield Elementary School

slide-5
SLIDE 5

S wansfield Elementary School

slide-6
SLIDE 6

S wansfield Elementary School (Existing Floor Plan)

slide-7
SLIDE 7

S wansfield Elementary School (Proposed Floor Plan)

slide-8
SLIDE 8

S wansfield Elementary School (Admin Office and Health Suite)

slide-9
SLIDE 9

S wansfield Elementary School (Classroom Addition)

slide-10
SLIDE 10

Summary

  • Schedule

– Design Development (DD) report June 2015 – Construction Documents (CD) report November 2015 – Receive bids February 2016 – Construction starts April 2016 – Completion December 2017

  • Request approval to move into DD phase